Royal Life Insurance Ltd v Secretary of State for the Environment and another
Compulsory purchase — Confirmation of compulsory purchase order — Whether the Secretary of State failed properly or at all to address a question of the viability of the scheme underlying the compulsory purchase identified by inspector — Whether second respondent acquiring authority entitled to costs
Pursuant to
section 142 of the Local Government, Planning and Land Act 1980 the second
respondents, Bristol Development Corporation, made a compulsory purchase order
in respect of 11.5 ha of land in the Bristol urban development area — The order
land included 4 ha belonging to the applicant — At an inquiry held by an
inspector appointed by the first respondent, the Secretary of State for the
Environment, the applicant argued that the development proposed by the second
respondents was based on an unrealistic assessment of office-floorspace
take-up, was not financially viable in itself and in consequence of that
non-viability was positively detrimental to the aim of regeneration of the
development area — The second respondents had called evidence showing that it
was neither relevant nor appropriate for detailed evidence on viability to be
put forward at the inquiry because of the prematurity of detailed assessment, the
confidentiality of the order land’s valuation and the sensitivity of continuing
negotiations with potential development partners — In concluding that the
proposals were soundly based, the inspector in his report made the caveat that
the second respondents had not demonstrated their viability, but he accepted
that a responsible body would not pursue a proposal unless the viability had
been demonstrated to their satisfaction — In seeking to quash the confirmed
compulsory purchase order under section 23 of the Acquisition of Land Act 1981,
it was contended for the applicant that the first respondent did not have
evidence before him and failed to properly or at all address the question of
viability raised by the caveat in the inspector’s report and that an order
should only be confirmed if the public interest decisively so demands
Held: The application was dismissed — Although the applicant’s evidence
related to part of the scheme, the inspector had evidence before him relating
to the whole scheme — Financial viability is only one of many factors,
including the merits of rival schemes, when considering whether regeneration is
on balance more likely to be achieved by the compulsory purchase — The
inspector’s process of reasoning, that despite the caveat the scheme was
soundly based, was unimpeached — The first respondent discharged his task of
seeing that the second respondents acted responsibly and in the public
interest; he was under no obligation to analyse viability and therefore did not
wrongly delegate that analysis to the second respondents
Compulsory purchase — Confirmation of compulsory purchase order — Whether the Secretary of State failed properly or at all to address a question of the viability of the scheme underlying the compulsory purchase identified by inspector — Whether second respondent acquiring authority entitled to costs
Pursuant to
section 142 of the Local Government, Planning and Land Act 1980 the second
respondents, Bristol Development Corporation, made a compulsory purchase order
in respect of 11.5 ha of land in the Bristol urban development area — The order
land included 4 ha belonging to the applicant — At an inquiry held by an
inspector appointed by the first respondent, the Secretary of State for the
Environment, the applicant argued that the development proposed by the second
respondents was based on an unrealistic assessment of office-floorspace
take-up, was not financially viable in itself and in consequence of that
non-viability was positively detrimental to the aim of regeneration of the
development area — The second respondents had called evidence showing that it
was neither relevant nor appropriate for detailed evidence on viability to be
put forward at the inquiry because of the prematurity of detailed assessment, the
confidentiality of the order land’s valuation and the sensitivity of continuing
negotiations with potential development partners — In concluding that the
proposals were soundly based, the inspector in his report made the caveat that
the second respondents had not demonstrated their viability, but he accepted
that a responsible body would not pursue a proposal unless the viability had
been demonstrated to their satisfaction — In seeking to quash the confirmed
compulsory purchase order under section 23 of the Acquisition of Land Act 1981,
it was contended for the applicant that the first respondent did not have
evidence before him and failed to properly or at all address the question of
viability raised by the caveat in the inspector’s report and that an order
should only be confirmed if the public interest decisively so demands
Held: The application was dismissed — Although the applicant’s evidence
related to part of the scheme, the inspector had evidence before him relating
to the whole scheme — Financial viability is only one of many factors,
including the merits of rival schemes, when considering whether regeneration is
on balance more likely to be achieved by the compulsory purchase — The
inspector’s process of reasoning, that despite the caveat the scheme was
soundly based, was unimpeached — The first respondent discharged his task of
seeing that the second respondents acted responsibly and in the public
interest; he was under no obligation to analyse viability and therefore did not
wrongly delegate that analysis to the second respondents
The following
cases are referred to in this report.
