Porter and another v Secretary of State for Transport
Stuart-Smith, Peter Gibson and Thorpe LJJ
Compulsory purchase — Compensation — Certificate of appropriate alternative development under section 17 of Land Compensation Act 1961 — Issue estoppel — Whether evidence can be adduced to show that conclusions by which certificate issued should not be followed in assessing compensation
The claimants owned land on the outskirts
of Evesham. The Secretary of State for Transport acquired two strips of land
(‘the red land’) from the claimants for the construction of a bypass (‘the
yellow route’), and took possession on September 20 1985. The claimants
retained adjoining land (‘the blue land’). Following an appeal under section 18
of the Land Compensation Act 1961, the Secretary of State for the Environment
granted a certificate of appropriate alternative development for the red land
for residential development. He agreed with the reasoning of his inspector and
concluded that because there was an alternative and more easterly route for the
bypass, the red land could have been residentially developed if it were not
being acquired by the acquiring authority for the yellow route. In the
reference to the Lands Tribunal, the acquiring authority sought to adduce
evidence that the conclusions of the Secretary of State for the Environment
should not be followed in assessing compensation for severance and injurious
affection in respect of the blue land. At the hearing of a preliminary point of
law, the tribunal accepted the claimant’s contention that the Secretary of
State for Transport was precluded by the doctrine of issue estoppel from
reopening the issue determined by the certificate of appropriate alternative
development. The Secretary of State for Transport appealed.
Held: The appeal was allowed.
Compulsory purchase — Compensation — Certificate of appropriate alternative development under section 17 of Land Compensation Act 1961 — Issue estoppel — Whether evidence can be adduced to show that conclusions by which certificate issued should not be followed in assessing compensation
The claimants owned land on the outskirts
of Evesham. The Secretary of State for Transport acquired two strips of land
(‘the red land’) from the claimants for the construction of a bypass (‘the
yellow route’), and took possession on September 20 1985. The claimants
retained adjoining land (‘the blue land’). Following an appeal under section 18
of the Land Compensation Act 1961, the Secretary of State for the Environment
granted a certificate of appropriate alternative development for the red land
for residential development. He agreed with the reasoning of his inspector and
concluded that because there was an alternative and more easterly route for the
bypass, the red land could have been residentially developed if it were not
being acquired by the acquiring authority for the yellow route. In the
reference to the Lands Tribunal, the acquiring authority sought to adduce
evidence that the conclusions of the Secretary of State for the Environment
should not be followed in assessing compensation for severance and injurious
affection in respect of the blue land. At the hearing of a preliminary point of
law, the tribunal accepted the claimant’s contention that the Secretary of
State for Transport was precluded by the doctrine of issue estoppel from
reopening the issue determined by the certificate of appropriate alternative
development. The Secretary of State for Transport appealed.
Held: The appeal was allowed.
1. Per Stuart-Smith and Thorpe LJ:
the decision of the Secretary of State for the Environment on an appeal under
section 18 of the Land Compensation Act 1961 cannot give rise to estoppel per
rem judicatam or an issue estoppel. Per Peter Gibson LJ: the
determination by the Secretary of State of an issue of hypothetical fact in
reaching his decision under section 18 is one to which an issue estoppel can
apply.
2. However, the issue determined by the
Secretary of State was not the same as that which has to be determined by the
Lands Tribunal. The Secretary of State does not have to evaluate the chance of
an alternative route being chosen, provided it was more than 50%; the tribunal
would be concerned in assessing value to evaluate the chances of this happening
more precisely.
The following cases are referred to in
this report.
Allied Maples Group Ltd v Simmons & Simmons
[1995] 1 WLR 1602, CA
Carl Zeiss Stiftung v Rayner & Keeler Ltd
(No 2) [1967] 1 AC 853; [1966] 3 WLR 125; [1966] 2 All ER 536, HL
Davies v Taylor [1974] AC 207; [1972] 3
WLR 801; [1972] 3 All ER 836, HL
Fidelitas Shipping Co Ltd v V/O Exportchleb
[1966] 1 QB 630; [1965] 2 WLR 1059; [1965] 2 All ER 4; [1965] 1 Lloyd’s Rep
223, CA
Hoystead v Commissioner of Taxation [1926]
AC 155, PC
Pointe Gourde Quarrying & Transport
Co Ltd v Sub-Intendent
of Crown Lands [1947] AC 565, PC
Thoday v Thoday [1964] P 181; [1964] 2
WLR 371; [1964] 1 All ER 341, CA
Thrasyvoulou v Secretary of State for the
Environment [1988] 1 QB 809; [1988] 1 EGLR 192; [1988] 10 EG 131 and 11 EG
83; [1988] 2 PLR 37
Thrasyvoulou v Secretary of State for the
Environment; Oliver v Secretary of State for the Environment [1990] 2 AC
273; [1990] 2 WLR 1; [1990] 1 All ER 65; (1989) 59 P&CR 326; [1990] 1 EGLR
197; [1990] 13 EG 69; [1990] 2 PLR 69, HL
This was an appeal by the Secretary of
State for Transport from a decision of the Lands Tribunal on a preliminary
point of law in a reference by the claimants for the determination of
compensation arising out of the compulsory purchase of land by the acquiring
authority.
