Green and others v Secretaries of State for the Environment and Transport and another
(Before Mr Justice GLIDEWELL)
Compulsory purchase — Application under section 23 of the Acquisition of Land Act 1981 to quash a compulsory purchase order — The applicants also sought to quash an associated order for the stopping up of highways, but as the two orders were interdependent the case was argued on the compulsory purchase order — Applicants were engaged in the retail furniture and furnishings trade and owned land in Eastleigh which was included in the order — The main issue was whether the Secretary of State for the Environment had erred in failing to have regard to a material consideration, namely, the question of ‘financial viability’, ie the balance between the cost of acquisition and the ground rent likely to be received by the local authority from the site — The scheme proposed was to provide on the 8-acre site a covered shopping centre and car park with rear pedestrian access — The applicants relied on such cases as Sovmots Investments Ltd v Secretary of State for the Environment and Prest v Secretary of State for Wales and submitted that there was an obligation on the local authority to call evidence to show the balance of cost and return — It was argued that as they had not done so the Secretary of State could not properly decide the issue in the absence of such evidence — Held, however, that the decision letter showed that the Secretary of State had not considered the financial viability of the scheme to be material and it was not therefore necessary for him to make a decision about it — He had accepted the inspector’s conclusion that the advantages of acquiring the site and proceeding with the scheme outweighed the necessity of extinguishing the applicants’ business (although the local authority did not admit such necessity, as they had offered relocation) and the consequential costs of acquisition — In these circumstances the Secretary of State was entitled to accept the inspector’s conclusion that the compulsory purchase order should be confirmed — Application dismissed
The applicants
were A T Green, the trustees of the Green settlement and Eastsleep Ltd, the
respondents being the Secretaries of State for the Environment and Transport
and Eastleigh Borough Council. The applicants’ interests and the land in
question are described at the beginning of Glidewell J’s judgment.
R Sears QC and
A Dinkin (instructed by Slaughter & May) appeared on behalf of the
applicants; M Spence QC and A Porten (instructed by R Read, Solicitor of
Eastleigh Borough Council) represented the council. The Secretary of State for
the Environment did not appear and was not represented.
Compulsory purchase — Application under section 23 of the Acquisition of Land Act 1981 to quash a compulsory purchase order — The applicants also sought to quash an associated order for the stopping up of highways, but as the two orders were interdependent the case was argued on the compulsory purchase order — Applicants were engaged in the retail furniture and furnishings trade and owned land in Eastleigh which was included in the order — The main issue was whether the Secretary of State for the Environment had erred in failing to have regard to a material consideration, namely, the question of ‘financial viability’, ie the balance between the cost of acquisition and the ground rent likely to be received by the local authority from the site — The scheme proposed was to provide on the 8-acre site a covered shopping centre and car park with rear pedestrian access — The applicants relied on such cases as Sovmots Investments Ltd v Secretary of State for the Environment and Prest v Secretary of State for Wales and submitted that there was an obligation on the local authority to call evidence to show the balance of cost and return — It was argued that as they had not done so the Secretary of State could not properly decide the issue in the absence of such evidence — Held, however, that the decision letter showed that the Secretary of State had not considered the financial viability of the scheme to be material and it was not therefore necessary for him to make a decision about it — He had accepted the inspector’s conclusion that the advantages of acquiring the site and proceeding with the scheme outweighed the necessity of extinguishing the applicants’ business (although the local authority did not admit such necessity, as they had offered relocation) and the consequential costs of acquisition — In these circumstances the Secretary of State was entitled to accept the inspector’s conclusion that the compulsory purchase order should be confirmed — Application dismissed
The applicants
were A T Green, the trustees of the Green settlement and Eastsleep Ltd, the
respondents being the Secretaries of State for the Environment and Transport
and Eastleigh Borough Council. The applicants’ interests and the land in
question are described at the beginning of Glidewell J’s judgment.
R Sears QC and
A Dinkin (instructed by Slaughter & May) appeared on behalf of the
applicants; M Spence QC and A Porten (instructed by R Read, Solicitor of
Eastleigh Borough Council) represented the council. The Secretary of State for
the Environment did not appear and was not represented.