Ashbridge
Investments Ltd v Minister of Housing and Local
Government [1965] 1 WLR 1320; [1965] 3 All ER 371; (1965) 63 LGR 400;
[1965] EGD 216; 195 EG 205, CA
de
Rothschild v Secretary of State for Transport (1988)
57 P&CR 330; [1989] 1 EGLR 19; [1989] 06 EG 123, CA
Green v Secretaries of State for the Environment and Transport (1984)
271 EG 550, [1984] 2 EGLR 27
Leser
Landau v Secretary of State for the Environment Unreported,
June 4 1991
Migdal
Investments Ltd v Secretary of State for the
Environment [1976] EGD 112; (1976) 240 EG 793, [1976] 2 EGLR 15
Prest v Secretary of State for Wales (1982) 81 LGR 193; [1983] EGD
282; 266 EG 527, [1983] 1 EGLR 17, CA
Sovmots
Investments Ltd v Secretary of State for the
Environment [1977] QB 411; [1976] 3 WLR 597; [1976] 3 All ER 720; (1976) 74
LGR 556, CA
This was an
application by Royal Life Insurance Ltd under section 23 of the Acquisition of
Land Act 1981 to quash part of the Bristol Development Corporation (Temple
Meads/Kingsley Village Part I) Compulsory Purchase Order 1990 made by the
second respondents, Bristol Development Corporation, and confirmed by the first
respondent, the Secretary of State for the Environment.
Brian Ash QC
and Paul Stinchcombe (instructed by Linklaters & Paines) appeared for the
applicant; Robert Carnwath QC and Alun Alesbury (instructed by the Treasury
Solicitor) represented the first respondent; John Taylor QC and Robert Fookes
(instructed by Lawrence Tucketts, of Bristol) represented the second
defendants.
Giving
judgment, ROSE J said: By its amended notice of motion the applicant
seeks under section 23 of the Acquisition of Land Act 1981 the quashing of that
part of the Bristol Development Corporation (Temple Meads/Kingsley Village Part
I) Compulsory Purchase Order 1990 which relates to land which it owns, namely
plots 10 and 11 of the order lands.
The essence of
the challenge can be shortly stated. Mr Ash QC, for the applicant, submits that
the first respondent failed properly, or at all, to address the question of
viability raised by way of way of caveat in his inspector’s report.
The background
is as follows. The second respondents, Bristol Development Corporation, are a
statutory body established under section 136 of the Local Government Planning
and Land Act 1980 to secure regeneration of the Bristol urban development area.
Pursuant to section 142 of the 1980 Act and Parts I and II of the Acquisition
of Land Act, the second respondents made the compulsory purchase order in
respect of 11.5 ha of land in the Bristol urban development area south-east of
the city centre.
The applicant’s
land, plots 10 and 11, is shown on the plan to the south-west of the floating
harbour and it amounts to some 4 ha (that is about one-third of the total order
lands). Statutory objections to the compulsory purchase order were made by the
applicant and others and these were considered by an inspector appointed by the
first respondent at a local planning inquiry held between the end of January
and March 20 1991. The inspector reported to the first respondent in July 1991.
The first respondent confirmed the compulsory purchase order by letter dated
January 28 1992. A notice of confirmation of the compulsory purchase order was
published on February 12 1992. The order lands are the first land to be the
subject of phased development by the second respondent in their intended
regeneration of the Bristol urban development area, which involves the
provision of, among other things, 93,000 msu2 of office space and further areas
amounting to over 30,000 msu2 of space devoted to other commercial, cultural
and residential uses.
At the local
inquiry the applicant argued that the development intended by the second
respondents was based on an unrealistic assessment of office-floorspace
take-up, was not financially viable in itself and in consequence of that
non-viability was positively detrimental to the aim of regeneration.
The applicant,
together with Temple Mead Development Ltd, called expert evidence in support of
the viability objection based on studies by two chartered surveyors, Mr Gary
Halman [ARICS] and Mr Peter Benjamin [FRICS]. In his proof of evidence Mr
Benjamin concluded that the second respondents’ scheme would make a loss of
£45m and was non-viable. The second respondents’ case on viability was that
this was a judgmental matter not capable of proof and that it was neither
relevant nor appropriate for detailed evidence on viability to be put forward
at the inquiry because of the prematurity of detailed assessment, the
confidentiality of order lands’ valuation and the sensitivity of continuing
negotiations with potential development partners.
