Maidstone Borough Council v Secretary of State for the Environment and another
Glidewell and Morritt LJJ and Sir John May
Compulsory purchase — Certificate of appropriate alternative development — Whether r(2) of section 5 of Land Compensation Act 1961 relevant to issue of certificate — Whether use of land for public open space by authority with compulsory powers to be disregarded under section 17(4)
On November 9
1990, and pursuant to two compulsory purchase orders made in 1988 and 1989,
Kent County Council, the second respondents, took possession of land, owned by
Maidstone Borough Council, which had been used as allotments; the land was
required for the construction of a road. In September 1990 the borough council,
as the local planning authority, issued a certificate of appropriate
alternative development that planning permission would be granted for offices,
residential development, an hotel and/or car parking. Following an appeal
against this certificate by the county council, and a report recommending the
appeal be dismissed by the appointed inspector, on April 16 1993 the Secretary
of State for the Environment considered the loss of public open space,
cancelled the certificate issued by the borough council and certified that if
the land were not proposed to be acquired, planning permission would be granted
for car parking for 250 cars and for the construction of the road. The borough
council’s application to quash the Secretary of State’s decision was dismissed
in the court below. They appealed contending, inter alia, that it had to
be assumed for the purposes of r(2) of section 5 of the Land Compensation Act
1961 that the borough council were a willing seller, and in that situation in
order for the land to be used as a public open space, it would have to be
acquired by an authority with compulsory purchase powers; such an acquisition
must be disregarded under section 17(4) of the 1961 Act in granting a
certificate.
Held: The appeal was dismissed. R(2) of section 5 has nothing to do with
the assumptions as to planning permission. The Secretary of State was therefore
entitled to consider the potential loss of public open space. The Secretary of
State had considered the opportunity cost of alternative public open space and
the possibility of part development of the site. The borough council had not
been prejudiced by any inadequacy of reasons in the Secretary of State’s
decision.
Compulsory purchase — Certificate of appropriate alternative development — Whether r(2) of section 5 of Land Compensation Act 1961 relevant to issue of certificate — Whether use of land for public open space by authority with compulsory powers to be disregarded under section 17(4)
On November 9
1990, and pursuant to two compulsory purchase orders made in 1988 and 1989,
Kent County Council, the second respondents, took possession of land, owned by
Maidstone Borough Council, which had been used as allotments; the land was
required for the construction of a road. In September 1990 the borough council,
as the local planning authority, issued a certificate of appropriate
alternative development that planning permission would be granted for offices,
residential development, an hotel and/or car parking. Following an appeal
against this certificate by the county council, and a report recommending the
appeal be dismissed by the appointed inspector, on April 16 1993 the Secretary
of State for the Environment considered the loss of public open space,
cancelled the certificate issued by the borough council and certified that if
the land were not proposed to be acquired, planning permission would be granted
for car parking for 250 cars and for the construction of the road. The borough
council’s application to quash the Secretary of State’s decision was dismissed
in the court below. They appealed contending, inter alia, that it had to
be assumed for the purposes of r(2) of section 5 of the Land Compensation Act
1961 that the borough council were a willing seller, and in that situation in
order for the land to be used as a public open space, it would have to be
acquired by an authority with compulsory purchase powers; such an acquisition
must be disregarded under section 17(4) of the 1961 Act in granting a
certificate.
Held: The appeal was dismissed. R(2) of section 5 has nothing to do with
the assumptions as to planning permission. The Secretary of State was therefore
entitled to consider the potential loss of public open space. The Secretary of
State had considered the opportunity cost of alternative public open space and
the possibility of part development of the site. The borough council had not
been prejudiced by any inadequacy of reasons in the Secretary of State’s
decision.
The following
cases are referred to in this report.