Giving
judgment, GLIDEWELL J said: The applicants, Eastsleep Ltd, are the lessees of
two shops with ancillary land and buildings at 114 to 122 Southampton Road,
Eastleigh in the County of Hampshire. The first applicants own no 114, which
has a total area of 3,200 square metres. The company trades in retail furniture
and furnishings. It is one of the largest retail premises in Eastleigh. It
trades under the style A T Green.
There is an
area of about 8 acres lying west of Southampton Road and between Factory Road
and Blenheim Road in Eastleigh which is proposed in the town centre action area
plan for redevelopment for shopping use. That plan was adopted in July 1979. On
May 29 1980 the borough council made a compulsory purchase order on the whole
of the 8-acre site to provide a covered shopping centre and car park with rear
pedestrian access. The compulsory purchase order area included the applicants’
properties. It also included a modern building occupied as a grocery
supermarket by Tesco, who agreed with the borough council a scheme for
incorporation of their building into the redevelopment and their premises were
then withdrawn from the compulsory purchase order.
The applicants
objected to the order and an inquiry was held before Mr L A Davies between June
8 and 18 1982; in other words, over some two weeks. In the event the applicants
were the principal objectors, although not the sole objectors. A number of
points, both of law and of planning merit, were advanced on the applicants’
behalf, but all failed to persuade the Secretary of State for the Environment,
who confirmed the compulsory purchase order by letter dated September 6 1983.
He also confirmed an associated order for the stopping up of highways. It is
agreed that the two orders are interdependent.
The applicants
now move under section 23 of the Acquisition of Land Act 1981 to quash the
compulsory purchase order and under section 244(3) of the Town and Country
Planning Act 1971 to quash the road closure. The case has been argued, for the
reason I have already given, on the compulsory purchase order. Section 23(1) of
the 1981 Act provides:
If any person
aggrieved by a compulsory purchase order desires to question the validity
thereof, or of any provision contained therein, on the ground that the
authorisation of a compulsory purchase thereby granted is not empowered to be
granted under this Act . . . he may make an application to the High Court.
Subsection (2)
deals with failure of the acquiring authority to comply with the relevant
requirements. Section 24(2) gives the court power ‘if on the application the
court is satisfied that — (a) the authorisation granted by the compulsory
purchase order is not empowered to be granted under this Act . . .’ to quash
the compulsory purchase order or any provision contained therein.
Mr Sears, for
the applicants, argues (to summarise first of all) that what is called
‘financial viability’, that is to say, the balance between the cost of acquisition
and the likely ground rent to be received by the council from the site, was a
material consideration in the Secretary of State’s decision on the objection to
the compulsory purchase order. It was for the local authority, he says, if they
so decided, to submit evidence on this issue, but they failed to do so. The
Secretary of State therefore had no, or virtually no, evidence on which he
could properly make a judgment on this issue and he therefore failed to have
regard to a material consideration.
Mr Sears
referred me to the words of Lord Denning MR in Ashbridge Investments Ltd
v Minister of Housing and Local Government [1965] 1 WLR 1320, the
passage being at p 1326, where his lordship said:
Seeing that
that decision — that is to say, whether or not to confirm a compulsory purchase
order — is entrusted to the Minister, we have to consider the power of the
court to interfere with his decision. It is given in Schedule 4, para 2. The
court can only interfere on the ground that the Minister has gone outside the
powers of the Act or that any requirement of the Act has not been complied
with. Under this section it seems to me that the court can interfere
with the Minister’s decision if he has acted on no evidence; or if he has come
to a conclusion to which on the evidence he could not reasonably come; or if he
has given a wrong interpretation to the words of the statute; or if he has
taken into consideration matters which he ought not to have taken into account,
or vice versa; or has otherwise gone wrong in law. It is identical with the
position when the court has power to interfere with the decision of a lower
tribunal which has erred in point of law.
