JA Pye (Oxford) Ltd v Kingswood Borough Council
HOBHOUSE, SWINTON THOMAS and BUXTON LJJ
Compensation for the acquisition of land — Completion of link road — Ransom value to development site — Whether Lands Tribunal made perverse finding as to scheme — Whether tribunal overlooked terms of acquisition agreement imposing differing inhibition on development
In 1979 the
appellant entered into an agreement with the county and district councils under
section 52 of the Town and Country Planning Act 1971 in relation to the
proposed development of an extensive site. That agreement provided that the
appellant would construct a link road. One clause of the agreement provided
that only 40% of the industrial development land could be developed at all
before the link road was completed and another clause that the residential
development contemplated by the appellant’s then current planning applications
was inhibited before the link road was completed. The link road had been first
proposed by the county council in a 1971 development brief; it was seen by the
highway authority as having substantial highway advantages. In July 1979
planning permission was granted for the site that contained conditions
restricting development pending the completion of the link road similar to the
section 52 agreement. By January 1988 the appellant had constructed two parts
of the link road; only some 25m of road through the reference land remained
unbuilt. On January 13 1988 the respondent authority contracted to sell the
reference land to the county council at a price to be determined by the Lands
Tribunal on the following assumptions: that an unopposed compulsory purchase
order had been made for highway purposes, and that possession had been taken on
January 13 1988. The 1988 agreement permitted the appellant to act for the
county council in valuation proceedings. The Lands Tribunal found, as a fact,
‘that the scheme or project for the furtherance of which the reference land was
acquired was the completion of construction of the link road … The ‘scheme’ is
the completion of the link road by acquiring the reference land’. The tribunal
determined the open market value of the reference land at £756,500. The
appellant appealed, contending that: the tribunal failed to appreciate the
distinction between the acquisition and the scheme underlying the acquisition;
the only reasonable finding for the tribunal was that the link road as a whole
was the reason for the acquisition of the reference land; and, in arriving at
the 25% share of the development value unlocked by the reference land, the
tribunal had failed to distinguish between the two separate provisions of the
1979 agreement that inhibited development until the link road was completed.
Held: The appeal was allowed in part. While the ‘scheme’ cannot be the
acquisition itself, the tribunal did not so hold. The tribunal held that the
scheme was the completion of the link road. The tribunal was not perverse in
its finding that the scheme did not include the whole of the link road. A
finding by a tribunal is not perverse just because a possible alternative was
open to the tribunal but not adopted by it. The actual decision in Batchelor
v Kent County Council [1990] 1 EGLR 32 establishes no more than that it
is a question of fact as to whether the underlying scheme as found enhanced the
value of the acquired land. The tribunal had applied that fact-finding
exercise. However, the tribunal appeared to have overlooked that the two
separate clauses in the section 52 agreement imposed different inhibitions on
development pending the completion of the link road.
Compensation for the acquisition of land — Completion of link road — Ransom value to development site — Whether Lands Tribunal made perverse finding as to scheme — Whether tribunal overlooked terms of acquisition agreement imposing differing inhibition on development
In 1979 the
appellant entered into an agreement with the county and district councils under
section 52 of the Town and Country Planning Act 1971 in relation to the
proposed development of an extensive site. That agreement provided that the
appellant would construct a link road. One clause of the agreement provided
that only 40% of the industrial development land could be developed at all
before the link road was completed and another clause that the residential
development contemplated by the appellant’s then current planning applications
was inhibited before the link road was completed. The link road had been first
proposed by the county council in a 1971 development brief; it was seen by the
highway authority as having substantial highway advantages. In July 1979
planning permission was granted for the site that contained conditions
restricting development pending the completion of the link road similar to the
section 52 agreement. By January 1988 the appellant had constructed two parts
of the link road; only some 25m of road through the reference land remained
unbuilt. On January 13 1988 the respondent authority contracted to sell the
reference land to the county council at a price to be determined by the Lands
Tribunal on the following assumptions: that an unopposed compulsory purchase
order had been made for highway purposes, and that possession had been taken on
January 13 1988. The 1988 agreement permitted the appellant to act for the
county council in valuation proceedings. The Lands Tribunal found, as a fact,
‘that the scheme or project for the furtherance of which the reference land was
acquired was the completion of construction of the link road … The ‘scheme’ is
the completion of the link road by acquiring the reference land’. The tribunal
determined the open market value of the reference land at £756,500. The
appellant appealed, contending that: the tribunal failed to appreciate the
distinction between the acquisition and the scheme underlying the acquisition;
the only reasonable finding for the tribunal was that the link road as a whole
was the reason for the acquisition of the reference land; and, in arriving at
the 25% share of the development value unlocked by the reference land, the
tribunal had failed to distinguish between the two separate provisions of the
1979 agreement that inhibited development until the link road was completed.
Held: The appeal was allowed in part. While the ‘scheme’ cannot be the
acquisition itself, the tribunal did not so hold. The tribunal held that the
scheme was the completion of the link road. The tribunal was not perverse in
its finding that the scheme did not include the whole of the link road. A
finding by a tribunal is not perverse just because a possible alternative was
open to the tribunal but not adopted by it. The actual decision in Batchelor
v Kent County Council [1990] 1 EGLR 32 establishes no more than that it
is a question of fact as to whether the underlying scheme as found enhanced the
value of the acquired land. The tribunal had applied that fact-finding
exercise. However, the tribunal appeared to have overlooked that the two
separate clauses in the section 52 agreement imposed different inhibitions on
development pending the completion of the link road.
The following
cases are referred to in this report.
Batchelor v Kent County Council (1989) 59 P&CR 357; [1990] 1 EGLR
32; [1990] 14 EG 129; RVR 181; [1990] JPL 571, CA
Camrose
(Viscount) v Basingstoke Corporation [1966]
1 WLR 1100; [1966] 3 All ER 161; (1966) 64 LGR 337, CA
Hertfordshire
County Council v Ozanne [1989] 2 EGLR 18;
[1989] 43 EG 182; [1989] RVR 179, CA
Myers v Milton Keynes Development Corporation [1974] 1 WLR 696;
[1974] 2 All ER 1096; (1974) 72 LGR 420; 27 P&CR 518; [1974] EGD 405; 230
EG 1275, CA
Pointe
Gourde Quarrying & Transport Co Ltd v Sub-Intendent
of Crown Lands [1947] AC 565, PC
Wards
Construction (Medway) Ltd v Barclays Bank plc
(1994) 68 P&CR 391; [1994] 2 EGLR 32; [1994] 40 EG 135, CA
Wilson v Liverpool Corporation [1971] 1 WLR 302; [1971] 1 All ER
628; (1971) 22 P&CR 282; [1971] EGD 144; 217 EG 987, CA
This was an
appeal by JA Pye (Oxford) Ltd by way of case stated from a decision of the
Lands Tribunal in a reference by consent to determine the purchase price of
land contracted to be sold by the respondents, Kingswood Borough Council, to
Avon County Council.