Clyde
& Co v Secretary of State for the
Environment [1977] 1 WLR 926; [1977] 3 All ER 1123; (1977) 75 LGR 660; 35
P&CR 410; [1977] 2 EGLR 148; [1977] EGD 892; 244 EG 1024; [1977] JPL 521,
CA
Granada
Theatres v Secretary of State for the
Environment (1980) 43 P&CR 258; [1981] 1 EGLR 142; 257 EG 1154; [1981]
JPL 278
Horn v Sunderland Corporation [1941] 2 KB 26; [1941] 1 All ER 480;
39 LGR 367, CA
Pointe Gourde
Quarrying & Transport Co Ltd v Sub-Intendent
of Crown Lands [1947] AC 565, PC
Save
Britain’s Heritage v Number 1 Poultry Ltd
[1991] 1 WLR 153; sub nom Save Britain’s Heritage v Secretary of
State for the Environment [1991] 2 All ER 10; (1991) 62 P&CR 105;
[1991] 3 PLR 17, HL
Scunthorpe
Borough Council v Secretary of State for the
Environment [1977] JPL 653
Trocette
Property Co Ltd v Greater London Council
(1974) 72 LGR 701; 28 P&CR 408; [1974] EGD 547; 231 EG 1031, CA
This was an
appeal by Maidstone Borough Council from the decision of Tucker J who on July
28 1994 refused an application by the borough council under section 21 of the
Land Compensation Act 1961 to quash a certificate of appropriate alternative
development issued by the first respondent, the Secretary of State for the
Environment, following an application and appeal by the second respondents,
Kent County Council.
Matthew Horton
QC and Murziline Parchment (instructed by Sharpe Pritchard, on behalf of
Maidstone Borough Council) appeared for the appellants; David Elvin (instructed
by the Treasury Solicitor) represented the first respondent; Timothy Comyn
(instructed by the solicitor to Kent County Council) represented the second
respondents.
Giving
judgment, Glidewell LJ
said: This is an appeal against a decision of Tucker J given on July 28 1994
refusing an application to him under section 21 of the Land Compensation Act
1961 for an order quashing the decision of the Secretary of State for the
Environment in a letter dated April 15 1993. The Secretary of State had himself
allowed an appeal by Kent County Council (‘Kent’) against a certificate of
appropriate alternative development issued by Maidstone Borough Council
(‘Maidstone’) as local planning authority under section 17 of the Act of 1961,
had cancelled the certificate issued by Maidstone and had issued a new
certificate in its place.
Land and
procedures leading to this appeal
The land, the
subject of this appeal (‘the site’), was an area of 8.15 acres on the east side
of Sandling Road, three-quarters of a mile north of the town centre of
Maidstone, in a part of the town which was substantially built up. The
Maidstone barracks was nearby. Until its acquisition by Kent, the site formed
part of a larger area of 17.63 acres, owned by Maidstone and used as allotment
gardens. The site was acquired by Kent for the construction of the A229
Maidstone Spine Road, by two compulsory purchase orders made by Kent on
December 5 1988 and September 25 1989, and a request made on March 30 1990 by
Kent to Maidstone to negotiate a sale of further land. Kent entered upon and
took possession of the whole site on November 9 1990.
The state of
the land before the acquisition was to be assessed as at the first three of
these dates, while the relevant planning policies were to be considered at
either all four dates or at the last of them, the date of entry — there are two
conflicting decisions of the High Court on this point. Fortunately, all parties
were and are agreed that neither the state of the land nor the relevant
planning policies altered between the first and last of the material dates.
30
At those
dates, a substantial number of the allotments on the whole 17.63 acres were
disused. At the time of the inspector’s inspection in February 1992, after the
acquisition by Kent, there remained a balance of 9.46 acres still in use as
allotment land. On this area at that time most of the allotments were in active
use.
Kent applied
for a certificate of appropriate alternative development, under section 17 of
the 1961 Act, on March 30 1990. The application stated that in Kent’s opinion,
if the land were not to be acquired by an authority possessing compulsory
purchase powers, planning permission would not be granted for any development
other than that for which it was being acquired. However, Maidstone, as local
planning authority, issued on September 14 1990 a certificate that, on the same
assumption, planning permission would have been granted for offices,
residential development, an hotel and/or car parking, all subject to
conditions.
It was against
this certificate that Kent appealed. The appeal was the subject of a local
inquiry which lasted, for reasons I find difficult to understand, for 23 days
starting on 30 July 1991 and ending on February 21 1992. The inspector reported
to the Secretary of State on May 15 1992. He recommended that the appeal be
dismissed and that Maidstone’s certificate be confirmed.
By a letter
dated April 15 1993 the Secretary of State did not accept that recommendation.