I turn to the
material which is before me, which includes the inspector’s report. The
inspector had a large number of documents submitted to him, one of which was a
letter antedating the inquiry dated February 9 1982 from the solicitors to the
applicants to the town centre project manager of the borough council in which
they set out and put on record their clients’ position with regard to the
compulsory purchase order and state at para 6:
However,
there is a further important aspect on which we wish to make our clients’
position clear. As it now seems that an agreement enabling our clients to
withdraw its objection is unlikely . . . and that there is currently no
prospect of a suitable alternative site . . . it is clear as matters stand at
present, that if the CPO is confirmed, compensation will have to be paid on a
total extinguishment basis. On current information this is likely to be well in
excess of £1,000,000. No doubt the borough has confirmed with the developers
the likely compensation position and that the scheme could stand such a
payment. (We assume that they have agreed to ‘stand behind’ the borough in
respect of all compensation payments.)
Para 7 reads:
We need
hardly remind the borough that financial considerations relating to local
authorities are now regarded as relevant considerations in proposals of this
kind and that a full investigation of the economic and financial issues will be
a major issue at the inquiry.
In usual form,
towards the end of his report the inspector made a series of what he described
(not always accurately, I say without disrespect to him) as findings of fact.
No xiii of those begins with the words: ‘The council anticipate that the
Cascade centre’–that being the name that was given to the proposed new centre–‘would
achieve a turnover of £9.4m durable trading based on a catchment area of
174,000 (by 1991)’. What the inspector does not say, but what was in fact the
evidence given to him, was that the £9.4m was in 1971 pounds and not in then
current pounds.
Para xv
contains the following sentence: ‘They conceded that if the scheme could be
made so attractive as to enlarge the catchment area as suggested by the council
a turnover of the order of £9.4m as calculated by the council might be
possible.’ So the issue there was the
number of people in the catchment area rather than the amount of likely trade
from a postulate catchment area. Paragraph xxi reads: ‘P Green estimate the
cost of extinguishment of their business at around £1m’.
The council
called no other evidence of either cost or likely income to them, but they did
have such evidence available. I deduce that from the fact that there was put
before the inspector part of the action area plan, one paragraph of which
contained the following words:
Particular
attention has also been directed at ensuring that the plan’s proposals are
realistic and capable of implementation. This has involved examining carefully
the financial viability of the proposals and in particular the cost and likely
income to the Borough Council.
Moreover, in
para 30 of his report, which is part of the summary of the case for the borough
council, the inspector, when discussing a suggestion by these applicants that
they might have managed to make an agreement with other developers who might
carry out a development instead of the developers whom the council had chosen,
said this:
The firm —
that is to say the present applicants — had received a particularly favourable
financial offer from the Rohan Group which the council, tied by statutory restrictions,
could not match although clearly the additional costs inherent in the Rohan
offer would be a charge on the scheme reflected in ground rents so that it
would be the ratepayers and future customers who would have footed the bill.
The council’s partnership scheme for overall comprehensive development would
result in substantial reductions in the charge on public resources as the main
capital costs would be borne by the private sector.
Although the
inspector did not refer to that, it was a piece of information which he did
have in front of him in addition to that to which I have already referred.
The inspector
went into the case for these applicants in very considerable detail. It
occupied 43 paragraphs in some 14 pages of his report and was by far the
largest single section of the report. In para 78 he repeated the point about
Messrs Green’s estimate that there was likely to be total extinguishment of
their business if the scheme went ahead and that that would lead to
compensation of about £1 million. At para 81, reporting the argument of Mr
Sears at the inquiry, he said:
In view of
the resources available to the council it was submitted that the quality of the
evidence they had presented was unacceptable. They had failed to call any
witness from the elected developers or county council and had given no evidence
as to the financial viability of the scheme contrasting remarkably with the
detailed analysis presented at the Bexleyheath inquiry.
of which he
had some evidence . . .
When
challenged on this matter the council had needed to resort to statements made
by the other prospective developers — statements made in the context of a
publicity campaign and in relation to a scheme for a smaller floorspace.