Robin Purchas
QC and John Harvey (instructed by Burroughs Day, of Bristol) appeared for the
appellant; Christopher Cochrane QC and Adrian Trevelyan-Thomas (instructed by
Sharpe Pritchard) represented the respondents.
Giving the
first judgment, BUXTON LJ said: This appeal concerns the valuation by
the Lands Tribunal of a small area of land (the reference land), a mere 276m2
under a transfer from the respondents (Kingswood) as vendors to Avon County
Council (Avon) as purchasers. The local authorities just mentioned, and other
local authorities that became involved in the matter, now have different names,
or have been reorganised into different authorities, from those that obtained
during the period with which we are concerned. Nothing turns on those changes
of name or structure. The actual appellant, JA Pye (Oxford) Ltd (Pye), is a
developer who is involved in these proceedings and in this appeal because it
was in connection with a development undertaken by Pye that Avon entered into
the transfer agreement. That agreement provided that in the reference to the
Lands Tribunal, whereby the purchase price was to be determined, Pye would be
permitted to act on behalf of Avon.
In that
reference, from the determination in which this appeal is brought, the Lands
Tribunal valued the reference land at £756,500. On the basis of assumptions
unsuccessfully urged before it by Pye, the Lands Tribunal would have valued the
reference land at £650, and it is that figure that Pye says should be
substituted by this court. Pye has a further and subsidiary ground of appeal,
to the effect that if it fails on 160
its main ground, and it is held that the Lands Tribunal adopted the correct
approach, nevertheless the tribunal erred in applying that approach in one
particular respect or, alternatively, did not sufficiently explain its
reasoning on that point. Pye submits that the decision should in any event be
remitted to the Lands Tribunal on that issue.
I set out the
background facts as shortly as is possible for the understanding of the issues
in the case.
General
area and its development
The case has
as its setting plans for the development, and the actual development, of a
substantial area of land on the outskirts of Bristol; proposals that date back
to as long ago as 1970. Although by no means all of the area was owned by Pye,
I will for convenience call it the Pye land. The Pye land extends towards the
A420 London/Chippenham Road to its north, and to open land to its south. More
precisely, the Pye land is bounded to its east by the A4175 Bath Road, and to
its west by a disused railway line, running approximately south to north-west.
To the west of that railway line lay a substantial area, centred on the village
of Warmely, that had been the subject of extensive additional residential
development in the 1960s and early 1970s. A road called Mill Lane ran from
Warmley Village towards the southern end of the Pye land. Some way short of the
railway line, and thus short of the Pye land, Mill Lane divided at a junction
into two roads, both of which continued in a generally easterly direction
across the railway and across the Pye land, and eventually into Bath Road. Of
those roads, Poplar Road ran north-eastwards from the junction, crossed the
railway by a bridge and ended in Bath Road. Victoria Road ran due east from the
road junction until very shortly before the railway, when it turned south-east,
again crossed the railway by a bridge, and equally ended in Bath Road.
In February
1970 Gloucestershire County Council, as the planning authority responsible for
the structure plan, published the Bristol East Fringe study, which identified
as suitable for development two very substantial parts of the Pye land. A
development brief published in 1971 in connection with those proposals
envisaged a new link road between Victoria Road, as it ran through the area
already under development west of the railway line, and Bath Road. That road
(the link road) would start from Victoria Road at the point where that road
turned south-eastwards before the railway line, and would run virtually due
east from there across the railway line to connect directly with Bath Road. It
would cross the railway line at the point where the reference land is located,
the latter land forming part of that former railway line. The development brief
envisaged that the part of Pye land south of the link road would be devoted to
industrial use; the part of the Pye land area north of the link road to
residential use.
Pye strongly
urged in the appeal before us that the construction of the link road was always
regarded as a general highways project. The link road was seen by the highway
authority as having substantial highway advantages in eliminating the
substandard railway bridge and the substandard entry on to the Bath Road of the
original access to Bath Road via Victoria Road. As a means of access it would
principally benefit the residential development west of the railway line, which
was not on any part of the Pye land nor part of the Pye development. To the
extent that, as became the case, construction of or contribution to the link
road was an obligation of Pye, that requirement thus had a strong element of
‘planning gain’, as opposed to being required to provide access to, or even to
facilitate, the Pye development. I did not understand that analysis to be
substantially contested by the respondents.
Pye’s
planning applications
Between 1971
and 1974 Pye purchased the greater part of the area identified for development
in the Bristol East Fringe study; which thus became ‘the Pye land’. In April
1973 Pye submitted a planning application (SG1180) for the development of the
Pye land, the proposals being in accordance with the 1971 development brief.
The then highway authority agreed to provide the link road. It was, however,
envisaged that in connection with that provision Pye would construct that part
of the link road that ran through its site from the railway to the Bath Road.
In June 1973
the then planning authority resolved to grant planning approval for application
SG1180, subject to Pye giving undertakings with regard to the off-site
roadworks and the provision, as part of the scheme, of public open spaces. That
proposal was confirmed by Kingswood as the new planning authority after local
government reorganisation in 1974. However, the permission was conditional on
the completion of the procedures to implement Pye’s undertakings, which
included the signing of an agreement under section 19 of the Gloucestershire
County Council Act 1956. Avon, the successors to that council, apparently
refused to contemplate such an agreement unless it was entered into by the
owners of all the land affected by the undertakings. That included the
reference land which, as part of a disused railway, was owned by British
Railways Board (BRB).
Pye agrees
to construct the whole of the link road
While attempts
were being made to resolve this impasse, there was a meeting between officers
of Kingswood and Avon and Pye on September 1 1977, at which Avon said that they
had no funds, and no prospect of funds, for highway construction. Pye thereupon
agreed to undertake the construction of the link road west of the railway line,
as well as east of the railway line, and acquired land west of the railway line
for that purpose. A new planning application, K448/11, was then submitted, on
November 8 1977. That differed from SG1180, and from other applications only
slightly modifying SG1180 that had been submitted in the interim, in that it
showed the whole of the part of the Pye land south of Poplar Road as an
industrial area, the part of the Pye land north of Poplar Road being allocated
to residential development. In a letter to Kingswood of November 15 1977
accompanying the proposal, Pye said that in view of the increased cost to them
of the road improvements (which included some matters other than the link road
itself) that had previously been regarded as being the financial responsibility
of Avon, the scheme would not be viable unless permission was granted for the
whole of the development, including all the residential development.
Planning
permission was however refused for all Pye’s applications. Pye appealed. In the
meantime, Avon had been advised that the undertakings sought from Pye were too
extensive to be secured merely by planning conditions, and therefore sought an
agreement between Avon, Kingswood and Pye under section 52 of the Town and
Country Planning Act 1971. That agreement (the section 52 agreement) was
entered into on July 19 1979; a draft of it was placed before the inspector at
the inquiry into the refusal of Pye’s planning applications.