Mr Brian
Raggett [ARICS], a partner in Hillier Parker, gave expert evidence along these
lines and in relation to other matters on behalf of the second respondents. He
had been appointed in February 1990 and had rigorously appraised the evolving
proposals that eventually formed phase 1.
In the light
of his expertise and evidence the second respondents were fully satisfied that
a viable scheme had been devised. The inspector’s report fully sets out the
evidence which he heard and the competing contentions advanced in argument
before him. His findings of fact with regard to viability are as follows:
34. The
Framework proposals have been tested for financial viability, but because of
the need for commercial confidentiality BDC are unwilling to release the
figures.
35. BDC
dispute the statements by TMDL and Royal Insurance that the Framework proposals
are not viable.
36. BDC are
in discussion with 3 potential development partners about implementation of the
Framework.
37. Royal
Insurance contend that the Framework proposals are financially unviable to the
extent of some £45m for that part of the Order Lands south of the Floating
Harbour.
38. TMDL
contend that Framework proposals are financially unviable to the extent of £38m
for that part of the Order Lands south of the Floating Harbour.
Before turning
to the inspector’s conclusions, it is convenient to set out the relevant
statutory provisions in relation to the second respondents and the material
parts of Circular 23/88 — Compulsory Purchase Orders by Urban Development
Corporations — to which the inspector referred in some detail. Section
136(1) of the Local Government, Planning and Land Act 1980 provides:
(1) The object of an urban development
corporation shall be to secure the regeneration of its area.
(2) The object is to be achieved in particular by
the following means (or by such of them as seem to the corporation to be
appropriate in the case of its area), namely, by bringing land and buildings
into effective use, encouraging the development of existing and new industry
and commerce, creating an attractive environment and ensuring that housing and
social facilities are available to encourage people to live and work in the
area.
Section 142(1)
provides:
An urban
development corporation may acquire (by agreement or, on being authorised to do
so by the Secretary of State, compulsorily) —
(a) land in the urban development area;
(b) land adjacent to the area which the corporation
requires for purposes connected with the discharge of the corporation’s
functions in the area;
(c) land, whether or not in or adjacent to the
area, which the corporation requires for the provision of services in
connection with the discharge of the corporation’s functions in the area.
Circular 23/88
relates to compulsory purchase orders by urban development corporations. Para 1
states:
It is
intended that in general the procedural guidance set out in DOE Circular 6/85
should apply to section 142 orders.
Para 5 says:
UDC’s
compulsory purchase powers are expressed in wide and general terms, reflecting
both the national importance of the task of urban regeneration and the
practical problems of ensuring that wide areas of severe urban dereliction can
be speedily returned to beneficial use.
Para 6 I shall
read in full:
In reaching a
decision on whether to confirm a section 142 order, the Secretary of State will
have in mind the statutory objectives of the UDC and will, inter alia,
wish to consider:
(i) whether the UDC has demonstrated that the
land is in need of regeneration;
(ii) what alternative proposals (if any) have been
put forward by the owners of the land or other persons for regeneration;
(iii) whether regeneration is on balance more
likely to be achieved if the land is acquired by the UDC;
(iv) the recent history and state of the land;
(v) whether the land is in an area for which the
UDC has a comprehensive regeneration scheme;
(vi) the quality and timescale of both the UDC’s
regenerations proposals and any alternative proposals.
Para 7 states:
The Secretary
of State recognises that in the special circumstances in which UDCs operate,
and given their specific duty to regenerate their areas, it will not always be
possible or desirable for them to have specific proposals for the land concerned
beyond their general framework for the regeneration of the area, and that
therefore the detailed land use planning and other factors will not necessarily
have been resolved before making a CPO.
Para 11 says:
Where a UDC
does not advance detailed proposals for redevelopment, the Secretary of State
will, however, expect the Corporation to have prepared a broad framework for
regeneration of the area. This should be summarised in the statement of reasons
which the Corporation is required to include in its order submission. UDC’s
will be expected to demonstrate the case for acquisition in the context of
their development strategy, and present the relevant evidence at a public
inquiry where appropriate.
It is to be
noted that neither the statute nor the circular refers to viability.