Then he set
out legal submissions made both on behalf of these applicants and the council
in response, and he recorded the submission of Mr Sears that the financial
considerations were now accepted by the courts as being relevant to the
consideration of the merits of a compulsory purchase order and recorded that Mr
Sears referred him to certain authority. The inspector said:
The
importance of this was not in the evidence presented by the council but rather
in the significant omission of any financial evidence as to the viability of
the whole scheme . . . The lack of substantive evidence meant that the
Secretary of State was not in a position to judge the viability of the scheme
and should not confirm the compulsory purchase order unless he was satisfied
that there was every prospect of the scheme going ahead.
So there is no
doubt (and indeed it was not suggested otherwise) that Mr Sears in his
submission to the inspector did raise this matter and raised it with his usual
clarity and vigour no doubt.
In reply to
that, Mr Spence for the council at para 91 is reported by the inspector as
saying:
Whilst it was
accepted that financial considerations could be relevant the council were under
no obligation to put forward detailed financial analysis to justify the scheme.
The witnesses for the council had wide experience of compulsory purchase order
inquiries having attended most of them — and it was explained to me that that
meant most such inquiries relating to town centres — and they had never been
required to produce costings for the scheme. The council were satisfied on the
advice given by their experts that the scheme was viable.
Having
received that report the Secretary of State, getting on for a year later, gave
his decision in a letter dated September 6 1983. He set out in detail in that
letter the inspector’s conclusions, one of which included the following
sentence:
However I
agree with the point made that it is for the council to produce cogent and
compelling evidence to support their case and whilst there may be no legal
obligation on the council’s part to produce evidence on the financial aspect
regarding the cost of acquisition and funding of the scheme it seems to me that
these are relevant matters which the Secretary of State may have wished (and
may still wish) to examine in the light of current national investment
policies.
He also said:
In assessing
the merits of the scheme therefore it is necessary to take into account the
possibility that the proposals may result in the extinguishment of the P Green
business. Having regard to the primary aim of the scheme to encourage the
larger type of store selling durable goods, it would seem incongruous to be
contemplating the displacement of one of the town’s most successful retailers
in this field whose trade may well then go to the large stores in Southampton. However,
I have given careful consideration to the powerful arguments made for the
retention of P Green in the town centre and I have concluded for the reasons I
have referred to that the public need for the land in this instance outweighs
the normal private rights of the individual firm.
That is the
Secretary of State repeating the inspector’s recommendation.
When the
Secretary of State came to consider these objections he said: ‘The objections
by Peter Green (Limited) and the inspector’s conclusions concerning them may
conveniently be dealt with under three headings — (i) planning procedures (ii)
financial viability of the scheme and (iii) the scale of the proposed scheme’.
I do not need to deal with anything except that part concerned with so-called
financial viability, which I must read in full. Para 14 says:
In para xiii
of his findings of fact the inspector records the council’s estimated turnover
for the proposed Cascade centre in para xxi records the estimate prepared by
Peter Green Ltd of the cost of extinguishment of their business. This was the
only evidence put before the Secretary as to the financial viability of the
proposed scheme.
Para 15 says:
The Secretary
of State accepts that the cost of any proposed scheme may be a relevant factor
in considering a compulsory purchase order submitted to him for confirmation.
Whilst there is no obligation on an acquiring authority requiring them to put
forward a detailed financial analysis of any proposed development, he takes the
view that it would be wrong for him to disregard28
clear evidence that an acquiring authority’s scheme was financially unsound or
extravagant. Notwithstanding the objectors’ doubts as to whether the council
have included in their written estimates a sum for the possible extinguishment of
their business, the Secretary of State does not accept that there is any
evidence before him in this case which could lead him to the view that the
proposed scheme was financially unsound or extravagant.
Para 16
continues:
It was argued
on behalf of Peter Green (Limited) that the government had advised that local
authorities contemplating town centre redevelopment should be aware of the
financial implications and that architectural and financial arguments should be
considered together. The 1963 Ministry of Housing and Local Government
publication referred to (‘Town Centres: Costs and Control of Redevelopment’)
certainly gives guidance concerning the prudent preparation of comprehensive
redevelopment schemes but it is not considered to be an instruction about the
presentation of evidence at a public local inquiry. The Secretary of State
considers the merits of an order on the basis of the facts and submissions
before him and he is satisfied that he has sufficient evidence to enable him to
come to a decision on this order.