Michael Barnes QC and Christopher
Katkowski (instructed by the Treasury Solicitor) appeared for the appellant;
Malcolm Spence QC and Nicholas Nardecchia (instructed by Rooks Rider)
represented the respondents.
Giving the first judgment, Stuart-Smith LJ said: This is an
appeal by way of case stated from a decision of the Lands Tribunal (the
president, Judge Marder QC) dated January 6 1995. By virtue of section 3(4) of
the Lands Tribunal Act 1949 the appeal is on law only. The appellant is the
acquiring authority.
The case concerns the determination of
the compensation payable by the Secretary of State for Transport to the
claimants for land acquired by him for the construction of the Evesham bypass.
The particular point in issue is whether the Secretary of State for the
Environment in issuing a certificate of appropriate alternative development on
an appeal to him under section 18 of the Land Compensation Act 1961, can give
rise to an issue estoppel which binds the claimants and the acquiring authority
in subsequent proceedings before the Lands Tribunal to assess the compensation.
The point was decided by the president of
the Lands Tribunal on a preliminary issue to the effect that there could in
principle be an issue estoppel in the above circumstances. He further held that
on the particular facts before him there was an issue estoppel. The Secretary
of State for Transport in this appeal contends, first, that in principle there
cannot be an issue estoppel where the decision said to found the estoppel is
one of the exercise of discretion such as a decision relating to the grant or
refusal of planning permission. Second, it is submitted that the issue said to
have been decided by the Secretary of State is not the same as that which falls
to be decided by the Lands Tribunal and accordingly there is no issue estoppel.
In 1985 the Secretary of State for
Transport proposed to construct a new highway to be part of the A435 trunk road
which would run to the east of the town of Evesham and would serve as a bypass
to that town. The claimants own an area of freehold land to the east of Evesham
which is shown edged blue on the plan. The line of the proposed 11
highway would pass across the claimants’ land. The proposed line is shown
coloured yellow on the plan (save that where it crosses the claimants’ land it
is coloured red). In order to acquire the necessary land the Secretary of State
made the Bath-Lincoln Trunk Road (A434-Evesham by-pass) Compulsory Purchase
Order 1985 under powers conferred on him by the Highways Act 1980. The land to
be acquired included a part of the claimants’ land, namely the strip shown
coloured red on the plan (which was, of course, a portion of the line of the
proposed road). Entry on the claimants’ land was made on September 20 1985.
That date became the valuation date for the purposes of assessing compensation.
Compensation for land compulsorily
acquired is assessed in accordance with principles contained in the Land
Compensation Act 1961 (‘the 1961 Act’) and the Compulsory Purchase Act 1965. It
is usual to divide the amount of the compensation payable into three
components: (1) the value of the land acquired; (2) any diminution in the value
of other land of the owners’ retained by them where the diminution is brought
about by the acquisition of the land taken; and (3) disturbance. In the present
case there is no relevant disturbance claim.
The assessment of the first component,
the value of the land taken is governed by r(2) of section 5 of the 1961 Act
which provides:
The value of land shall, subject as
hereinafter provided, be taken to be the amount which the land if sold in the
open market by a willing seller might be expected to realise:
The assessment of the second component is
governed by section 7 of the Compulsory Purchase Act 1965, which provides:
In assessing the compensation to be paid
by the acquiring authority under this Act regard shall be had not only to the
value of the land to be purchased by the acquiring authority, but also to the
damage, if any, to be sustained by the owner of the land by reason of the
severing of the land purchased from the other land of the owner, or otherwise
injuriously affecting that other land by the exercise of the powers conferred
by this or the special Act.
In assessing compensation no account is
to be taken of any increase or decrease in the value of the land which is due
to the scheme which underlies the compulsory acquisition: see Pointe Gourde
Quarrying & Transport Co Ltd v Sub-Intendent of Crown Lands
[1947] AC 565, and section 6 and Schedule 1 to the 1961 Act.
The claimants consequently claim
compensation for (a) the value of the land taken (the red strip on the plan)
and (b) a diminution in the value of the land retained by them (the remainder
of the blue edged land on the plan after excluding the red strip). In order to
assess the land value in both cases it was necessary to ascertain what planning
permission (if any) enured for the benefit of the areas of land involved.
In accordance with the Pointe Gourde
principle the question of what planning permission was to apply to the areas of
land had to be ascertained ignoring the effects of the proposal to construct
the new highway. Sections 17 and 18 of the 1961 Act contain a statutory
procedure for the determination of this question in relation to the land acquired.