The inspector
concludes that the need for regeneration has been demonstrated and that the
second respondents clearly have a comprehensive regeneration scheme for the
order lands and beyond. He goes on to consider factors (ii), (iii) and (vi) of
para 6 of the circular. In relation to the objector’s alternative proposals he
says at para 24.5:
I believe
that such a pattern of redevelopment would be physically possible, and I see no
reason to doubt that it would be commercially viable.
His
conclusions as to the viability of the second respondents’ proposals appear at
paras 24.8, 24.9 and 24.10, which I shall read in full:
24.8 The Development Corporation’s argument that
viability goes to implementation not acquisition is not one that I can wholly
accept. It is clear that consideration needs to be given to the balance of
advantage of Development Corporation’s proposals as against alternative
proposals in achieving regeneration of the Order Lands. This necessitates some
consideration of viability, since that which is not viable is unlikely to be
implemented and hence cannot achieve regeneration.
24.9 The Development Corporation repeatedly
asserted that the Framework proposals had been rigorously tested for viability
and been found satisfactory. However they declined for reasons of commercial
confidentiality to produce any figures. No development partner currently exists
to implement their proposals, although discussions were stated to be
proceeding. By contrast, both Royal and TMDL produced some figures to support
their views that the proposals were not viable. However, neither had carried
out a full study of the proposals as currently existing, although both stated
that nothing that had become known during the course of the inquiry would cause
them to radically revise their assessment.
24.10 I am, therefore, obliged to record that the
Development Corporation did not demonstrate the viability of their proposals,
although they asserted it repeatedly and with some force. In the final
analysis, I can do no other than accept that, as a responsible public body, the
Development Corporation would not pursue a proposal the viability of which had
not been demonstrated to their satisfaction. Certainly, they have sought the
advice of reputable and experienced consultants in this field, who appeared at
the inquiry to give evidence on their behalf. I cannot, however, reach a more
positive conclusion on this point.
The
inspector’s overall conclusion appears at para 24.26. It is:
Having
considered these and all other aspects I see no reason to doubt that the
Framework proposals are soundly based and will lead to regeneration of the
Order Lands. The only caveat I find it necessary to make is in respect of
financial viability (see 24.10 above).
As to the
alternative proposals the inspector says:
24.34 . . . In my judgment what would result on the
Triangle site would be a series of disjointed and poorly related developments
that would fail to achieve the potential of this important site, to provide
satisfactory pedestrian routes from the station to the city centre, and to open
up the Floating Harbour to public use. Such a proposal would achieve
redevelopment, in the sense of putting buildings on land, but would not
constitute regeneration in the wider sense. Certainly it would not constitute
‘something splendid’, and I have some hopes that the Framework proposals, as
realised, might just achieve that end.
24.35 Regeneration beyond the Order Lands would be
unlikely to occur as a result of the alternative proposals.
24.36 I must now deal with Great Western Way
— that relates
to plot 11 —
Its retention
is, I consider, one of the main reasons why TMDL’s illustrative proposals are
unsatisfactory. For example, it frustrates attempts to bring the Floating
Harbour and the station buildings into a mutually beneficial relationship with
the Triangle site. I must conclude that if the regeneration of the Order Lands
is to be fully achieved, then Great Western Way must go.
24.38 I conclude, therefore, that the Development
Framework proposals would secure regeneration of the Order Lands, and that the
alternative proposals are materially unsatisfactory for the reasons I have
given. 24.39 Having regard to all these matters and to the reasons for the
setting up of an Urban Development in the first instance, I conclude that a
compelling case in the public interest has been made for confirmation of the
Compulsory Purchase Order, with one exception.
The inspector
goes on to deal with the exception which is immaterial for present purposes and
his recommendation at para 25.40 is:
I recommend
that the Bristol Development Corporation (Temple Meads/Kingsley Village part 1)
Compulsory Purchase Order 1990 be confirmed
— subject to
the exception to which I have referred.