The actual
decision in relation to the matter is contained in paras 19 and 20:
The Secretary
of State is content with the inspector’s reasoning, and agrees with his
conclusion, on these objections. For the reason set out above the Secretary of
State for the Environment accepts the recommendation of the inspector that the
Eastleigh Town Centre Action Area Plan Compulsory Purchase Order (No 1) be
confirmed subject to a modification to exclude the premises of Tesco Ltd
(identified hatched green on the order map). This letter constitutes his
decision to that effect.
I have already
summarised Mr Sears’ submissions, but I must deal with them now in a little
more detail. What he submitted to me is this. A local authority which seeks to
acquire land compulsorily is obliged at an inquiry into objections to the
compulsory purchase order to call such evidence as is necessary to show that
the acquisition of the land is necessary in the public interest. See the
judgment of Forbes J in Sovmots Investments Ltd v Secretary of State
for the Environment [1977] QB 411, the passages being at pp 423 and 424. At
p 423 he says:
The second
point on which Mr Goodfellow maintains the inspector misdirected himself is the
question of the cost of acquisition. At the inquiry Camden argued that cost was
a wholly irrelevant consideration or at least not a primary consideration, but
nevertheless prudently armed itself with figures concerned with cost, and cost
was very much an argument at the inquiry.
At p 424,
having considered a decision of Ackner J in relation to a planning matter where
he decided that cost was not relevant, Forbes J said:
I think the
position is a fortiori with compulsory purchase orders made by local
authorities under Part V of the Housing Act 1957. It seems to me that the
Secretary of State has a duty to consider cost in these cases, or at any rate
in suitable cases may well have such a duty. The provision of housing accommodation
after all involves the proper deployment not only of the ratepayers’ but also
the taxpayers’ money and it seems to me that the Secretary of State is entitled
to take these matters into account in suitable cases and that therefore cost
can be relevant. That I think is the extent to which the court can give a
ruling: cost may or may not be a relevant consideration depending on the
circumstances of the case; all that the court can do is to say that cost can be
a relevant consideration and leave it to the Minister to decide whether in any
circumstances it is or is not. Of course it follows that the weight to be given
to cost, if it is a relevant factor, is also a matter for the Minister and not
one in respect of which any court is entitled to substitute its opinion.
That case went
on via the Court of Appeal to the House of Lords, but the point about costs was
not relevant on the appeal and therefore there is nothing in the decisions of
either of those bodies which deals with the matter. As far as Forbes J’s dictum
is concerned, I respectfully accept and agree with every word of it.
The other
authority to which I have been referred, which is of course binding on me, is
the decision of the Court of Appeal in Prest v Secretary of State for
Wales [1982] 81 LGR 193.* That was a
case of a compulsory purchase order of some land for a new sewage works. The
landowner conceded that a new sewage disposal works was required (and I think
he went further and said it was highly desirable), but he wanted some other
part of his land to be taken for the purpose. He was perfectly willing for some
of his land to be taken. There was evidence at the inquiry that the
construction of the new works on, to be precise, either of two alternative
sites would be quite appreciably more expensive than on the compulsory purchase
order site. That was a principal matter at the inquiry and the inspector
regarded it obviously in the end as the compelling factor. But before the
decision was made (although after the completion of the inquiry) the objector
or his solicitors wrote to the Secretary of State making the point that if the
compulsory purchase site were not used it would be a suitable site for
industrial development, whereas the alternative site would be agricultural only
and thus the cost of acquisition of the compulsory purchase order site with the
benefit of, I suppose, a deemed planning permission for industrial development
would be very considerably greater than that of either of the alternative sites
and this would outweigh the additional cost of construction on the alternative
sites.
*Editor’s
note: Also reported at (1982) 266 EG 527, [1983] 1 EGLR 17.