An application may be made to the local planning authority by either the
landowner or the acquiring authority for a certificate of appropriate
alternative development (a ‘section 17 certificate’). On receipt of an
application the local planning authority are required by section 17(4) to issue
a certificate either (a) that in their opinion if the land were not proposed to
be acquired compulsorily planning permission would have been granted for a
class or classes of development specified in the certificate, or (b) that in
their opinion in the above circumstances planning permission would not have
been granted for any development. The latter form of certificate is often
called a nil certificate. Sections 14(1) and 15(5) of the Act provide that in
ascertaining the value of the relevant interest it shall be assumed that
planning permission would be granted in accordance with the certificate. It
should be noted that the provisions of section 17 and sections 14(1) and 15(5)
are such that the certificate, and any planning permission assumed in
accordance with the certificate, relate only to the interest in land proposed
to be acquired. It follows that a certificate may determine the situation as
regards planning permission on the land being acquired, but has no statutory
effect on the planning situation on other land of the landowner which is not
being acquired and in respect of which there may be a claim for the diminution
in its value. Section 18 contains a procedure by which the landowner or the
acquiring authority may appeal to the Secretary of State for the Environment
against the decision of the local planning authority in issuing a certificate
under section 17. Section 18(3) prescribes that, if required by either party,
the Secretary of State must hold a hearing before an appointed person (ie an
inspector) before determining the appeal.
The claimants contended that in the
absence of the highway scheme planning permission would have been granted to
develop their land residentially. Accordingly, they said that the value of the
land taken and their claim for compensation for diminution in the value of the
land retained should be assessed on the basis of the potential of the land for
residential development. They applied to the local planning authority, Wychavon
District Council, for a section 17 certificate certifying residential
development as the appropriate alternative development. That council issued a
nil certificate (save in respect of a small and immaterial part of the land
being acquired). The claimants appealed to the Secretary of State for the
Environment under section 18 of the Act. A hearing was held before an inspector
in May 1988 and the inspector reported to the Secretary of State on September
23 1988.
A question which arose at the hearing was
what new highway provision (if any) would have been made in the vicinity of
Evesham in the absence of the proposal to acquire the claimants’ land to
construct a bypass on the line shown in yellow on the plan. The claimants
contended that what would have happened in this hypothetical situation is that
a bypass would have been constructed to the east of the town on a line shown in
green on the plan (the ‘green route’). The green route would have passed
through the claimants’ land some distance to the east of and roughly parallel
with the route actually constructed. The actual route and the green route start
and end at approximately the same point but take a somewhat different
intermediate course. In other words in highway terms they both fulfil much the
same function of providing a bypass for traffic to the east of Evesham. The
purpose of the claimants in making the contention which they did was that they
argued that if there was assumed to be a bypass on the green route that highway
would form a physical boundary to the outward spread of Evesham and would add
force to their argument that planning permission would then have been granted
for the residential development of the greater part of their land which lay
inside the physical boundary.
At the hearing the local planning
authority felt unable to answer the question of what road project there would
have been apart from the project on the line proposed by the Secretary of State
for Transport. The Secretary of State was invited to attend the proceedings in
order to assist on this matter. He was in any event entitled to attend the
hearing by reason of section 18(3) of the Act. The submissions made on behalf
of the Secretary of State were that if the actual route had not been
implemented there would either have been no scheme, or if there was one, the
most likely alternative route would have been (a) a combination of a central
route and a southern bypass and eastern link, or (b) if an eastern route alone
had been selected as an alternative to the actual route an inner eastern route
would have been chosen.
The inspector who held the hearing
rejected the Secretary of State’s submissions and concluded that the green
route was the most likely alternative route. He included this conclusion in his
report to the Secretary of State, and recommended at para 8.1 of his report
that the appeal be allowed and a section 17 certificate be issued specifying
residential development as the appropriate alternative development. The
Secretary of State in substance agreed with the inspector and on November 30
1988 he issued a section 17 certificate with residential development specified.
The result of the decision of the
Secretary of State and of the certificate issued is that in the valuation of
the land acquired from the claimants it must be assumed that planning
permission would be granted for its residential development. The whole of the
claimants’ 12
claim for compensation (that is the claim to the value of the land acquired and
the diminution in the value of their remaining land) was referred by them to
the Lands Tribunal.
Mr Malcolm Spence QC, on behalf of the
respondents, contends that even if the section 17 certificate does not preclude
the Lands Tribunal from reaching a conclusion that planning permission for
housing would not have been granted for their land to the west of the green
route, the finding of the inspector, accepted by the Secretary of State, that
if the actual route had not been adopted, the bypass would have been
constructed on the line of the green route creates an issue estoppel and the
acquiring authority cannot dispute this in the proceedings before the Lands
Tribunal. The distinction is perhaps a fine one, because, if the green route
had been constructed, it is very likely that it would have formed the eastern
boundary of the town’s development and the respondents would therefore have
been likely to have obtained planning permission up to this line.