He cancelled the certificate issued by Maidstone and in its place certified
that if the land were not proposed to be acquired by an authority possessing
compulsory purchase powers, planning permission would have been granted,
subject to conditions, for car parking for 250 cars and for the construction of
the road, but would not have been granted for any other development. This was
the certificate which, by their application to the High Court, Maidstone sought
to quash.
Legislation
Since land
compulsorily acquired is not being bought or sold on the open market, the
assessment of compensation is necessarily a theoretical process, which is
nevertheless intended to quantify the proper value of the land to its owner who
is to be deprived of it: see for example the judgment of Scott LJ in Horn
v Sunderland Corporation [1941] 2 KB 26 CA, at p42
what [the
Act] gives to the owner compelled to sell is compensation — the right to be
put, so far as money can do it, in the same position as if his land had not
been taken from him.
The Land
Compensation Act 1961 was amended in several material respects by the Planning
and Compensation Act 1991. I shall quote the provisions of the Act as they were
worded at the time relevant in this case.
The basic
rules for the assessment of compensation are contained in sections 5 and 6 of
the Act of 1961. The rules in section 5 which are relevant in this case are:
(2) The value
of land shall, subject as hereinafter provided, be taken to be the amount which
the land if sold in the open market by a willing seller might be expected to
realise:
(3) The
special suitability or adaptability of the land for any purpose shall not be
taken into account if that purpose is a purpose to which it could be applied
only in pursuance of statutory powers, or for which there is no market apart
from … the requirements of any authority possessing compulsory purchase powers.
Section 6
reproduces, at least in part, what is called the Pointe Gourde principle
(Pointe Gourde Quarrying & Transport Co Ltd v Sub-Intendent of
Crown Lands [1947] AC 565) that is, that compensation is to be assessed
without taking into account any increase or decrease in the value of the land
acquired which results from the ‘scheme’ for which the land is being acquired.
The person or
tribunal assessing compensation obviously also needs to know what if any
development has been or would be permitted on the land if it were not to be
compulsorily acquired. The Act of 1961 contains the following relevant
provisions:
14–. (1) For the purpose of assessing compensation in respect of any
compulsory acquisition, such one or more of the assumptions mentioned in
sections fifteen and sixteen of this Act as are applicable to the relevant land
or any part thereof shall … be made in ascertaining the value of the relevant
interest …
(3) Nothing
in those provisions shall be construed as requiring it to be assumed that
planning permission would necessarily be refused for any development which is
not development for which, in accordance with those provisions, the granting of
planning permission is to be assumed; but, in determining whether planning
permission for any development could in any particular circumstances reasonably
have been expected to be granted in respect of any land, regard shall be had to
any contrary opinion expressed in relation to that land in any certificate
issued under Part III of this Act.
15–. (1) In a case where —
(a)
the relevant interest is to be acquired for purposes which involve the carrying
out of proposals of the acquiring authority for development of the relevant
land or part thereof, and
(b) on
the date of service of the notice to treat there is not in force planning
permission for that development, it shall be assumed that planning permission
would be granted … such as would permit development thereof in accordance with
the proposals of the acquiring authority…
(5) Where a
certificate is issued under the provisions of Part III of this Act, it shall be
assumed that any planning permission which, according to the certificate, would
have been granted in respect of the relevant land or part thereof, if it were
not proposed to be acquired by any authority possessing compulsory purchase
powers would be so granted …
16–. (1) If the relevant land or any part thereof … consists or forms
part of a site defined in the current development plan as the site of proposed
development of a description specified in relation thereto in the plan, it shall
be assumed that planning permission would be granted for that development.
Part III of
the Act of 1961 lays down an elaborate procedure for the certification by
planning authorities of appropriate alternative development. The provisions
which are relevant in this case are:
17 (1) Where an interest in land is proposed to be acquired by an
authority possessing compulsory purchase powers … then … either of the parties
directly concerned may apply to the local planning authority for a certificate
under this section …
(4) Where an
application is made to the local planning authority for a certificate under
this section in respect of an interest in land, the local planning authority
shall … issue to the applicant a certificate stating either of the following to
be the opinion of the local planning authority regarding the grant of planning
permission in respect of the land in question, if it were not proposed to be
acquired by an authority possessing compulsory purchase powers, that is to say
—
(a)
that planning permission for development of one or more classes specified in
the certificate … would have been granted; or
(b)
that planning permission would not have been granted for any development other
than the development (if any) which is proposed to be carried out by the
authority by whom the interest is proposed to be acquired …
(7) In
determining, for the purposes of the issue of a certificate under this section,
whether planning permission for any particular class of development would have
been granted in respect of any land, the local planning authority shall not
treat development of that class as development for which planning permission
would have been refused by reason only that it would have involved development
of the land in question … otherwise then in accordance with the provisions of
the development plan relating thereto.