The matter
referred to in the letter was not referred to at all in the decision of the
Secretary of State. For that reason the confirmation of the compulsory purchase
order by the Secretary of State was challenged. At first instance the challenge
failed, but on appeal it succeeded. Lord Denning MR said at the bottom of p
200, quoting Lord Greene MR in Associated Provincial Picture Houses Ltd
v Wednesbury Corporation [1948] 1 KB 223 at p 229: ‘He’, that is to say
the minister, ‘must call his own attention to the matters which he is bound to
consider.’ Lord Denning went on:
This was put
a little more fully by Lord Diplock in Secretary of State for Education and
Science v Tameside Metropolitan Borough Council [1977] AC 1014 at p
1065 that: ‘Or, put more compendiously, the question for the court is, did the
Secretary of State ask himself the right question and take reasonable steps to
acquaint himself with the relevant information to enable him to answer it
correctly?’
As I have said,
Lord Denning answered that question: ‘No, he did not.’
Watkins LJ put
it a little more fully. There are two passages from his judgment to which I
propose to refer. At p 207 he said:
What he
that is, the
Secretary of State,
may not do is
to proceed to exercise his discretion and allow it to be swayed by a factor
which is inadequately presented to him. It matters not, so it seems to me, that
he could reasonably have expected an objector or a supporter of his ultimate
decision to have fully exposed for him that factor in all its facets at public
inquiry or in some other way. He conducts a process of administrative decision
which is quite unlike that conducted by courts and some, if not all, tribunals.
Nevertheless, it is a process which is governed by disciplines vital to the
public interest.
At p 211 he
said:
In the sphere
of compulsory land acquisition, the onus of showing that a compulsory purchase
order has been properly confirmed rests squarely on the acquiring authority
and, if he seeks to support his own decision, on the Secretary of State. The
taking of a person’s land against his will is a serious invasion of his
proprietary rights. The use of statutory authority for the destruction of those
rights requires to be most carefully scrutinised. The courts must be vigilant
to see to it that that authority is not abused. It must not be used unless it
is clear that the Secretary of State has allowed those rights to be violated by
a decision based upon the right legal principles, adequate evidence and proper
consideration of the factor which sways his mind into confirmation of the order
sought.
Mr Sears’
submissions go on that in this case the Secretary of State accepted that the
financial cost return balance was a relevant matter for his consideration and
he refers me in this respect to para 15 of the decision letter which I have
read. Thus, Mr Sears argues, there was an obligation on the local authority to
call the evidence necessary to show what the cost return balance was. They
failed to do so. The Secretary of State could thus not decide the issue without
such evidence and he was wrong to say that it was for the objector to establish
that the scheme was financially undesirable.
In reply, Mr
Spence, for the local authority, accepted that Mr Sears’ submissions as to the
legal position were entirely correct. However, he did not accept that the
Secretary of State had said in his decision letter that the financial viability
(the balance between costs and likely return to the council) was a relevant
matter in this case. Properly understood, said Mr Spence, what the Secretary of
State was saying in para 15 of his letter may be paraphrased as follows.
Firstly, it might be — and it would have been the case if the objector had led
some evidence that the scheme was financially unsound — that financial
viability was a relevant consideration. But, secondly, such evidence was not
led and thus it did not become a relevant consideration and the Secretary of
State did not need evidence about it. Thirdly, since he had sufficient evidence
about the other compelling matters which justified the compulsory acquisition,
which were all relevant, he could properly make a decision. That last point,
says Mr Spence, is what the Secretary of State was saying at the end of para 16
of his letter.
In this sense,
said Mr Spence, this present case is very much to be contrasted with Sovmots
where, as I have already recorded, Forbes J29
was saying that evidence of financial matters was important and cost was very
much an argument at the inquiry, and with Prest where cost was the
fundamental feature upon which the decision turned. In Prest the cost of
the works was the vital feature that persuaded the Secretary of State to
confirm the compulsory purchase order, and his omission of the cost of the
acquisition of the land was the vital feature that flawed his decision.