This distinction is one to which Mr
Spence attaches some importance, although it is not fully reflected in the
preliminary question of law posed for the decision of the Lands Tribunal which
is in these terms:
Whether the doctrines of res judicata
and/or issue estoppel apply in the circumstances of this case so as to preclude
the acquiring authority from calling evidence before, and making submissions to
the tribunal, that the conclusions reached by the Secretary of State for
Environment as set out in a letter dated November 30 1988 whereby he decided to
issue a certificate under Section 17 of the Land Compensation Act 1961 for
residential development of the land acquired from the claimants should not be
followed and applied by the tribunal in assessing the amount of compensation to
be paid in respect of severance and/or injurious affection to the land retained
by the claimants.
The principles of estoppel per rem
judicatam and issue estoppel are explained by Diplock LJ in Thoday v
Thoday [1964] P 181 at pp197–8 he said:
… estoppel per rem judicatam … is
a generic term which in modern law includes two species. The first species, which
I will call ’cause of action estoppel,’ is that which prevents a party to an
action from asserting or denying, as against the other party, the existence of
a particular cause of action, the non-existence or existence of which has been
determined by a court of competent jurisdiction in previous litigation between
the same parties. If the cause of action was determined to exist, ie judgment
was given upon it, it is said to be merged in the judgment, or, for those who
prefer Latin, transit in rem judicatam. If it was determined not to
exist, the unsuccessful plaintiff can no longer assert that it does; he is
estopped per rem judicatam. This is simply an application of the rule of
public policy expressed in the Latin maxim Nemo debet bis vexari pro una et
eadem causa. In this application of the maxim causa bears its
literal Latin meaning. The second species, which I will call ‘issue estoppel,’
is an extension of the same rule of public policy. There are many causes of
action which can only be established by proving that two or more different
conditions are fulfilled. Such causes of action involve as many separate issues
between the parties as there are conditions to be fulfilled by the plaintiff in
order to establish his cause of action; and there may be cases where the
fulfilment of an identical condition is a requirement common to two or more
different causes of action. If in litigation upon one such cause of action any
of such separate issues as to whether a particular condition has been fulfilled
is determined by a court of competent jurisdiction, either upon evidence or
upon admission by a party to the litigation, neither party can, in subsequent
litigation between one another upon any cause of action which depends upon the
fulfilment of the identical condition, assert that the condition was fulfilled
if the court has in the first litigation determined that it was not, or deny
that it was fulfilled if the court in the first litigation determined that it
was.
It is common ground that four matters
have to be established if there is to be an issue estoppel.
1. The issue in question must have been
decided by a court or tribunal of competent jurisdiction. It is accepted by the
appellant that the Secretary of State, when deciding an appeal under section 18
of the 1961 Act, is a competent tribunal.
2. That the issue must be one which
arises between parties who are parties to the decision. This also is accepted.
3. That the issue must have been decided
finally and must be of a type to which an issue estoppel can apply.
4. The issue in respect of which the
estoppel is said to operate must be the same as that previously decided. These
propositions derive from Carl Zeiss Stiftung v Rayner & Keeler
Ltd (No 2) [1967] 1 AC 853.
It is in relation to points 3 and 4 that
the controversy in this appeal arises.
The first question therefore is whether
the Secretary of State’s decision on the section 18 appeal is one that can give
rise to an issue estoppel. In Thrasyvoulou v Secretary of State for
the Environment [1990] 2 AC 273* it was held that certain matters decided
by the Secretary of State on an appeal against an enforcement notice could give
rise to a plea of estoppel per rem judicatam or issue estoppel, but this
did not apply, at least so far as estoppel per rem judicatam is
concerned, to a decision on the ground that planning permission ought to have
been granted for development to which the notice relates.
*Editor’s note: Also reported at [1990] 1
EGLR 197
At p287D Lord Bridge of Harwich, with
whose speech the other members of the House agreed, dealt with the various
grounds under section 88(2) of the Town and Country Planning Act 1971 on which
an appeal against an enforcement notice can be based.
Ground (a) is that planning
permission ought to be granted for the development to which the notice relates.
Ground (b) is that the matters alleged in the notice do not constitute a
breach of planning control. Ground (c) is that the breach of planning
control alleged in the notice has not taken place. Ground (d) applies to
notices alleging development by carrying out building etc. operations which can
only be enforced against within four years of the development taking place.
Ground (d) is therefore established if the breach of planning control
occurred more than four years before the issue of the enforcement notice.