Section 18
provides that where the local planning authority have issued a certificate
under section 17, either the landowner or the authority seeking to acquire the
land compulsorily may appeal to the Secretary of State against that
certificate. On such an appeal the Secretary of State shall (section 18(2)):
consider the
matters to which the certificate relates as if the application for a
certificate under section seventeen of this Act had been made to him in the
first instance, and shall either confirm the certificate, or vary it, or cancel
it and issue a different certificate in its place, as he may consider appropriate.
Section 21
provides a procedure for challenging the decision of the Secretary of State
under section 18 on the grounds that his decision is:
not within
the powers of this Act or that any of the requirements of this Act … or rules
made thereunder have not been complied with.
A person
aggrieved by the Secretary of State’s decision may make an application to the
High Court which (section 21(1)(b))
31
if satisfied
that the decision is not within the powers of this Act or that the interests of
the applicant have been substantially prejudiced by a failure to comply with
the said requirements, may quash the decision.
It was, of
course, under this provision that Maidstone made their application to the High
Court to quash the Secretary of State’s decision on the appeal to him under
section 18.
Development
plan provisions
At the
relevant dates, the development plan consisted of the Kent structure plan and
the approved Maidstone town map. The town map was, however, much out of date,
and for practical purposes it had been superseded, first, by the Maidstone and
vicinity local plan of which a draft was published in 1985, and then by the
Maidstone Borough local plan, of which drafts were published in 1989 and 1990.
The structure
plan contained two relevant policies, TR9 and TR10. These provided that
existing recreational open spaces would be safeguarded and where appropriate
new areas provided, and that facilities for sports and recreation should be
provided within easy reach of centres of population.
The town map
showed the appeal site allocated for allotment purposes and highway purposes.
In the 1985 local plan there was a policy, which was repeated in the borough
local plan of 1989 and 1990, which noted the opportunity which open sites in
the built-up area of the town presented for the provision of public open space,
and said:
In view of
the high cost of creating a new public open space, the opportunity should be
carefully examined before allowing built development on such land.
A note said,
however, that although it might be important to keep open space, a new use for
it must often be found. The plans also said specifically that the council, ie
Maidstone, would seek an adequate level of public open space and would
investigate opportunities to increase the level of public open space in areas
of shortfall as they should arise.
In his report
the inspector recorded that Maidstone had a total of 612 acres of public open
space, which exceeded the standard proposed by National Playing Fields
Association of 6 acres per 1,000 population, which would have indicated a
requirement of 462 acres. However, the site was in the north ward of the town.
If the NPFA standard were applied to that ward alone the requirement would be
some 45 acres of public open space. At the time of the inquiry there were less
than 4 acres in this ward, and the local plan provided for an addition of some
7 acres, 5.25 acres on the former playing fields of Maidstone barracks and 1.8
acres for a children’s play area on the site itself.
Inspector’s
report
In his
conclusions, the inspector considered first the desirability of the use of the
site for public open space. He noted that in the public consultation about the
local plan there was ‘no pressure from the public for enhanced public open
space/playing fields’. As between the site at Maidstone barracks allocated in
the plan for public open space and the appeal site, he expressed the view that
the barracks’ site was preferable for that use. He concluded:
Enhancement
of public open space would be wholly in accordance with local planning policy.
I do not however consider that the need to take advantage of that opportunity
is of such great moment that would rule out other sorts of development.
He then
considered in turn each of the types of development referred to in the
certificate issued by Maidstone. As to offices, he said that office development
on the appeal site would have been beneficial to meet a demand for small to
medium office premises. With regard to housing, he said:
While I do
not consider there to be an absolutely compelling case on need grounds for
residential development of the appeal site, I do think the appeal site could,
in the no-scheme world, have been considered for early development thus
enabling other sites to be allocated post–1996 rather than pre–1996 thereby
usefully assisting the five years’ supply situation.