The section 52
agreement was all subject to the grant of permission on any of Pye’s
applications (clause 1). So far as is relevant to the present appeal, it
provided that an area of the old railway, including the reference land, was
owned by BRB, who were in negotiation for its sale to Kingswood (recital 3); if
it appeared that either Kingswood or Pye would not be able to acquire the
reference land, or to acquire it sufficiently promptly to permit the
development to proceed according to its programme, Avon would use their best
endeavours to acquire the reference land, and would be reimbursed by Pye for
the cost thereof (clause 6); Pye would construct the link road within three
years of planning permission being granted on its applications or, if by then
the reference land was not available to Pye, would by that date construct the
link road apart from that part crossing the reference land (clause 7); only 40%
of the land south of Poplar Road would be permitted to be developed by Pye
before the completed link road had been dedicated to public vehicular traffic
(clause 9). By a further provision, clause 15, limitations were placed on Pye’s
development of the land north of Poplar Road, intended for residential
development, until the link road had been completed. The exact terms of this
clause affect a particular issue in the appeal, and I will therefore return to
them in more detail later in this judgment.
With regard to
clause 6 of the agreement, it is to be noted that no specific reference is made
to the use by Avon of compulsory purchase 161
powers in acquiring the reference land; though no doubt, and Pye gave evidence
before the Lands Tribunal to the effect that, the availability of that power on
the part of Avon was well in the minds of the parties to the agreement.
Further, Pye placed emphasis before us on a further section 52 agreement,
entered into between itself and Avon in October 1979, relating to the industrial
land only, in which the obligations in the section 52 agreement were
reinforced. I do not however see, any more than did the Lands Tribunal, that
the October 1979 agreement added anything to the position relevant to this
appeal that was already established by the section 52 agreement of July 1979,
and, like the Lands Tribunal, I will continue to refer principally to that
latter agreement.
On July 23
1979 the Secretary of State allowed Pye’s appeal in respect of application
K448/11, subject to conditions. The conditions relevant to the present matter
were (condition c, echoing clause 9 of the section 52 agreement) that no more
than 40% of the industrial development (south of Poplar Road) should be brought
into use until the link road had been completed to the satisfaction of the
local planning authority; and (condition g, echoing clause 15 of the section 52
agreement) that the development of the land north of Poplar Road should not be
commenced before the completion of the link road.
Pye’s
acquisition of the reference land
This grant of
permission fulfilled the precondition for the operation of the section 52
agreement. On January 22 1982 Kingswood purchased from BRB, for £5, six miles
of the old railway, including the reference land. There were, however, further
difficulties about the progress of the development, including the need for
further applications for planning permission. Pye wrote to Kingswood on August
8 1986 acknowledging that the section 52 agreement remained in force. That
agreement was, by consent of the original parties, amended on September 30 1987
to take account of the new applications and to offset the delay in starting the
development. Prior to that Kingswood had written to Pye’s solicitors in January
1987 acknowledging that Pye and Kingswood had been in dispute for some time as
to the sum to be paid by Pye for acquiring the reference land from Kingswood,
and recording that Kingswood were now negotiating with Avon for the transfer of
the reference land to Avon in accordance with clause 6 of the section 52
agreement.
On January 13
1988 Kingswood entered into a contract (the 1988 agreement) to sell to Avon the
freehold interest in the reference land, the agreement reciting in clause I
that it was made to enable the development contemplated by the section 52
agreement to be carried out. The 1988 agreement further provided that the
purchase price was to be determined by a reference to the Lands Tribunal, in
which reference it would be assumed that Avon had made an unopposed compulsory
purchase order for the acquisition of the reference land for highway purposes.
That is the reference with which this appeal is concerned. Pye was not formally
a party to the 1988 agreement, but, as we have seen, the agreement provided
that Pye should be permitted to act on behalf of Avon in the valuation
proceedings.
The valuation
date under that reference was January 13 1988. On that date Pye had already
constructed the link road to adoptable standards from the railway line
eastwards to the Bath Road, and also from the railway line westwards to the
junction with Victoria Road. The link road was therefore complete, apart from
the short section, no more than some 25m long, as yet unbuilt, crossing the
reference land. Since the valuation date Pye has completed the link road across
the reference land and it is open to traffic for its entire length. Pye has
also proceeded with its industrial and residential development.
Reference
to the Lands Tribunal
The function
of valuing the reference land was conferred on the Lands Tribunal by an agreed
reference made by the parties under the 1988 agreement. That agreement recited,
as we have seen, that the transfer of the reference land from Kingswood to Avon
was to enable the development contemplated by the section 52 agreement to be carried
out. The parties to the 1988 agreement further agreed that in the reference the
Lands Tribunal should assume that Avon had made an unopposed compulsory
purchase order for the purchase of the reference land for highway purposes and
had taken possession of the reference land on the date of the 1988 agreement,
that is to say on January 13 1988. The Lands Tribunal accordingly considered
that it was obliged to apply to this case of deemed compulsory purchase the
general rules applying to valuation on compulsory acquisition of land,
including that:
(i) the
valuation should be the amount that a willing seller of the reference land
would have achieved in the open market on January 13 1988;
(ii) any
increase in such valuation that was attributable to the underlying purpose of
the acquisition should be disregarded.
These general
principles have not been disputed before us. Their proper application to the
facts of this case has been the subject of strenuous disagreement. The second
principle is that which is conventionally known as the Pointe Gourde
rule or principle. Since it is that principle that is the source of the dispute
in this case, and which produces the very striking difference in valuation
terms between the parties, it will be convenient to set out the law binding us
as to its content and application before dealing further with the Lands
Tribunal’s determination.
Pointe
Gourde principle
In Pointe
Gourde Quarrying & Transport Co Ltd v Sub-Intendant of Crown Lands
[1947] AC 565, at p572, the House of Lords said:
It is well
settled that compensation for the compulsory acquisition of land cannot include
an increase in value which is entirely due to the scheme underlying the
acquisition.
In Wards
Construction (Medway) Ltd v Barclays Bank plc (1994) 68 P&CR 391*,
at p396, this court, per Nourse LJ, summarised the way in which that
principle should be applied in practice:
*Editor’s
note: Also reported at [1994] 2 EGLR 32; [1994] 40 EG 135
In order
correctly to apply the Pointe Gourde principle it is necessary, first,
to identify the scheme and, secondly, its consequences. The valuer must then
value the land by imagining the state of affairs, usually called ‘the no-scheme
world’, which would have existed if there had been no scheme.
How in this
process the ‘scheme’ is to be identified was explained by this court in Wilson
v Liverpool Corporation [1971] 1 WLR 302, in particular in the judgment
of Widgery LJ, at p310A:
Whenever land
is to be compulsorily acquired, this must be in consequence of some scheme or
undertaking or project. Unless there is some scheme or undertaking or project,
compulsory powers of acquisition will not arise at all, and it would, I think,
be a great mistake if we tended to focus our attention on the word ‘scheme’ as
though it had some magic of its own. It is merely synonymous with the other
words to which I have referred, and the purpose of the so called Pointe
Gourde rule is to prevent the acquisition of the land being at a price
which is inflated by the very project or scheme which gives rise to the
acquisition.