The crucial
part of the first respondent’s decision letter is para 6, which reads as
follows:
After careful
consideration of all the material before him, the Secretary of State accepts
the Inspector’s findings of fact and wholly agrees with his conclusions and
recommendation. In considering this Order the Secretary of State has had regard
to the advice contained in DOE Circular 23/88 and in particular to the
considerations set out in paragraph 6(i) to 6(vi) of that Circular. He is
satisfied that with the exception of Plot 24, the land included in the modified
Order is required so that the regeneration of the Order land may be secured. He
accepts that the alternative proposals for redevelopment of the Order lands
summarised in paragraph 24.4 of the Inspector’s report would be feasible,
commercially viable and, in part, capable of early implementation. However, he
agrees with the Inspector’s conclusion that the alternative redevelopment
proposals would not achieve the comprehensive regeneration envisaged by the
Development Framework adopted by the Development Corporation in accordance with
its objective to secure the regeneration of its area. The Secretary of State is
further satisfied that the Development Corporation have demonstrated that they
are, so far as is practicable, taking steps to assist in the relocation of
persons and businesses whose interests would be required as a result of the
Order. The Secretary of State has accordingly decided to confirm the order
subject to the modifications shown on it . . .
Mr Ash QC, on
behalf of the applicant, submits, and indeed it is common ground, that the
compulsory purchase order can be quashed if the Secretary of State, in the
words of Lord Denning in Ashbridge Investments Ltd v Minister of
Housing and Local Government [1965] 1 WLR 1320 at p 1326F:
. . . has
acted on no evidence; or if he has come to a conclusion to which on the
evidence he could not reasonably come; or if he has given a wrong
interpretation to the words of the statute; or if he has taken into consideration
matters which he ought not to have taken into account, or vice versa; or has
otherwise gone wrong in law.
Mr Ash also
relies on passages in the judgments of Lord Denning and Watkins LJ in Prest v
Secretary of State for Wales (1982) 81 LGR 193*. At p 198 Lord Denning
said:
I regard it
as a principle of our constitutional law that no citizen is to be deprived of
his land by any public authority against his will, unless it is expressly
authorised by Parliament and the public interest decisively so demands: and
then only on the condition that proper compensation is paid: see Attorney-General
v De Keyser’s Royal Hotel Ltd [1920] AC 508. If there is any
reasonable doubt on the matter, the balance must be resolved in the favour of
the citizen. This principle was well applied by Forbes J in Brown v Secretary
of State for the Environment (1978) 40 P&CR 285, where there were
alternative sites available to the local authority, including one owned by
them.
He said, at p
291:
‘It seems to
me that there is a very long and respectable tradition for the view that an
authority that seeks to dispossess a citizen of this land must do so by showing
that it is necessary . . .’
*Editor’s
note: Also reported at [1982] 266 EG 527, [1983] 1 EGLR 17.
At p 211
Watkins LJ said:
In the sphere
of compulsory land acquisition, the onus of showing that a compulsory purchase
order has been properly confirmed rests squarely on the acquiring authority
and, if he seeks to support his own decision, on the Secretary of State. The
taking of a person’s land against his will is a serious invasion of his
proprietary rights. The use of statutory authority for the destruction of those
rights requires to be most carefully scrutinised.
The Court of
Appeal’s decision in de Rothschild v Secretary of State for Transport
(1988) 57 P&CR 330† Mr Ash
describes as ‘the low point’ of the court’s approach to compulsory purchase
orders. In that case the Court of Appeal rejected the submission made by Mr Ash
and his then leader that special rules apply to challenges to compulsory
purchase orders. Slade LJ, in a judgment with which the other members of the
court agreed, at p 336 said:
Having
considered the judgments of this court in Prest and of Forbes J in Brown,
I conclude that both of them were merely examples of challenges to the
Secretary of State’s decision on conventional Wednesbury/Ashbridge grounds.
Though all the judgments in Prest contained observations regarding onus,
I, for my part, read them as doing no more than giving a warning that in cases
where a compulsory purchase order is under challenge, the draconian nature of
the order will itself render it more vulnerable to successful challenge on Wednesbury/Ashbridge
grounds unless sufficient reasons are adduced affirmatively to justify it
on its merits.
† Editor’s
note: Also reported at [1989] 1 EGLR 19.
On p 337 Slade
LJ said:
First, I do
not accept that any special rules beyond the ordinary Wednesbury/Ashbridge rules
fall to be applied when the court is considering a challenge to the Secretary
of State’s confirmation of a compulsory purchase order. Secondly, however, the
Secretary of State, as Mr Laws on his behalf accepted and submitted, must be
satisfied that the compulsory purchase order is justified on its merits before
he can properly confirm it. He must not exercise his powers capriciously. Given
the obvious importance and value to land owners of their property rights, the
abrogation of those rights in the exercise of his discretionary power to
confirm a compulsory purchase order would, in the absence of what he perceived
to be a sufficient justification on the merits, be a course which surely no
reasonable Secretary of State would take.