As to an
hotel, he considered that such a development would be ‘wholly in keeping’,
though the location of the appeal site was not ideal. Finally, as to car
parking, he said:
In my opinion
250 vehicles could be accommodated on the site which could be satisfactorily
screened so as not to unacceptably harm visual amenity.
His overall
conclusion was that:
Development
of the appeal site with offices, residential, hotel and car parking would have
been beneficial in land use planning terms at all the relevant dates.
He therefore
recommended that the appeal should be dismissed and the certificate issued by
Maidstone, as local planning authority, should be upheld.
Secretary
of State’s decision
The reasoning
in the Secretary of State’s decision letter, which Mr Matthew Horton QC, for
Maidstone, challenges in his submissions in this appeal, was contained in paras
5, 7 and 8 of the decision letter dated April 15 1993.
Para 5 said:
The
Inspector’s conclusions, at paragraphs 7.2 to 7.4 of his report, with regard to
the parties’ submissions relating to the judgment of the High Court in the case
of Scunthorpe Borough Council v Secretary of State for the
Environment and others [1976] JPL 653, are noted. There are two issues to
be addressed here. The first is whether it is admissible to issue a section 17
certificate specifying development for public open space: and the second is
whether the safeguarding of a use for public open space is capable of being a proper
consideration in determining the alternative development (if any) that should
be specified in a certificate. On the first issue, the Scunthorpe judgment is
not directly relevant because in that case the land in question was being
acquired for public open space, whereas in this instance it is being acquired
in connection with a highway scheme. Instead, it is relevant to consider the
third rule for assessing compensation in section 5 of the 1961 Act, as amended
by the Planning and Compensation Act 1991. By analogy with this rule, it is
inappropriate, other than as specified in section 17(a) and (b), to issue a
certificate under section 17 for a purpose which could be realised only in
pursuance of statutory powers, or for which there is no market apart from the
requirements of any authority possessing compulsory purchase powers, because a
certificate in such terms would be meaningless. On the second issue it is noted
that the circumstances in the present appeal are distinguishable from those in
the Scunthorpe case. Use of the appeal site as public open space would not
involve the public acquisition of land, since the site is (or was at the
relevant dates) owned by the Borough Council. For this reason, it is considered
that in this instance the loss of potential public open space is capable of
being a material consideration in determining whether planning permission would
have been granted in a ‘no scheme world’ for any class of development.
In para 6, the
Secretary of State accepted the inspector’s identification of the main issues
in the appeal to him as:
Highway
considerations, loss of potential open space/playing fields and the intrinsic
merits of the certificate developments themselves.
He also agreed
with the inspector that the likely increase in road traffic resulting from the
types of development referred to in the certificate:
would not
have been sufficiently serious to have warranted the refusal of permission for
any of the classes of development specified in the certificate on highway grounds.
The Secretary
of State then expressed his conclusion on the other two issues as follows:
7. The other
conclusions of the Inspector have been very carefully considered but, in
certain respects, rather different views have been formed for the reasons which
follow. Opportunities to provide additional public open space/playing fields in
Maidstone, without incurring substantial public expenditure on land
acquisition, are very limited. Although Maidstone as a whole is well provided
with public open space/playing fields, there is a substantial shortage in the
locality of the appeal site. As the Inspector notes, this deficiency and
similar ones elsewhere have been addressed by policies and proposals in
successive development plans. Prior to the formulation of the acquisition
scheme, there was a specific proposal (RT 8) in the Maidstone and vicinity
local plan for the Borough Council to investigate the possibility of
establishing new public open space at Sandling Road Allotments. Other more
general policies called for the careful consideration of the use of disused
allotments and other open land in the urban area to rectify local open space
deficiencies. The Inspector’s conclusions with respect to the use of the
adjacent Maidstone Barracks site are noted, but it is considered that the rare
opportunity presented by the appeal site would have been vigorously
safeguarded. For the above reasons, there would have been serious planning
objections to the development of the land. These objections would have been set
aside only if they were outweighed by a very strong need for a particular class
of development. On the available evidence, the view is taken that the need for
more land for offices, housing or hotels would not have overridden the
objections. In reaching this view, full consideration has been given to the
possibility that an office development could have provided for either a new
road link to adjacent existing commercial premises or the relocation of those
premises to the appeal site, with consequent local benefits. However, for the
reasons given by the Inspector in paragraph 7.38 of his report regarding a car
park development, the view is taken that the need for additional parking
facilities would have outweighed the planning objections and that planning
permission would have been granted for such a class of development. In taking
this view, particular weight is placed on the location of the site within
walking distance of the town centre. Although this factor would make the site
attractive for a hotel or office development, for those classes of development
it is not of the same overriding importance and a greater choice of location is
possible.