The extent of
the scheme is a matter of fact in every case, as is shown by the decision in Fraser
v Fraserville City [1917] AC 187 to which Lord Denning MR has referred.
It is for the tribunal of fact to consider just what activities — past, present
or future — are properly to be regarded as the scheme within the meaning of
this proposition.
It was not
contested before us that that guidance given by Widgery LJ applies to this
case.
‘Ransom
value’ of the reference land
The dispute,
and the importance to the dispute of the Pointe Gourde principle, is
best introduced by pointing to the feature of the reference land that was
alleged to give it the very substantial value found by the Lands Tribunal.
In the actual
world as it existed on January 13 1988 there was, in the open market, a
purchaser who would, as found by the tribunal, have been prepared to pay a
premium or ransom value for the reference land. That purchaser was Pye, or any
owner of the Pye land 162
who was the beneficiary of the planning permission that attached to that land.
The tribunal put it thus, at p69 of its determination:
We are not in
doubt that at the valuation date (January 13 1988) the reference land possessed
a premium value in the hands of the vendors. By that date, the construction of
the link road had been carried out to east and west, and possession of the
strip which is the reference land was necessary in order to complete the link.
By reason of the 1979 agreement and the conditions imposed by the Secretary of
State on the grant of planning permission, Pye (or indeed any owner of the Pye
land) could not develop 60% of the industrial area nor carry out any of the
residential development in the area north of Poplar Road until the link road
was completed. Thus the reference land was the key to this development.
Such a person
would have been prepared to pay a very large price for the reference land, far
in excess of its value to any other purchaser, in order to unlock or ‘ransom’
the value of the Pye land, which, by the terms of the section 52 agreement and
of the planning permission, could not be developed until the owner of the Pye
land had completed the link road, for which he must have the reference land.
Unless, therefore, the hypothetical open market that the tribunal had to
assume excluded that purchaser, it would be obliged to award the vendor the
price that that purchaser would be willing to pay.
Hence the
importance of Pointe Gourde. Pye argued that the purchaser willing to
pay a ransom price had to be excluded because the ransom price was generated
by, and was attributable to, the scheme underlying the acquisition of the
reference land. That ‘scheme’ was, according to Pye, the construction of the
link road, as a highway scheme, which had been envisaged as such, in very much
the same terms, since the original development brief in 1971, and whose
construction was the underlying purpose of the acquisition of the reference land.
The section 52 agreements and the conditions in the planning permission that
had been found by the tribunal to have created the ransom value could not be
looked at independently of that scheme, because they only came into existence
because of the prior existence of the scheme. Pointe Gourde therefore
required that the ‘no-scheme world’ in which the reference land had to be
valued was a world in which the link road did not exist, and, therefore, in
which, of necessity, the section 52 agreements and the conditions in Pye’s
planning permission did not exist either. On that hypothesis the reference land
had no ransom value.
Lands
Tribunal’s decision: the ‘scheme’
The tribunal
dealt with this contention originally in comparatively brief terms at p69 of
its determination. It set out the steps to be taken in applying the Pointe
Gourde principle as summarised in Wards Construction and then said:
We find as a
fact that the scheme or project for the furtherance of which the reference land
was acquired was the completion of construction of the link road … The ‘scheme’
is the completion of the link road by acquiring the reference land.
For my part, I
would think that that finding of fact by the tribunal was, in any event,
conclusive against Pye’s contentions. The tribunal found, in terms that in
themselves have not been challenged, that the actual ransom value of the
reference land sprang from the existence of the section 52 agreement. That
agreement was made in 1979 and extended in 1987, in both cases well before the completion
of the link road by the steps adopted in 1988 was contemplated. Similarly, the
planning permission that required the link road to be completed dated from
1979. Neither as a matter of chronology nor as a matter of logic could it be
said that the value of the reference land that was conferred by the existence
of the section 52 agreement and the conditions in the planning permission was
due, let alone entirely due, to the scheme as found by the tribunal.
The tribunal
did not, however, leave the matter there, but reasoned the matter out more
fully in the light of the facts of the case, at pp70–71 of the determination:
What is known
as the Pye industrial land was identified by the planning authorities as
suitable for development originally in the study, and in the 1971 development
brief there first appeared a proposed ‘link road’ between Bath Road and
Victoria Road in the approximate position of the road that has now been built.
Had the highway authority at that stage taken steps to obtain the land to
construct such road, then doubtless the Pointe Gourde principle would
have applied to restrict the value to the owner or owners of the land taken so
as to prevent them from benefitting from the scheme underlying that
acquisition, namely the project to open up this large area of Bridge Yate to
development. That, however, is not what happened. The sequence of events
following upon the entry of Pye on to the scene in about 1970–1971 is set out
in great detail in the planning inspector’s report to the Secretary of State
dated December 11 1978 and need not be repeated here. In essence the intention
of the authorities to construct the link road had by 1978 been abandoned on a
change of policy by Avon; instead of seeking contributions where possible
towards the cost of highway construction by the council, it became the policy
of Avon that the cost of highway works directly required by a development be
met by the developer. It was as a direct consequence of this policy that Pye
was unable ultimately to obtain planning permission for industrial development
of the land south of Poplar Road and residential development of the area north
of Poplar Road without undertaking the construction at Pye’s expense of the
link road. The inference from the attitude of the planning and highway
authorities at that time must be that the link road was considered by them to
be ‘directly required’ for the purpose of industrial development of Pye’s land.
Hence the entry by Pye into the section 52 agreement dated 19 July 1979 under
which development of 60% of the industrial land and all the proposed
residential development north of Poplar Road was prohibited unless and until
Pye had constructed the link road. We accept Mr Cochrane’s submission that
planning permission for any development would not have been granted unless Pye
undertook to build the link road. That seems clear from the inspector’s
recommendation that execution of the agreement ‘should be a prerequisite of any
planning permission’ and from the fact that the Secretary of State imposed
conditions on the grant of planning permission to the same effect.
In our
judgment, it was the obligations thus undertaken by Pye that conferred a
premium value on the reference land. The owner of the former railway line was
at that point in time in a position to hold to ransom any owner of the Pye land
seeking to develop that land to its full potential and to proceed with
residential development on the land north of Poplar Road. It is clear to us
that the obligation and its effect in creating a premium value was not
attributable to any scheme of the authorities to construct a link road, but was
attributable to the needs of Pye to obtain the land and build the link road in
order to develop the Pye land fully. In other words, the premium value of the strip
of railway land was not entirely due to any scheme or project underlying the
acquisition. It was due at least primarily to the fact that acquisition of the
strip was the key which unlocked the development value latent in the Pye land,
and similarly in the land owned by Pye, north of Poplar Road.
So viewed, it
will be noted, the tribunal considered that the premium value of the reference
land was not entirely due to any scheme or project underlying the
acquisition; it does not appear to have confined itself to the scheme as found
by them.