Ground (e) applies to development consisting of making a material of use
of land which can only be enforced against if the change of use was made since
1963. Ground (e) is therefore established if the change of use occurred
before the beginning of 1964. The remaining grounds (f) to (h)
relate to subsidiary issues which may arise as to the service of the enforcement
notice, the steps required to be taken to remedy the breach of planning control
alleged and the time for taking those steps and these grounds have no relevance
for present purposes.
An issue on ground (a) arises in
every appeal against an enforcement notice since by section 88B(3) there is
deemed to be an application for planning permission for the development to
which the notice relates. In determining whether to allow an appeal on that
ground the Secretary of State will decide as a matter of policy and in the
exercise of discretion whether planning permission should be granted and in
relation to ground (a) no question of legal right arises. By contrast
the question whether any of the grounds (b) to (e) on which the
appellant relies had been established will be answered by applying the relevant
rules of planning law to the facts found and the answer will determine in each
case an important matter of legal right. This may be simply illustrated by
examples. Thus, if an issue is raised on appeal against a notice on ground (b)
as to whether or not a building operation to which the notice relates was
within the terms of planning permission granted either upon an express
application or by the terms of a development order, a decision of that issue to
allow the appeal on ground (b) will determine the status of the building
in question as having been lawfully erected.
He then went on to give examples on the
grounds (c) to (e). The reference to the fact that in relation to
ground (a) no question of legal right arises must, I think, be a
reference to the fact that the applicant for planning permission, or appellant
from an enforcement notice, has no legal right to a grant of planning
permission, in the event that certain facts are established. This is in
contradistinction to a decision of a court of law where as a rule a litigant
who establishes certain facts which constitute a cause of action is entitled as
a matter of legal right to a decision in his favour. A decision whether or not
to grant planning permission is a matter of discretion based upon
considerations of policy and aesthetic opinion, as to which opinions may vary.
That this is Lord Bridge’s meaning appears from a later passage, where he makes
it plain that someone who has been granted planning permission in respect of a
piece of land thereby acquires legal rights. At p290E he said:
13
Much of the argument against allowing a
plea of res judicata or issue estoppel founded on the determination of an
appeal against an enforcement notice under section 88(2) of the Act rested on
the proposition that such a determination is characterised by a ‘planning
decision’ and emphasis was placed on the rights of members of the public to be
heard. Mr Laws submitted that no distinction could be drawn between a decision
on ground (a) of section 88(2) to grant or withhold planning permission
for the development the subject of an enforcement notice, and the decision of
any issue arising under grounds (b) to (e). If an estoppel arises
in the one case, he submits, it must equally arise in the other. I cannot
accept this submission. A decision to grant planning permission creates, of
course, the rights which such a grant confers. But a decision to withhold
planning permission resolves no issue of legal right whatever. It is no more than
a decision that in existing circumstances and in the light of existing planning
policies the development in question is not one which it would be appropriate
to permit. Consequently, in my view, such a decision cannot give rise to an
estoppel per rem judicatam. I also think that there is a significant
distinction between the issue raised by an appeal under ground (a) and
the issues raised by any of grounds (b) to (e) in that members of
the public have the right to attend any public inquiry and to be heard as
objectors against the grant of planning permission, but can have no locus
standi as objectors, although they may be heard as witnesses of fact, in
relation to the issues raised on grounds (b) to (e).
Basing himself on the reasoning of Lord
Bridge, Mr Michael Barnes QC, on behalf of the appellant, submitted that a
decision by the Secretary of State under section 18 of the 1961 Act as to
whether or not planning permission would have been granted in a hypothetical
situation is of a similar nature to a decision whether it should be granted in
an actual situation, involving similar questions of discretion, policy and
opinion, and accordingly could not give rise to an estoppel.
Mr Spence sought to distinguish the two,
first on the basis that the section 18 decision is a hypothetical rather than
an actual one. But I cannot see that this is a relevant distinction. Second, on
the basis that in a section 18 case the public have no participation, unlike an
appeal on a planning application or against an enforcement notice. This is the
point made by Lord Bridge at the end of his second paragraph quoted. This is a
distinction; but it is only one of the reasons given by Lord Bridge and does
not affect principal ground.
Mr Spence accepts, as I understand it,
that a nil certificate would not estop the respondents from contesting before
the Lands Tribunal that planning permission would have been granted on the
retained land. This he suggests is the effect of section 14(3) and (3A) of the
1961 Act; though the Lands Tribunal is required to have regard to the contrary
opinion expressed in the nil certificate. But both section 15(5) and section
14(3) and (3A) are only concerned with the compulsorily acquired land and do
not affect the retained land. In my judgment, it would be remarkable if an
estoppel per rem judicatam could be created by a positive certificate
but not by a nil certificate.
But Mr Spence’s secondary submission, and
one I think on which he places most reliance, is that even if the decision
itself that planning permissions would have been granted up to the green route
does not create an estoppel per rem judicatam for the reasons given by
Lord Bridge, findings of fact made by the inspector and adopted by the
Secretary of State, which were a necessary part of the reasoning which led to
the grant of the certificate, nevertheless can give rise to an issue estoppel.