8. The view
is taken, having regard to the surrounding land uses, that planning permission
would not have been granted for any other class of development for which
permission is required.
Grounds of
appeal
In the notice
of motion, the grounds for the application to quash the Secretary of State’s
decision were that he erred in law in:
1. Taking
into account as a material consideration the loss of potential public open
space;
2. Failing to
take into account that the question posed by the application for a certificate
of appropriate alternative development is to be decided on the hypothesis that
the owner of the land, the subject of the application, is willing to sell the
land;
3.
Alternatively, in relation to the decision which the Appellant would have
taken, if it is lawful to hypothesise that the Appellant would have considered
retaining the land in its ownership by:
(a) failing
to take into account the opportunity cost to the Appellant of retaining the
land and developing it as public open space;
(b) failing
to consider whether the Appellant would have permitted the development of part
of the land for public open space and part for offices, hotel and residential
development, or for accommodation of two or more thereof.
The grounds of
appeal are more extensively set out, but grounds l to 8 inclusive raise
essentially the same issues as those contained in grounds 1 and 2 of the notice
of motion to which it is therefore sufficient to refer. Grounds 9 and 10 of the
appeal are the same as ground 3(a) and (b) in the notice of motion. The issues
set out in grounds 1 and 2 of the notice of motion are the major issues in this
appeal and I therefore consider them first.
Mr Horton
argues that land used as public open space is almost invariably owned by a
local authority, ie an authority possessing compulsory purchase powers. If the
site were not owned by a local authority, it could only be used as public open
space if it were acquired by an authority possessing compulsory purchase
powers. Section 17(4) requires that in deciding what planning permission would
have been granted such an acquisition must be disregarded. Therefore in that
situation planning permission for the use of the site as public open space
would not be granted: see the decision of Sir Douglas Frank QC in Scunthorpe
Borough Council v Secretary of State for the Environment [1977] JPL
653. Up to this point, in my view, Mr Horton’s argument is correct.
The argument
continues that the Secretary of State distinguished the present case from the
facts in Scunthorpe Borough Council because:
Use of the
appeal site as POS would not involve the public acquisition of land, since the
site … was at the relevant dates owned by the BC.
He therefore
decided that the loss of potential POS was capable of being a material
consideration in determining what planning permission would have been granted
in the ‘no-scheme world’, which means, if the site had not been acquired for
the construction of the road.
Mr Horton
argues that making this distinction because the site was owned by Maidstone was
both unfair and wrong in law. It was unfair because it would result in
Maidstone obtaining less compensation than they would if they were not a local
authority. It was wrong in law because r(2) of section 5 of the Act of 1961
requires the valuer to assume that the vendors (Maidstone) are a willing
seller. Thus, for the purposes of a section 17 certificate, it must be assumed
that Maidstone are selling or have sold the site. In that factual situation, in
order to be used as public open space, the land would have had to be acquired
by another authority possessing compulsory purchase powers, which section 17(4)
requires to be disregarded. Therefore the loss of potential public open space
is not a material consideration.
As to whether
the result of the Secretary of State’s decision is unfair, opinions may differ.
Many sensible people might think that, since the site was being transferred
from one local authority to another for a public purpose, and some of the
compensation was being provided out of the national purse by way of a grant
from the Department of Transport, there was nothing unfair in the compensation
which would pass being less than the sum which would be paid to a private land
owner whose land was acquired. But in any case fairness is only relevant for
the light it sheds upon the proper interpretation of the statutory provisions.
As to whether
the Secretary of State was wrong in law, I start by expressing my firm opinion
that, unless there is something in the statutory provisions to the contrary,
the loss of potential public open space clearly was a material consideration.