Pye’s
attack on the tribunal’s finding as to the ‘scheme’
Mr Robin
Purchas QC, for Pye, frankly recognised that he was faced with a serious
problem, in that he had to displace the tribunal’s finding, held by this court
in Wilson v Liverpool Corporation and other cases to be a finding
of fact, that the relevant scheme for the purposes of applying Pointe Gourde
was the completion of the link road. I deal later with the implications
of Mr Purchas’ positive case as to the identification of the ‘scheme’ that I
have already set out in summary. Here I address his criticisms of the
tribunal’s finding.
Mr Purchas
argued that the tribunal’s decision was flawed on two separate grounds. First,
the tribunal had erred in law in failing to appreciate the distinction between
the acquisition and the scheme underlying the acquisition. Second, the decision
was perverse, because given that the link road had been a proposal since 1971,
the only reasonable finding for the tribunal was that the link road as a whole
was the reason for the acquisition of the reference land.
As to the
first of these criticisms, I agree that the ‘scheme’ cannot be the acquisition
itself. So to hold would not only be logically inconsistent with Pointe
Gourde, but also inconsistent with statements, such as that in Wilson
and in Pointe Gourde itself, that the scheme must underlie the
acquisition. But that is not what the tribunal did hold. It held in terms that
the scheme for the furtherance of which the land was acquired was the
completion of the link road. The acquisition was 163
a necessary precondition to that completion, but on no view was it, or was it
held by the tribunal to be, the same thing as the scheme of completion.
As to the
second criticism, it is, in my view, quite impossible to contend that the
tribunal was perverse in its finding. I venture to suggest that lying behind
the persistent view that such findings are ones for the tribunal of fact is the
realisation that the tribunal of fact is a specialist and expert tribunal, well
able to understand the realities of a complicated factual and transactional
situation such as the present. No doubt the tribunal could have found that the
scheme was the whole of the link road plan, as Pye urged, but it did not do so.
But a finding by a tribunal such as the present cannot be shown to be perverse
just because a possible alternative was open to the tribunal but not adopted by
it.
That, in my
view, is sufficient to dispose of this point. There is, in addition, a further
consideration. I have demonstrated that in determining the second question that
it posed itself under Pointe Gourde, whether any increase in value of
the reference land was wholly attributable to the scheme, the tribunal did not
stop short at the logical implications of a finding that the scheme was the
completion of the link road, but explained how the particular situation of Pye
caused the accretion of value to the reference land. Although the tribunal did
not say so in terms, the implication of its reasoning, set out above, is that
the completion of the link road that it was discussing was the completion of
that road by Pye. Mr Purchas said that such an approach was not open to
the tribunal, because it infringed the principle that once the scheme had been
identified, the fact that it was implemented by a different person was
irrelevant. That argument, as applied in this case, however, presupposes what
it seeks to establish, that the ‘scheme’ was the link road proposal, unchanged
since 1972. But the tribunal found otherwise, in the substantial passage
analysing the implications of the change of policy on Avon’s part in 1977 that
I have cited above. So to find, and to find that the obligations undertaken by
Pye that conferred the premium value on the reference land sprang from that
change of policy, was very well within the vires of the tribunal as a
fact-finding body.
‘Scheme’
as contended for by Pye
I have already
indicated that Pye argued that the relevant scheme was, and could only be, the
link road proposal as originally formulated in 1971. Mr Purchas argued that if
that were the scheme, the sequential approach as set out in Wards
Construction required the valuation exercise to be conducted in a no-scheme
world. In that no-scheme world there was no link road, and therefore, of
necessity, no obligation on Pye to construct such a road. In such a world, the
section 52 agreement that created the premium value simply did not exist.
I am minded to
accept that, granted the premise of this argument, its conclusions follow. They
would, if adopted, demonstrate an artificiality striking even by the standards
of the jurisprudence of valuation: not least because they would oblige the
tribunal, in conducting the valuation exercise imposed on it by the 1988
agreement, to assume the non-existence of the section 52 agreement, even though
the 1988 agreement had recited that it had been made in order to enable the
development contemplated by the section 52 agreement to be carried out.
Somewhat similarly, in the present reference, the only relevance of the basic
principle as stated in Pointe Gourde is to determine whether the premium
value of the reference land that the tribunal found to exist as a matter of
fact in the real world was entirely due to the scheme. But there was nothing in
the scheme as it was formulated in 1971 that conferred any premium value on the
reference land; that premium value only arose from the section 52 agreements
and the conditions on the planning permission.
Those problems
are, however, set aside by the tribunal’s finding that, whatever may have been
the position in 1971, the facts had changed with the change of policy by Avon
and the need for Pye to agree to complete the link road. The tribunal made that
finding as a matter of fact, and not in order to avoid the difficulties
discussed in the preceding paragraph. That those difficulties would otherwise
arise does, however, at least demonstrate that the tribunal’s findings of fact
and its conclusions as to the nature of the relevant scheme are difficult to
characterise as perverse.
Decisions
in Wards and Batchelor
The tribunal
considered at some length the actual decisions in this court in Wards
Construction v Barclays Bank, already referred to above, and also in
its predecessor case, Batchelor v Kent County Council (1989) 59
P&CR 357*. That was because the present respondents urged on the tribunal
that it was bound by those cases to hold that the ransom value of the reference
land was not attributable to any scheme, but was a reflection of the latent
development value of the Pye land that was unlocked or released by the
completion of the link road.
*Editor’s
note: Also reported at [1990] 1 EGLR 32; [1990] 14 EG 129
The tribunal
appears to have accepted those submissions. It explained the matter thus:
In our view
the relevant law is clear, having been much clarified by the Court of Appeal in
the recent case of Batchelor v Kent County Council. That case was
concerned with the valuation of land acquired by an actual compulsory purchase
order, but in other respects the facts are similar to those of the present
case. Those facts included planning permission for large-scale development that
could not be fully implemented until ‘off-site road works’ had been completed;
roadworks that involved construction of a roundabout on the claimant’s land;
and agreement between the parties that construction of the roundabout was the
scheme underlying the acquisition. When the Batchelor case first came
before the Court of Appeal (59 P&CR 358) Mann LJ said at pp360–361:
‘The Pointe
Gourde…principle enjoins the Tribunal to ignore ‘an increase in value which
is entirely due to the scheme underlying the acquisition’. The scheme underlying
the acquisition was here stated by the Tribunal to be ‘the construction of the
roundabout and the associated road works’. The roundabout and associated works
when they were completed, removed the inhibition imposed by … the planning
permission … the removal of the inhibition was a removal naturally to be
desired by the landowners whose development was otherwise curtailed. The
critical question as it seems to me, is whether the scheme underlying the
acquisition as found, did enhance the value of the order land. The question is
a question of fact. If there were found to be an enhancement, its dimension was
a matter of valuation. It is to be observed, and critically so, that the
tribunal must search for an increase in value ‘entirely due to the scheme’.
The Pointe
Gourde principle cannot diminish a pre-scheme value. Was there a particular
value prior to the scheme underlying the acquisition? As it seems to me the
tribunal found that there was.’