Mr Spence cited no authority for this proposition, though he submitted that it
was based on general principle. He relied upon a dictum of Lord Shaw of
Dumfermline in Hoystead v Commissioner of Taxation [1926] AC 155
at p170 where he said:
It is seen from this citation of
authority that if in any Court of competent jurisdiction a decision is reached,
a party is estopped from questioning it in a new legal proceeding. But the
principle also extends to any point, whether of assumption or admission, which
was in substance the ratio of and fundamental to the decision
This passage was cited with approval by
Lord Reid in the Carl Zeiss case at p915G. Mr Spence also referred to
two passages from the judgments of the Court of Appeal in Fidelitas Shipping
Co Ltd v V/O Exportchleb [1966] 1 QB 630. Lord Denning MR said at
p640:
The rule then is that, once an issue has
been raised and distinctly determined between the parties, then, as a general
rule, neither party can be allowed to fight that issue all over again.
Diplock LJ at p641 said:
The final resolution of a dispute between
parties as to their respective legal rights or duties may involve the
determination of a number of different ‘issues’, that is to say, a number of
decisions as to the legal consequences of particular facts, each of which
decisions constitutes a necessary step in determining what are the legal rights
and duties of the parties resulting from the totality of the facts.
These passages are quoted by Lord
Wilberforce in Carl Zeiss at p964. But these were cases where the
original decision was one capable of creating an estoppel per rem judicatam
or cause of action estoppel, because they were decisions of a court determining
the legal rights of the parties by applying the law to the facts found. It is
entirely understandable that an issue estoppel can arise from such a decision.
They do not lend any support to the contention that where the decision is not
such as to create an estoppel per rem judicatam, the lesser creature,
issue estoppel can nevertheless arise. Such a conclusion seems to me to be
inconsistent with the reasoning of Lord Bridge in Thrasyvoulou. At the
beginning of his speech he posed the question thus at p285:
My Lords, these two appeals raise the
question whether a decision of the Secretary of State allowing an appeal
against an enforcement notice on one of the grounds in paragraphs (b) to
(e) of section 88(2) of the Town and Country Planning Act 1971, as
amended by the Local Government and Planning (Amendment) Act 1981, is capable
of giving rise to an estoppel per rem judicatam or to an issue estoppel.
If Lord Bridge had thought that even
though a decision whether or not to grant planning permission was not one to
which estoppel per rem judicatam could apply, it was possible for an
issue estoppel to arise in relation to some finding of fact made by the
Secretary of State and necessary to his decision, I find it very surprising
that he did not say so. It seems to be implicit in his judgment that he thought
no such thing. In fact as Diplock LJ made clear in the passage I have cited
from Thoday v Thoday, estoppel per rem judicatam embraces both
cause of action estoppel and issue estoppel. Since Lord Bridge cited this
passage, it seems to me clear that in holding that a decision on ground (a) of
section 88(2) cannot give rise to estoppel per rem judicatam, he must be
taken to have included in this issue estoppel.
Mr Spence sought to gain some support from
a dictum of Ralph Gibson LJ in the Court of Appeal in the Thrasyvoulou
v Secretary of State for the Environment [1988] 1 QB 809* at p824A he
said:
*Editor’s note: Also reported at [1988] 1
EGLR 192
It is necessary now to consider whether
issue estoppel can arise out of the decision by the Secretary of State or an
inspector upon a section 36 appeal. In my judgment issue estoppel can so arise
if the party seeking to raise it proves that the earlier decision in the
section 36 appeal was given in his favour against the planning authority upon
an issue as to his existing rights of use of the property, and was a decision
of the same issue as that raised in the new proceedings.
A section 36 appeal is simply an appeal
from the refusal of planning permission by the local planning authority, and
raises identical issues to those in an appeal against an enforcement notice
under section 88(2). But I do not understand this passage to differ in any way
from what Lord Bridge said in the House of Lords. It relates to grounds other
than the question whether or not planning permission should be granted and is
made clear in the next paragraph of his judgment.
Moreover, I think there is force in Mr
Barnes’ submission that it would be remarkable if, although no estoppel per
rem judicatam could arise on a section 17 certificate, whether positive or
negative (and Mr Spence concedes there cannot be in relation to a nil
certificate), there 14
were to be an issue estoppel in relation to a finding of fact upon which the
section 17 certificate is largely based.
There is I think an additional reason why
a decision of the Secretary of State whether to grant planning permission,
whether on an appeal from an enforcement notice or original refusal by the
local authority, cannot give rise to estoppel per rem judicatam, either
in the form of cause of action or issue estoppel, and that is because it lacks
the necessary element of finality. It is well established that a judgment
pending trial, such as whether or not to grant an interlocutory injunction,
cannot give rise to an estoppel of either sort, because it lacks this element
of finality. As Lord Bridge pointed out in Thrasyvoulou a refusal of
planning permission does not finally determine the matter; a fresh application
can be made. Moreover, although a grant of planning permission can create
rights and if acted upon cannot be revoked, if it is allowed to lapse
determines nothing.