Mr Spence also
reminds me of the practical difficulty of a local authority which is seeking to
acquire land, particularly where it is seeking to acquire a number of buildings
in a town centre from different landowners or owners of different interests,
going into detail at a public inquiry about either acquisition costs or its
estimated acquisition costs or likely future return. I do not think Mr Spence’s
point relates to construction costs. That of course might be a matter for the
developer who is going to bear the costs of it, not for the local authority.
The point is that if the compulsory purchase order is going to be confirmed
these matters are going to be in dispute between the individual landowners and
the authority and if necessary the dispute is one which will have to be
referred to and determined by the Lands Tribunal. Obviously, says Mr Spence,
the local authority cannot be put in a position where it has to reveal its hand
at an early stage, thus giving the landowner a potential weapon in negotiations
which will not come about unless and until a compulsory purchase order is
confirmed but which will be absolutely vital if a compulsory purchase order is
confirmed.
That same
point was not relevant in the Sovmots case. What was in issue there was
not costs of acquisition, but the likely cost of works needed to the various
flats which were the subject of acquisition and the likely rent to be charged
by the council for those flats. Of course, it was in issue in Prest, but
it was absolutely fundamental that the figures in Prest were those given
on the one hand as far as construction is concerned by the council and on the
other hand as far as acquisition is concerned by the objectors.
On the
question of whether the Secretary of State did say in his decision letter that
financial viability was a material consideration, not without some hesitation I
agree with Mr Spence. While the Secretary of State did not say in terms, ‘I do
not consider this in the end a relevant consideration’, he did refer to the
only findings of fact as to the financial viability of the scheme. It is quite
clear to me, and must have been quite clear to him and his advisers, that those
two facts were insufficient to enable him to make a judgment as to whether or
not the scheme would be financially viable. It would be inconceivable therefore,
in my view, that if he had considered that this was a relevant factor he would
have gone on and said: ‘It is relevant, it is therefore necessary for me to
decide this issue, but I cannot do so, because I do not have the necessary
evidence.’ He must be understood, in my
view, as saying, in a passage that has its difficulties in interpretation, that
in the circumstances it was not necessary for him to make a decision about
financial viability.
The local
authority’s case at the inquiry, including its evidence, can in my view be
summarised in this way. Firstly, they submitted, it is agreed that
redevelopment in this area generally is desirable. The issue, so far as these
objectors are concerned, is whether it is necessary to acquire their premises in
order to carry out the development satisfactorily. Secondly, the council’s case
was that the scheme which they were proposing which was the basis of the
compulsory purchase had many advantages about which the council called
considerable and detailed evidence. I have already said that they called
evidence to the effect that the proposed centre should attract a volume of
trade estimated at £9.4 million durable trading in 1971 pounds.
The council
went on that a smaller development omitting the objectors’ properties and then
necessarily omitting some adjoining properties would not have such advantages
and because it would not have those advantages it might well not proceed at
all, thus losing the advantage of this development completely to the town. As
far as the possibility of alternative development was concerned, as proposed by
these developers, that would place a greater financial burden on the rates.
Finally the
council said: We are willing to relocate these objectors in the area and we
thus do not accept that their business would be extinguished, but even if it
is, the other advantages of acquiring the site and going ahead with the scheme
outweigh the necessity to extinguish the Green business and the resultant costs
of acquisition that would arise from that (although I do not think the council
ever accepted the £1 million figure).
The inspector
concluded that even taking the risk of extinguishment into account the public
need for the land outweighed the private rights of the objectors. In my
judgment, the Secretary of State was acting within his powers when he said, on
such limited evidence as the inspector had as to financial cost, that that
evidence was not sufficient to displace the inspector’s opinion as to the
advantages of the scheme in the public interest. Thus, in my judgment, the
Secretary of State was entitled to accept the inspector’s conclusions that the
compulsory purchase order should be confirmed. For these reasons the
application for an order to quash the compulsory purchase order fails and it is
dismissed.
The
application was dismissed with costs, the applicants to pay half the costs of
each respondent.