On that basis
the tribunal concluded:
We are unable
to detect a distinction in principle between the Batchelor case and the
present case. In our judgment, on similar facts we are bound to follow and
apply the reasoning of the Court of Appeal in the Batchelor/Wards
cases, and to hold that the reference land had a premium value in the hands of
the vendors that is not entirely due to the scheme underlying the acquisition
and therefore is not to be left out of account by reason of the Pointe
Gourde principle. It follows that we find that the reference land is to be
valued by reference to the factual matrix in the relevant area at the valuation
date.
Mr Purchas
criticised the tribunal’s view that it was bound to reach the conclusions that
it did by the reasoning of this court in Batchelor. I think that he was
right to do so. I do not think that the actual decision in Batchelor
establishes anything more than, as Mann LJ said in the passage cited by the
tribunal, that it is a question of fact as to whether the underlying scheme as
found enhanced the value of the acquired land. That principle necessarily
cannot dictate in any particular case what that finding of fact should be. So
far as Batchelor additionally emphasised, as it did, that the increase
in value, to be discounted under Pointe Gourde, must be entirely due to
the scheme, that was already the law, valuable though it was to have the matter
reviewed and re-emphasised in the particular factual situation that obtained in
Batchelor.
I cannot,
therefore, support all of this part of the tribunal’s reasoning. I do not
think, however, that that is in any way fatal to the 164
tribunal’s conclusion, and it is fair to say that Mr Purchas did not suggest
that this point would avail him even if he were unable to make good his other
submissions, as I hold that he indeed is unable to do. Well before embarking on
its consideration of Batchelor, the tribunal had already reached the
conclusions that I have quoted earlier in this judgment by exercise of its
fact-finding powers that were confirmed in Batchelor, and uncompelled by
any authority. In so doing it properly followed the process set out in Batchelor,
and subsequently in Wards. There is, however, absolutely no indication
that it felt constrained by those cases to reach any particular factual result
other than that it would have arrived at without reference to the factual
results in those cases.
It therefore
followed, as the tribunal said, that the reference land had to be valued
according to the actual facts existing at the valuation date. That followed
inevitably from its earlier finding that the ransom value was not to be
discounted under Pointe Gourde, a conclusion that the tribunal had
already reached before it turned to detailed consideration of Batchelor.
Pye’s
evidence to the tribunal
The foregoing
considerations are, in my view, sufficient to dispose of Pye’s main ground of
appeal, and to uphold the principal reasoning of the tribunal. However, out of
deference to the argument addressed to us, I mention one other matter. Pye gave
evidence before the tribunal, relied on also before us, that Pye itself would
never have contemplated acquiring the reference land at a ‘ransom’ or other
inflated value, and that Pye had not sought a different planning permission
without the obligations of the section 52 agreement because it believed that the
reference land would be made available at a reasonable cost. Pye only entered
into the section 52 agreement because it anticipated that the purchase price,
based on Avon’s powers of compulsory acquisition, would be a small sum of
money.
The reason for
citing this evidence, which was not commented on by the tribunal in its
determination and in respect of which it made no finding, was that set out in
ground 4 of Pye’s grounds of appeal: that the tribunal erred in law:
In taking
account of the section 19 agreements dated 19 July 1979 and 26 October 1979, by
which the Purchaser as Highway Authority was obliged to use its statutory
powers as such to acquire land including the reference land for the link road,
that approach was not consistent with the principle in Pointe Gourde in
that the statutory powers of acquisition are required to be ignored: in
particular failing to consider or state any reason for rejecting (if that was
the case) the unchallenged evidence of the Appellant that the agreements would
not have been entered into in the absence of the statutory powers of
acquisition.
I leave aside
whether we should consider matters upon which the tribunal has made no finding
of fact, since the argument is, in any event, misconceived. First, Pye plainly
accepted the terms of the 1988 agreement, and thereby contemplated that the
valuation of the reference land should be on the basis there set out, of a
notional compulsory purchase by Avon to further the section 52 agreement. Pye’s
explanation of its decision to enter into the section 52 agreement was not
simply that it was influenced by the ability of Avon to use compulsory purchase
powers, but rather that it assumed that acquisition on the basis of use or
notional use of those powers would result in a low price. It was that
assumption that Pye relied on when it consented to the 1988 agreement as an
alternative to resolving its dispute with Kingswood as to the price for the
reference land. The tribunal’s task was to value the land according to the
objective terms of the 1988 agreement, not according to what one of the parties
hoped to achieve from the 1988 agreement. Second, and in any event, ground 4
assumes that all that the section 52 agreement provided or, rather,
envisaged was that Avon would or might use compulsory purchase powers. But it
equally importantly placed obligations on Pye. Even, therefore, if it were
correct that in performing the valuation exercise the tribunal had to ignore
Avon’s compulsory purchase powers, that would not in any way constrain it to ignore
the whole of the section 52 agreement, including Pye’s obligations thereunder.
Conclusion
I would
accordingly dismiss the main part of this appeal. I turn to consider Pye’s
complaint about the tribunal’s application of the method of valuation adopted
by it.
Tribunal’s
valuation
I accept the
submissions of Mr Christopher Cochrane QC, for the respondents, that, first,
the actual valuation exercise is a matter for the expertise of the tribunal, in
which this court will not interfere; and second, that in conducting the
valuation in this case the tribunal had of necessity to reach broad and robust
conclusions about hypothetical events in a setting now long in the past. The
difficulty that I now address, however, exists despite the adoption of both of
those principles or assumptions.
The tribunal
approached its task, on the basis of the general assumptions that I have held
to have been correct, by asking, first, what was the development value of the
Pye land; and then considering what the owner of the reference land could have
obtained for that land from a developer of the Pye land who wanted to unlock
that development value. The tribunal concluded that the starting point for
calculating that ‘ransom’ price for the reference land would have been 50% of
the development value of the Pye land. However, the tribunal acknowledged that
there were alternative solutions for the developer of the Pye land other than
the completion of the link road. He could apply for fresh planning permissions,
without the condition as to construction of the link road. The tribunal
concluded that in the changed conditions of 1988, with a different policy
attitude as to the legitimacy of conditions aimed at ‘planning gain’, such
permissions might well have been granted and, if they were not, an appeal to
the Secretary of State might well have succeeded. Further, as the tribunal
found, an amendment to the section 52 agreements would also have been required,
but that might well have been obtained. The successful achievement of those
alternatives would have robbed the reference land of its premium value, and the
threat of that would have been present to the mind of the hypothetical owner of
the reference land: to the extent, as the tribunal found, that he would have
accepted substantially less than the starting figure of 50% of the development
value of the Pye land.
The tribunal
continued:
One of the
factors which would clearly be present to the minds of both parties to the
negotiations would have been the delay, costs and uncertainty inherent in the
pursuit of a revised planning permission and amended section 52 agreements by
the purchaser. In this context we have carefully considered the alternative
valuations. We think that a potential purchaser would be likely to have
estimated that the time taken to achieve the potential alternative solutions
would have been about two years.