I think that
this approach to the matter reconciles the judgments in Prest with the
ordinary principles of our law applicable to claims for judicial review.
Furthermore, it has the merit of avoiding any reference to onus of proof, which
is an expression more appropriate, as Mr Laws pointed out, to a lis inter
partes.
Mr Ash accepts
in the light of that decision that no special rules apply, but he submits that
a special approach is appropriate to a compulsory purchase order in that it
should only be confirmed if the public interest decisively so demands and that
is a phrase which appears in the judgment of Slade LJ at p 343. It is not in
issue before me that I must be guided by the Court of Appeal’s approach in de
Rothschild.
From this
standpoint Mr Ash submits, first, that the Secretary of State failed to
consider the applicant’s principal objection, namely that the second
respondent’s proposals were not commercially viable and therefore not likely to
cause regeneration. The inspector at para 24.8 recognised ‘that which is not
viable is unlikely to be implemented and hence cannot achieve regeneration’,
and the caveat which he entered at 24.26 should, submits Mr Ash, have
caused the first respondent to examine viability. There was, submits Mr Ash,
assertion by the second respondent but no evidence on which the Secretary of
State could reasonably conclude that the second respondents’ scheme was viable.
Therefore, whether the matter is considered ‘on the merits’ in accordance with de
Rothschild, or on the basis that the public interest ‘decisively demands’
compulsory purchase in accordance with Prest and de Rothschild there
is no proper basis on which the Secretary of State could confirm the order.
The inspector
failed to make any finding as to the viability of the second respondents’
proposals and concluded merely that viability was shown to the second
respondents’ satisfaction. The inspector, submits Mr Ash, was by his caveat recommending
confirmation, provided the Secretary of State was satisfied as to viability and
it was not possible for the Secretary of State to accept the inspector’s
recommendation without first concluding that the scheme was viable.
Mr Ash further
submits that it was not open to the first respondent to delegate assessment of
viability to the second respondents, which is the effect of his decision. Mr
Ash relies on a passage at p 357 of Wade’s Administrative Law 6th ed. It
is indeed common ground that a power could only lawfully be exercised by the
authority on whom it is conferred. Mr Ash accepts that the reasons ground
advanced in the notice of motion adds nothing material to his argument.
For the first
respondent, Mr Carnwath submits, as to no evidence, in reliance on Migdal
Investments Ltd v Secretary of State for the Environment (1976) 240
EG 793, [1976] 2 EGLR 15 that ‘no evidence’ means ‘no evidence’. Here Mr
Raggett’s expert evidence for the second respondents was before the inspector.
It was not the ipse dixit of the second respondents themselves and the
inspector was entitled to rely on it. Mr Benjamin’s evidence on behalf of the
applicant is open to criticism: first, that it dealt with only part of the
scheme, namely that south of the Floating Harbour whereas Mr Raggett’s evidence
looked at the whole scheme; and, second, as Mr Taylor for the second
respondents points out, that it was based on an old block plan in relation to a
different area of office footage (690,000 sq ft rather than 1 m sq ft). This
justified the inspector in what amounted to the positive conclusion at para
24.10 that he accepted Mr Raggett’s evidence.
I accept these
submissions. It follows that Mr Ash’s lack of evidence argument fails. The
crucial question however remains as to whether, in the light of the inspector’s
caveat on viability, it was open to the Secretary of State to confirm
the compulsory purchase order without further analysing viability.
Mr Carnwath
submits that the fact that the Secretary of State has to have regard to
viability does not mean that he has to subject it to detailed analysis. When
cost is relevant its weight is for the minister: see per Forbes J in Sovmots
Investments Ltd v Secretary of State for the Environment [1977] QB
411 at p 422 cited by Glidewell J in Green v Secretaries of State for
the Environment and Transport (1984) 271 EG 550, [1984] 2 EGLR 27. Mr
Carnwath relies on the Green case where it was held that in confirming a
compulsory purchase order the Secretary of State was entitled not to take financial
viability into account if he took the view that it was immaterial in the light
of the advantages of the scheme and the public interest. In the present case
the Secretary of State, submits Mr Carnwath, wholly agreed with the inspector
in his formulation of the issues, his views of the issue merits and demerits,
notwithstanding the caveat, and his overall conclusion that the second
respondents’ scheme would secure regeneration which the alternative proposals
would not and that (para 24.39): ‘. . . a compelling case in the public
interest had been made for confirmation’. Neither the statute nor the circular
refers to viability. Indeed Mr Carnwath submits some schemes may not be
financially viable in an ordinary commercial sense. Financial viability is
merely one of many factors, including the merits of rival schemes, which may be
relevant when considering whether regeneration is on balance more likely to be
achieved if the land is acquired by the urban development corporation.