There is authority for the proposition that the desirability of retaining land
in its existing use is a material consideration, and thus a valid reason for
refusing permission for any development which would conflict with that use. See
Clyde & Co v Secretary of State for the Environment [1977] 1
WLR 926* and Granada Theatres v Secretary of State for the
Environment† [1981] JPL 278, in which the late Forbes J, in
his usual trenchant way, said that:
*Editor’s
note: Also reported at [1977] 2 EGLR 148.
†Editor’s
note: Also reported at [1981] 1 EGLR 142.
he was
surprised that it should have been necessary for there to be an authority for
the proposition that in a change of use case the desirability of preserving the
existing use was a material consideration because it seemed to him so
self-evident a proposition.
In my view,
where land is open with no buildings on it, the desirability of keeping it
unbuilt upon but putting it to a different use is equally a material
consideration. I am not sure that Mr Horton argues to the contrary.
What then of
his argument that by the application of r(2) of section 5, Maidstone must be
presumed to have sold or to be selling the land? The argument may appear to
derive some support from one sentence in the judgment of Megaw LJ in Trocette
Property Co Ltd v Greater London Council (1974) 28 P&CR 408 at
p415 when he said:
In a case
which concerns compensation for the acquisition of a freehold interest in land
… no question can arise as to the special characteristics of the particular
freehold owner.
But Megaw LJ
continued:
The compensation
which falls to be paid does not vary according to whether the freehold owner
would in fact refuse to sell, if he had the choice, or whether, if he sold, he
would be likely to be a hard bargainer or a soft bargainer, or whether he would
insist on conditions which would reduce the value of the land in the hands of
the purchaser.
It is clear
that in this passage Megaw LJ was expounding r(2) of section 5. He was not
considering the present question at all.
Put shortly,
the answer to Mr Horton’s submission is that r(2) of section 5 has nothing to
do with assumptions as to planning permission at all.
Section 5 of
the Act of 1961 substantially repeats and is derived 32
from section 2 of the Acquisition of Land (Assessment of Compensation) Act
1919. Before 1919, there had grown up among statutory arbitrators who were
assessing compensation for compulsory purchase a practice of assuming that the
seller was unwilling to sell (as in fact, of course, he usually was). The
arbitrators then reflected this unwillingness in an increase in the
compensation, ie as being the amount which might tempt an otherwise unwilling
seller to become willing to sell. The enactment of r(2) of section 5 put an end
to this approach.
At that time,
if land were thought to have development value, as we now call it, the valuer
had to assess what the prospects of development were, as well as what value to
give the land with such prospects. Horn v Sunderland Corporation
is a good example of a case in which this happened.
But with the
advent of rigid planning control in 1948, and the return in 1959 to market
value as being the basis for the assessment of compensation for the compulsory
purchase of land, the need arose for a procedure for answering the valuer’s
question:
What, if any,
planning permission should I assume would be granted if there were no
compulsory purchase?
The answer is
to be found by the application of the provisions of sections 14, 15, 16 and
Part III of the Act of 1961. The rules in section 5 play no part in this
process of deciding what planning permission is to be assumed.
When the
valuer obtains an answer to the question what planning permission is to be
assumed, he can then proceed to value the land, applying the other provisions
of Part II of the Act of 1961, including where appropriate r(2) in section 5.
Tucker J seems
to have accepted a submission that r(2) did not apply to a certificate of
appropriate alternative development because sections 5 and 17 are contained in
different parts of the Act of 1961: see the passage at p15B of the transcript
of his judgment. I do not think that this of itself is an answer to Mr Horton’s
submission, but in all other respects I agree with the judge’s conclusion on
this issue. He said at p16C:
When it comes
to assessing compensation, the Lands Tribunal will assume a willing seller, but
one who is selling land for which planning permission other than for car
parking would not be available. But at this stage we are not concerned with the
actual assessment of compensation, but with the proper basis for the assessment
under the certification procedures.