On that basis
the tribunal calculated a cost to the developer imposed by that necessary delay
in releasing the development value of his land. It would be that cost that he
would seek to avoid by purchasing the reference land. Such a cost was
substantially less than the full value of the development land. That reduced
cost led the tribunal to conclude that a vendor of the reference land,
realising that that was the alternative available to the purchaser, would have
accepted substantially less than the starting hypothesis of 50% of the full
development value of the Pye land. The tribunal therefore reduced that figure
from 50% to 25%.
All of the
foregoing turns on the judgment and expertise of the tribunal, and is not and
cannot be challenged before us. The point of difficulty is, however, the
following. It was accepted before us, and we understood that it was accepted in
argument before the tribunal, that the section 52 agreement imposed different
limitations on the Pye industrial land, on the one hand, and on the Pye
residential land, on the other. Put briefly, the position is that by clause 9
of the agreement only 40% of the industrial land could be developed at all
before the link road was completed; whereas by clause 15 of the agreement what
was inhibited before the completion of the link road was the residential
development contemplated by Pye’s then current planning applications. I
consider the respondents’ concession that that was the 165
meaning of clause 15 to have been correctly made. The terms of the conditions
in the planning permission granted on application K448/11 were not so clearly
distinct; but I conclude that ‘the development’ of the residential land
referred to in condition g was the development to which that permission related
and no other.
The
significance of this is as follows. Even if new planning permissions would have
been forthcoming, because the local authority would have appreciated that they
had to apply the new policy on planning gain, that latter policy would not have
applied to inhibit the local authority in their willingness to release Pye from
the section 52 agreement. They might have had a reason for trying to maintain
Pye’s obligations in order to secure the completion of the link road. If the
local authority took that attitude, an application to the Lands Tribunal for
release of the covenants in the agreement would have been required, with
consequent delay. The tribunal no doubt had that well in mind, though it did
not distinguish in its reasoning between delay in relation to planning
permission and delay in relation to the section 52 agreement covenants.
However, on the true construction of the section 52 agreement as set out above,
any difficulty in securing the release of that agreement would not prevent Pye
from developing the residential land, provided that it could obtain a new
planning permission, since all that was inhibited by the section 52 agreement
was development of that land under the existing planning permission.
The tribunal
did not distinguish in its reasoning between the limitations on development of
the residential land, which made up the major part of the development value of
the Pye land as a whole, and the limitations on development of the industrial
land. That difference may affect the outcome of the tribunal’s valuation
process, if inhibitions imposed by the section 52 agreement were regarded as
more likely to cause delay than inhibitions imposed by the planning permission.
We cannot, however, know from the tribunal’s reasoning what assumption it made
about the effect of clause 15 of the section 52 agreement and whether that
assumption affected its conclusion.
Mr Purchas
conceded (or, more accurately, recognised that he could not offset the view
expressed by the court in argument) that we cannot substitute any figure for
that reached by the tribunal. Since, however, it is possible that the tribunal
may have been misled by assuming that both clause 9 and clause 15 of the section
52 agreement had the same effect, I see no alternative to remitting the
reference to the tribunal for that point to be reconsidered. The remission
should be in extremely limited terms, and will, of course, not involve the
calling of any further evidence before the tribunal. That will be achieved by
remitting the award to the Lands Tribunal in the terms proposed by Hobhouse LJ
at the end of his judgment. Should there be any difficulty in reconstituting
the same tribunal as heard the original reference, the parties should agree
that the jurisdiction of the Lands Tribunal for this purpose should be
exercised by the president sitting alone, as is provided for by section 3(1) of
the Lands Tribunal Act 1949.
Agreeing, HOBHOUSE
LJ said: This is an appeal by way of case stated from an award of the Lands
Tribunal arising from a reference by the parties to a contract for sale dated
January 13 1988. The history of this matter is fully set out in the reasoned
award attached to the case stated and has been summarised in the judgment of
Buxton LJ. It is not necessary to refer to the terms in which the questions of
law are worded in the case stated. The two grounds of appeal which have been
argued before us fall within the ambit of those questions.
The reference
land which was the subject of the contract for sale was a small rectangle of
land, which lay across a former railway on the line of the link road between
Victoria Road and the Bath Road in Bristol. The agreement provided that the
price for the land which the vendors, Kingswood Borough Council, agreed to
transfer to the purchasers, Avon County Council, should be ‘that sum determined
by the Lands Tribunal acting as arbitrator in accordance with a reference by
consent’. Special clause I of the agreement went on to provide that (among
other things):
The Vendor
has agreed to transfer the property to the Purchaser for the purpose of
enabling development contemplated by an agreement dated 19th July 1979 made
between the Vendor and Purchaser and JA Pye (Oxford) Limited and an agreement
dated 30th September 1987 between the Vendor and Purchaser and JA Pye (Oxford)
Estates Limited, JA Pye (Oxford) Limited and JA Pye (Oxford) Homes Limited …
It is further
agreed that:
(a) the
following assumptions will be made in the reference and arbitration namely
that:
(1) the
Purchaser has made an unopposed compulsory purchase order for the purchase of
the property for highway purposes and the Vendor is seized in fee simple in
possession of the property free from encumbrances:
(2) the
Purchaser has served notice to treat in respect of the property and has taken
possession thereof as of the date of this agreement
(b) JA Pye
(Oxford) Limited shall be permitted to act for and on behalf of the Purchaser
in relation to the said reference and arbitration and to argue that the
property had no or only a nominal value in consequence of the said agreement
dated 19th July 1979 made between the Vendor and Purchaser and JA Pye (Oxford)
Limited or otherwise.
(c) such
argument as is referred to in (b) above is not accepted by the Vendor who is at
liberty to argue for such price as he contends is proper.
These terms of
reference anticipate a Pointe Gourde question. This is the principle of
valuation affirmed by Lord MacDermott when delivering the advice of the Privy
Council in Pointe Gourde Quarrying & Transport Co Ltd v Sub-Intendent
of Crown Lands [1947] AC 565 at p572:
It is well
settled that compensation for the compulsory acquisition of land cannot include
an increase in value which is entirely due to the scheme underlying the
acquisition. As it was put by Eve J in South Eastern Ry Co v London
County Council [1915] 2 Ch 252 (at) 258: ‘Increase in value consequent on
the execution of the undertaking for or in connection with which the purchase
is made must be disregarded’.
Therefore, it
is necessary to identify what was ‘the scheme underlying the acquisition’
(which is a question of fact for the fact-finding tribunal: Wilson v Liverpool
Corporation [1971] 1 WLR 302, Hertfordshire County Council v Ozanne
[1989] 2 EGLR 18*) and disregard any enhancement of the land to be valued that
is to be derived from that scheme. This is the limit of the principle. It does
not preclude the valuer from taking into account any enhanced value of the land
which derives from any other factor, as, for example, its value for development
(Viscount Camrose v Basingstoke Corporation [1966] 1 WLR 1100; Myers
v Milton Keynes Development Corporation [1974] 1 WLR 696) or its value
as a ‘ransom strip’ (Batchelor v Kent County Council 59 P&CR
357). Indeed, it is the duty of the valuer fully to reflect such enhancing
features in his valuation.
