Back
Legal

JA Pye (Oxford) Ltd v Kingswood Borough Council

Compensation for the acquisition of land — Completion of link road — Ransom value to development site — Whether Lands Tribunal made perverse finding as to scheme — Whether tribunal overlooked terms of acquisition agreement imposing differing inhibition on development

In 1979 the
appellant entered into an agreement with the county and district councils under
section 52 of the Town and Country Planning Act 1971 in relation to the
proposed development of an extensive site. That agreement provided that the
appellant would construct a link road. One clause of the agreement provided
that only 40% of the industrial development land could be developed at all
before the link road was completed and another clause that the residential
development contemplated by the appellant’s then current planning applications
was inhibited before the link road was completed. The link road had been first
proposed by the county council in a 1971 development brief; it was seen by the
highway authority as having substantial highway advantages. In July 1979
planning permission was granted for the site that contained conditions
restricting development pending the completion of the link road similar to the
section 52 agreement. By January 1988 the appellant had constructed two parts
of the link road; only some 25m of road through the reference land remained
unbuilt. On January 13 1988 the respondent authority contracted to sell the
reference land to the county council at a price to be determined by the Lands
Tribunal on the following assumptions: that an unopposed compulsory purchase
order had been made for highway purposes, and that possession had been taken on
January 13 1988. The 1988 agreement permitted the appellant to act for the
county council in valuation proceedings. The Lands Tribunal found, as a fact,
‘that the scheme or project for the furtherance of which the reference land was
acquired was the completion of construction of the link road … The ‘scheme’ is
the completion of the link road by acquiring the reference land’. The tribunal
determined the open market value of the reference land at £756,500. The
appellant appealed, contending that: the tribunal failed to appreciate the
distinction between the acquisition and the scheme underlying the acquisition;
the only reasonable finding for the tribunal was that the link road as a whole
was the reason for the acquisition of the reference land; and, in arriving at
the 25% share of the development value unlocked by the reference land, the
tribunal had failed to distinguish between the two separate provisions of the
1979 agreement that inhibited development until the link road was completed.

Held: The appeal was allowed in part. While the ‘scheme’ cannot be the
acquisition itself, the tribunal did not so hold. The tribunal held that the
scheme was the completion of the link road. The tribunal was not perverse in
its finding that the scheme did not include the whole of the link road. A
finding by a tribunal is not perverse just because a possible alternative was
open to the tribunal but not adopted by it. The actual decision in Batchelor
v Kent County Council [1990] 1 EGLR 32 establishes no more than that it
is a question of fact as to whether the underlying scheme as found enhanced the
value of the acquired land. The tribunal had applied that fact-finding
exercise. However, the tribunal appeared to have overlooked that the two
separate clauses in the section 52 agreement imposed different inhibitions on
development pending the completion of the link road.

Start your free trial today

Your trusted daily source of commercial real estate news and analysis. Register now for unlimited digital access throughout April.

Including:

  • Breaking news, interviews and market updates
  • Expert legal commentary, market trends and case law
  • In-depth reports and expert analysis

Up next…