I accept Mr
Carnwath’s submissions, supported as they are by Mr Taylor QC. In my judgment
the inspector’s approach to viability culminating in his caveat amounts
to this: viability is a factor to be considered because regeneration is
unlikely if a scheme is not viable (para 24.8); it was not shown by the
objector’s evidence that the second respondents’ scheme was not viable or by
the second respondents’ evidence that the scheme was viable (para 24.9);
although the second respondents on reputable advice were satisfied as to its viability,
a question mark existed over viability, expressed by the caveat (para
24.10); despite that question mark, the second respondents’ scheme was soundly
based and would lead to regeneration (para 24.26), which the alternative
proposals would not (para 24.38); a compelling case for confirmation of the
compulsory purchase order in the public interest had therefore been made out
(para 24.39). It seems to me that that process of reasoning, and the Secretary
of State’s adoption of it, is unimpeached by Mr Ash’s central challenge. So far
as delegation is concerned, Mr Ash’s argument is doomed to fail in view of my
conclusion on his primary submission that viability was no more than one of
many factors for consideration when assessing likelihood of regeneration. The
second respondents’ satisfaction as to viability does not, in my view,
represent a delegation by the Secretary of State of any function properly his.
His task as confirming authority was to see that the second respondents’ acted
responsibly and in the public interest and this duty he discharged.
He was, in my
judgment, under no obligation to analyse viability and it cannot therefore be
said that he wrongly delegated that analysis to the second respondents.
Accordingly, despite Mr Ash’s attractive submissions this challenge fails and
is dismissed.
Following an
application for costs on behalf of the second respondents, ROSE J continued:
The second respondents seek an order for their costs against the unsuccessful
applicants. Curiously this is the most difficult aspect of this case which I
have had to decide. On the one hand it is common ground that a practice has
developed in recent years of awarding two lots of costs where the second
respondents are a developer. Equally there is a practice, it is common ground,
of not awarding two sets of costs where the second respondents are a local
authority.
Clearly an
urban development corporation are in some respects akin to a developer and in
some respects akin to a local authority. They are by virtue of section 135, a
creature of the Secretary of State, but also there may be circumstances in
which they have wholly independent interests to pursue, which cannot be pursued
by the Secretary of State. The only decision brought to my attention in
relation to the costs of an urban development corporation is that of Auld J in Leser
Landau v Secretary of State for the Environment (unreported, June 4
1991), where he reached the conclusion that two orders for costs should be
made.
As Mr Ash
points out, it does not appear that section 135, in so far as it takes the
matter very far, was brought to the attention of Auld J. The way in which Mr
Taylor first puts the matter is that the second respondents have a special
interest in pursuing the urgency of the matter. It does not seem to me that
that is a matter which is on analysis separate from the Secretary of State’s
interest in the matter.
The second
aspect to which he draws attention is that by reason of the arguments and
ruling which I gave yesterday at the outset of this matter the original notice
of motion was defective in form and in fact it had to be amended and was
amended with my leave at the behest of Mr Ash.
Thus Mr Taylor
submits there was an additional reason for the second respondents to be
present. The difficulty with that argument is that the second respondents
failed on the jurisdictional challenge which, no amendment having at that stage
been sought by the applicant, they sought to launch.
There was,
prior to the hearing before me, correspondence between the first respondent and
the applicants, of which the second respondents were in ignorance before this
case was called on. That matter does not seem to me to advance the second
respondents’ case in relation to costs having regard to the fact, as I have
said, that their jurisdictional challenge, unsupported by the first respondent
failed. It does not seem to me that advances the second respondents’ case or
that they had any separate interest to pursue.
Accordingly,
in my judgment, the justice of this case will be met if the applicant pay the
first respondent’s costs, but it does not have to pay the second respondents’
costs.