*Editor’s
note: Also reported at [1989] 43 EG 182
In the present
case, as appears from the terms of reference and as explained in the reasons of
the Lands Tribunal and the judgment of Buxton LJ, the enhanced value of the
reference land derives from the facts that:
(1) By the
agreement of July 19 1979 JA Pye (Oxford) Ltd (whom I will call the company)
undertook neither to ’cause nor permit to be developed and brought into use
more than forty percentum by area of the land south of Poplar Road … prior to
the dedication to public vehicular traffic of the Link Road …’ (clause 9) and
that it would ‘neither cause nor permit the development to be carried out on
land to the north of Poplar Road until … the dedication to the public of the
Link Road as a continuous through route from Victoria Road to Bath Road and …
the closure of the railway bridge on Poplar Road’ (clause 15).
(2) The
planning consents held by the company for the development of the two blocks of
land south and north of Poplar Road contained equivalent restrictive
conditions.
It is not in
dispute that these undertakings and conditions could not be fulfilled until the
reference land had been acquired, since completion of the link road
necessitated the putting of a roadway across the reference land. At January 13
1988 the link road had already been completed on each side up to the boundaries
of the reference land; all that remained was to connect up the roadways on each
side of 166
the reference land. For this purpose the reference land had to be acquired.
Subject to a
point that arises on the construction of clause 15 of the July 1979 agreement, it
is now accepted that, upon the findings of fact made by the Lands Tribunal, the
value of the reference strip as between a willing seller and a willing buyer
was, as at the valuation date January 13 1988, £775,000 less betterment of
£18,500 equals £756,500; this was the sum it awarded. How this figure is
arrived at is explained at pp58–61 of the reasons of the Lands Tribunal. The
enhancing factor was the fact that the reference land was the key that unlocked
for the company the full development value in the company’s land south and
north of Poplar Road. The tribunal has held that, were it not for this
enhancing factor, the value of the reference land would have been no more than
£650: see its alternative award at p61.
It must be
observed that the enhanced value of the reference land is not an enhanced value
to the purchaser who is actually acquiring the land under the contract of
January 1988. The land had no special value to the county council and certainly
not any value beyond that derived from the road improvement scheme pursuant to
which the land was, notionally, being compulsorily acquired by the county
council. The enhanced value derives from the fact that there is an alternative
purchaser who would in his own interests be prepared to pay the vendor an
enhanced price for the reference land.
It was the
function of the Lands Tribunal as the fact-finding body to find what was the
scheme that underlay the deemed compulsory purchase of the reference land by
the purchaser. It was accepted by both parties that the purchase was, as the
January 1988 agreement provides, ‘for highway purposes’. Accordingly, it was
accepted by both parties that the underlying scheme did not extend beyond the
construction of the link road. The purchasers contended that the scheme was the
construction of the whole of the link road. The vendors contended that it was
simply the completion of the link road. The Lands Tribunal found that the
contention of the vendors was to be preferred. No basis has been shown upon
which this finding of fact can be challenged on this appeal as disclosing any
error of law. It is not suggested that it misdirected itself on the law. The
most that can be said is that it is a conclusion of fact that, the purchasers
submit, is legally inconsistent with the primary facts, which were not in
dispute. However, I have not been able to detect what that inconsistency is and
I agree with Buxton LJ that this challenge to the award of the Lands Tribunal
must fail.
However, I
consider that, even on the contention of the purchasers, the purchasers failed
to make out that the enhanced value of the reference land to the company should
be excluded. That enhanced value derives from the value of the reference land
to the company — for the company’s own purposes — to enable the company to
develop profitably its own land north and south of Poplar Road. That, on any
view, was not the scheme that underlay the purchase of the reference land by
the county council. The relevant scheme was a highway improvement scheme for
highway purposes. The interest of the company in acquiring the land was
precisely analogous to an interest in the acquisition of access land without
which other land could not be developed: Batchelor v Kent County
Council (supra). The mere fact that the key which unlocks the
development value derives from a restrictive agreement rather than physical
propinquity does not alter this conclusion. Indeed, it reinforces it:
physically, the completion of the link road was unimportant to either part of
the company’s land. The land south of Poplar Road already had good access to
the Bath Road and the land north of Poplar Road had access both east and west
along Poplar Road to Victoria Road and the Bath Road respectively. The highway
improvement scheme was meritorious in its own terms and distinct from the
question of the merit of the developments. The only link arose from the desire
of the planning authority under the regime that existed prior to 1983 to obtain
a collateral ‘planning gain’ in a manner which, as the Lands Tribunal pointed
out on p59 of its reasons, would not have been sustainable in 1988.
The main
ground of appeal having failed, a further point has been raised on this appeal.
The reasoning of the Lands Tribunal was that in order to release the
development value of the land north and south of Poplar Road it would be
necessary for the company not only to obtain unconditional planning consents
for the developments but also to obtain a release from the undertakings given
in clause 9 and clause 15 of the July 1979 agreement. The Lands Tribunal made
no distinction between the two blocks of development land (beyond recognising
that it was only 60% of the development value of the southern land which was
restrained by clause 9). This overlooked an argument of the purchasers that a
distinction ought to be made because clause 15 related solely to ‘the
development’ of the northern land and ‘the development’ was defined in the July
1979 agreement as being development consequent on planning consents given
pursuant to certain identified planning applications: see recitals 4 and 8 and
the later supplementary agreement dated September 13 1987. Therefore, as
regards the land north of Poplar Road, clause 15 only restricted its
development under those planning consents and did not affect or restrict any
development of that land under fresh consents that might be applied for and
obtained after January 1988. The obstacle in respect of the northern land was
not the need to remove the restriction in clause 15 of the July 1979 agreement,
but the need to obtain a fresh planning consent. The Lands Tribunal made no
reference to this point in the critical part of its reasoning on pp59 and 60.
The
development value of the northern land was financially important as is demonstrated
by appendix 9 to the reasons. How this factor would affect the valuation of the
reference land is a question of fact. Maybe it would not affect it at all.
There are some indications in the reasoning of the tribunal that this was or
would be its view. It was seeking to arrive at a figure that a willing
(hypothetical) vendor would be likely to accept and the interested purchaser be
willing to pay, rather than a precise calculation. This was a proper approach:
r 2. Further, it clearly excluded any consideration which might arise from the
fact that one or other party might also be the relevant planning authority: see
the lower part of p59. But it remains the position that the Lands Tribunal, as
the fact-finding body, has not made a finding of fact specifically on this
point and it appears to be at least possible that it overlooked it.
It follows
that the award must be remitted to the Lands Tribunal with a direction that it
reconsiders its award taking into account the limited effect of clause 15 of
the agreement of July 19 1979, and publish a fresh award either confirming or
varying, as it thinks fit, its previous assessment. I would also endorse what
has been said by Buxton LJ as to the desirability that, if there is any
difficulty about reconstituting the same tribunal consisting of the president
and Mr Hopper, the parties should concur in asking the president to hear and
determine the remission sitting alone.
SWINTON
THOMAS LJ agreed and did not add anything.
Appeal
allowed in part.