In my
judgment, in this respect the learned judge was entirely correct. However, one
later sentence in the judge’s judgment, at p18 C, where the judge said that he
accepted:
that the
notion of what Maidstone would have done with the land as owners was not
relevant to a determination under section 17,
appears to
conflict with the other passage I have just quoted. This is explicable because
by p18 the judge had concluded his judgment on grounds 1 and 2 of the notice of
motion, and had turned to consider ground 3. Thus the later sentence is to be
understood in an entirely different context. Indeed the sentence itself makes
this clear because it starts with the words:
In this
connection …
Although as I
have said, these two grounds in the notice of motion have been expanded into
eight grounds of appeal, on which Mr Horton addressed us at length, all the
expanded grounds relate to, or depend upon, the issues set out in grounds 1 and
2 of the notice of motion. It is therefore unnecessary to consider them in more
detail. In so far as any of the grounds of appeal raise arguments which can
still be advanced on the assessment of compensation, if necessary before the
Lands Tribunal, I do not intend to say anything that would prevent that
happening. In relation to this appeal I say simply that for the reasons I have
sought to explain, I reject the arguments contained in grounds 1 and 2 of the
notice of motion, and in grounds 1 to 8 inclusive of the notice of appeal.
This leaves
grounds 9 and 10 of the appeal. Ground 9 relates to what is called ‘opportunity
cost’. It seems that this phrase was not used during the argument before the
inspector. However, it is clear from his report that Maidstone did make a
submission to him that if there were a need for more POS in the northern area
of the town, then:
(a) other
areas of land, unsuitable or less suitable than this site for building
development, could be acquired and used for open space purposes — see para 6.53
and 6.54 of his report; and
(b) if
planning permission were given for any of the developments specified in the
certificate, that would result in a payment to Maidstone which could then be
used to acquire other land for use as public open space and/or for other public
projects: see paras 6.63 and 6.64 of the report.
Since he
recommended that permission would be granted for the certificate developments,
the inspector did not make a direct recommendation on this argument.
However, in
para 7 of the decision letter the Secretary of State said:
On the
available evidence, the view is taken that the need for more land for offices,
housing or hotels would not have overridden the objections. In reaching this
view, full consideration has been given to the possibility that an office
development could have provided for either a new road link to adjacent existing
commercial premises or the relocation of those premises to the appeal site,
with consequent local benefits.
It is
therefore clear that the Secretary of State did consider that aspect of the
‘opportunity cost’ argument and reached a conclusion upon it.
Mr Horton
argues that his reasoning on this issue is not sufficiently clear. This is only
a ground of challenge under section 21 as a breach of the relevant rules of
procedure, which require the Secretary of State to give reasons. It can only
succeed if, to refer back to section 21, ‘the interests of (Maidstone) have
been substantially prejudiced by a failure to comply with’ the rules in this
respect. In his speech in Save Britain’s Heritage v Number 1 Poultry
Ltd [1991] 1 WLR 153 at p167E-H, Lord Bridge of Harwich defined the various
ways in which an applicant for planning permission or a local authority
respondent may be prejudiced by a failure to give reasons. Although Maidstone
are understandably disappointed by the Secretary of State’s decision in this
case, I cannot conclude that they are prejudiced by any inadequacy in his
reasoning in this respect.
This leaves
ground 10. As to this Tucker J said at p20:
This ground
relates to the allegation that the Secretary of State did not consider the
possibility of part of the land being developed, and part being used as POS.
The submission under this head was refreshingly brief. It was that after
deciding that the POS/playing fields objections would have overridden the
certified developments, the Secretary of State did not consider the possibility
of part of Maidstone’s land being developed and part being used as POS.
It is clear
to me from the decision letter that the Secretary of State was fully aware of
the findings made by the inspector and of the arguments put forward at the
inquiry. I very much doubt whether the matters raised under this ground
featured prominently in those arguments. In my opinion, there was no necessity
for the Secretary of State to make express reference to them. The absence of
such a reference does not mean that they were not considered. There is in my
opinion nothing in this ground.
I, too, doubt
whether these matters featured prominently in the argument at the inquiry. But
I am of the view that it is clear that the Secretary of State did consider the
issue. His certificate is for permission for car parking for 250 cars, which
would only occupy a relatively small part of the site. In relation to the
balance of the site, he clearly rejected the proposal for planning permission
for offices, housing or an hotel — for any form of built development — because
of the importance in his view of the loss of potential open space. Therefore
his reasoning adequately covers the possibility of planning permission being
granted partly for POS and partly for some other form of built development. I
would therefore reject this argument also.
33
For these
reasons I conclude that Tucker J came to a correct decision on all the
arguments advanced to him and raised in this appeal, which I would therefore
dismiss.
Morritt LJ
and Sir John May agreed and did not add anything.
Appeal
dismissed.