In my judgment, Mr Barnes is correct on
the first question and the decision of the Secretary of State on a section 18
appeal cannot give rise either to estoppel per rem judicatam or an issue
estoppel.
I turn to consider the second question,
namely whether the issue determined by the Secretary of State is the same as
that which has to be determined by the Lands Tribunal. Mr Barnes submits that
it is not. What the Lands Tribunal has to assess is the diminution in value, if
any, to the land of the respondents retained by them. Consideration of the open
market value of a piece of land will involve an assessment of the chances of
planning permission being granted for it, together with such questions as the
demand for such development. The assessment of the prospect of planning
permission no doubt depends to a large extent on where an alternative bypass
would have gone if it had not followed the yellow route. To this extent the
questions before the Lands Tribunal and the Secretary of State are similar;
but, in my view, they are not the same.
The point can best be illustrated by
taking an example where the facts may be somewhat different from those which in
fact existed. Suppose there were two alternative routes to the route chosen,
one to the east of it and one to the west. The two alternatives might be very
evenly balanced. But the Secretary of State might decide that the scales just
tipped in favour of the eastern route, with the result that he concludes that
planning permission would have been granted up to that alternative route and
this would include the claimants’ land. Because of the assumptions required to
be made in relation to the acquired land, this finding is the equivalent of a
certainty that planning permission would be granted in relation to that land.
Mr Spence also submits that the finding as to the position of the alternative
route must also be regarded as a certainty, because he says it is a finding of
hypothetical fact. It is only necessary for the Secretary of State to find the
position of the alternative on a balance of probability; but the Lands Tribunal
have to assess the extent of the chance, which in the example given is only
just better than even.
Where a court or tribunal has to decide
what would have happened in a hypothetical situation which does not exist, it
usually has to approach the matter on the basis of assessing what were the
chances or prospect of it happening. The chance may be almost a certainty at
one end to a mere speculative hope at the other. The value will depend on how
good this chance is. Where however the court or tribunal has to decide what in
fact has happened as an historical fact it does so on balance of probability;
and once it decides that it is more probable than not, then the fact is found
and is established as a certainty. This distinction is well illustrated by the
case of Davies v Taylor [1974] AC 207 and Allied Maples Group
Ltd v Simmons & Simmons [1995] 1 WLR 1602, CA.
It would be unnecessary for the Secretary
of State to evaluate the chance of the eastern route being the preferred
alternative route in the event that the actual route was not chosen, provided
it was more than 50%; but the Lands Tribunal would be concerned in assessing
value to evaluate the chances of this happening more precisely.
It may well be that on the facts of this
case the only viable alternative was the green route and other alternatives can
be completely discounted. I do not know. But a question of principle cannot be
determined on the basis of favourable facts of a particular case, and for this
reason also I am of the opinion that the Secretary of State’s decision did not
create an issue estoppel.
I would allow this appeal and answer the
question posed in para 4 of the case stated, namely whether the Lands Tribunal
erred in law in rejecting the acquiring authority’s submission that no issue
estoppel was created in favour of the claimants in the alternative.
Agreeing, Peter Gibson LJ said: There is much that is common ground
between the parties. Of the four conditions for there to be an issue estoppel,
which Stuart-Smith LJ has set out in his judgment, only the satisfaction of
part of the third condition, viz that the issue in question must be of a type
to which an issue estoppel can apply, and the fourth condition, viz that the
issue, in respect of which the estoppel is said to operate, must be the same as
that previously decided, is now contested by the acquiring authority.
It is right to point out at the outset
that, as Mr Spence QC for the claimants emphasised, they do not rely on the
certificate under section 17 Land Compensation Act 1961 itself, which was
directed by the Secretary of State on the appeal to him under section 18, for
the issue estoppel asserted by the claimants; they merely rely on one issue of
hypothetical fact underlying the certificate. That fact is that there would
have been an alternative bypass to the east along the line of the preferred
route in the absence of the actual bypass. There is no doubt but that the issue
whether there would have been such an alternative bypass on that line was an issue
that was distinctly raised by the claimants and determined by the Secretary of
State in the course of arriving at his decision to issue the section 17
certificate.
The first question is therefore, in my
view, more accurately stated as whether the determination by the Secretary of
State of an issue of hypothetical fact in reaching his decision under section
18 is one to which an issue estoppel can apply. Mr Barnes QC for the acquiring
authority submitted that the Secretary of State had to reach a decision whether
in his opinion planning permission would have been granted for a form of
development on the land acquired if it were not being acquired compulsorily,
and that in essence was the decision the Secretary of State makes on any
planning appeal, including an appeal on ground (a) of section 88(2) Town and
Country Planning Act 1971. He relied on what Lord Bridge said in Thrasyvoulou
v Secretary of State for the Environment [1990] 2 AC 273 at pp287 and
290 as authority for the proposition that the decision of the Secretary of
State in the section 18 appeal is one of a nature and category which cannot
give rise to an estoppel per rem judicatam. If that proposition were limited to
the decision whether to direct the issue of a section 17 certificate, I would accept
it. Mr Barnes submitted that if the genus of estoppel per rem judicatam
does not apply to a decision, it would be absurd to hold that one species of
that genus, issue estoppel, can apply to the same decision. Put that way, his
submission is a mere truism which does not help to resolve the real question.
Issue estoppel, as distinct from cause of
action estoppel, will arise where cause of action estoppel cannot be
established but nevertheless there has been a final determination of a precise
point distinctly put in issue and the contrary of the same point is sought to
be raised in subsequent proceedings between the same parties. I cannot see why
in principle an issue estoppel in respect of the determination of such a point
may not arise in the course of proceedings culminating in a decision which
itself cannot be the subject of an estoppel. It is said that Lord Bridge’s
speech in Thrasyvoulou is inconsistent with the possibility of an issue
estoppel arising in such circumstances. I am unable to agree. The observations
of Lord Bridge on ground (a) of section 88(2), and the reasons why he
distinguished that ground from grounds (b) to (e), were directed
to the decision of the Secretary of State as to whether planning permission
should be granted. As he said (at p289), that decision will be reached ‘as a
matter of policy and in the exercise of discretion’ and (at p290) ‘It is no
more than a decision that in existing circumstances and in the light of
existing planning policies the development in question is not one which it
would be appropriate to permit’. None of that reasoning is pertinent to the
determination of a point of fact, actual or hypothetical, that determination
not being dependent on policy or discretion. I would add that in that part of
Lord Bridge’s speech where he considers ground (a) of section 88(2), he
uses the terms ‘estoppel per rem judicatam’ and ‘issue estoppel’ indifferently
(see p295) but goes on to distinguish between them by reference to the
terminology used by Diplock LJ in Thoday v Thoday [1964] P 181 at
pp197–8. Thus applying that terminology and classification by analogy to the
issues which arise on an appeal against an enforcement notice on any of grounds
(b) to (e) of section 88(2), he thought the analogue of a cause
of action estoppel would arise whenever the determination of the ground decided
in favour of the appellant on an appeal against an enforcement notice could be
relied on in an appeal against a second enforcement notice in the same terms
and directed against the same development as the first. But he contrasted that
with the issue estoppel that arose on the appeal in Oliver v Secretary
of State for the Environment, (decided at the same time as the Thrasyvoulou
appeal) where there was a determination of an issue of fact (as to an
established use) which Lord Bridge described as an essential foundation for the
finding of an inspector, which issue could not be raised in subsequent
proceedings. I cannot see why the determination of an issue of fact which was
an essential foundation for the decision of the Secretary of State on an appeal
under ground (a) should not similarly give rise to an issue estoppel.
It is not suggested that an issue of
hypothetical fact should be treated differently from an issue of actual fact.
Accordingly, I would hold on the first question that the determination by the
Secretary of State of an issue of hypothetical fact in reaching his decision
under section 18 is one to which an issue estoppel can apply.
That leaves the second question: is the
issue of whether there would have been an alternative bypass on the line of the
preferred route the same as that to be determined by the Lands Tribunal? For
the reasons given by Stuart-Smith LJ I agree with him that it is very similar
but that it is not the same.
I, too, would allow the appeal and answer
the question in para 4 of the case stated in the manner proposed by
Stuart-Smith LJ
Also agreeing, Thorpe LJ said: The result for which the land owners
contended in the Lands Tribunal has obvious practical attractions. If by an
expensive appellate procedure the Secretary of State has pronounced what would
have happened had the yellow route not been selected, the proposition that the
same hypothetical question of fact should be reinvestigated in subsequent
proceedings between the same parties is obviously unattractive. Therefore the
decision of the president of the Lands Tribunal is hardly surprising and I
would have favoured upholding it had authority permitted.
However, Mr Barnes swiftly demonstrated
that authority does not permit, and Mr Spence’s manful efforts to turn the
attack were, in my judgment, unavailing. For me the case of Thrasyvoulou
v Secretary of State for the Environment [1990] 2 AC 273 is
determinative. Although the speech of Lord Bridge does not expressly state that
issue estoppel cannot underlie a decision to which estoppel per rem
judicatam cannot apply, I share the view of Stuart-Smith LJ, that that is
the effect of his judgment by implication. Thus I accept Mr Barnes’ submissions
on both issues and agree that this appeal should be allowed.
Appeal allowed.