Fletcher Estates (Harlescott) Ltd and another v Secretary of State for the Environment and another
Compulsory purchase — Compensation — Certificate of appropriate alternative development — Section 17 of the Land Compensation Act 1961 — Relevant date for determining planning policies
On January 30
1986 the second respondent, the Secretary of State for Transport, made a
proposal to acquire two parcels of land owned by the first and second
applicants for the construction of a bypass. The proposal to acquire was a
proposal within the meaning of section 22(2) of the Land Compensation Act 1961.
The date of entry for both parcels of land was January 5 1990. In 1992 the
applicants applied for certificates of appropriate alternative development
under section 17 of the 1961 Act. In May 1993 the local planning authority
issued certificates for residential and industrial development. Following an
appeal under section 18 by the Secretary of State for Transport, the Secretary
of State for the Environment allowed the appeal and substituted negative
certificates in each case, adopting the date of entry as the relevant date for
the application of current and reasonably foreseeable planning policies. The
applicants contended, inter alia, that the relevant date is the date
under section 22(2)(a) of the 1961 Act when the proposal to acquire was
made and the Secretary of State for the Environment was wrong in not
discounting the effect of the proposal to acquire the land before the date of
the proposal to acquire, namely January 30 1986.
Held: The decisions were quashed. Jelson Ltd v Minister of
Housing and Local Government [1970] 1 QB 243 is binding authority; the
relevant date for the purposes of considering the application of current and
reasonably foreseeable planning policies is the date of the proposal to
acquire, namely January 30 1986. On the relevant date, policy would have
supported the grant of planning permission for residential development if it
had not been proposed for acquisition for construction of the bypass. The
Secretary of State for the Environment was in error in failing to discount the
effect of the proposal to acquire the land before the date of the proposed
acquisition. He was not required to take the policies and facts on the relevant
date as if the scheme had been cancelled on that date; he was required to
assume the scheme had never been conceived at all.
Compulsory purchase — Compensation — Certificate of appropriate alternative development — Section 17 of the Land Compensation Act 1961 — Relevant date for determining planning policies
On January 30
1986 the second respondent, the Secretary of State for Transport, made a
proposal to acquire two parcels of land owned by the first and second
applicants for the construction of a bypass. The proposal to acquire was a
proposal within the meaning of section 22(2) of the Land Compensation Act 1961.
The date of entry for both parcels of land was January 5 1990. In 1992 the
applicants applied for certificates of appropriate alternative development
under section 17 of the 1961 Act. In May 1993 the local planning authority
issued certificates for residential and industrial development. Following an
appeal under section 18 by the Secretary of State for Transport, the Secretary
of State for the Environment allowed the appeal and substituted negative
certificates in each case, adopting the date of entry as the relevant date for
the application of current and reasonably foreseeable planning policies. The
applicants contended, inter alia, that the relevant date is the date
under section 22(2)(a) of the 1961 Act when the proposal to acquire was
made and the Secretary of State for the Environment was wrong in not
discounting the effect of the proposal to acquire the land before the date of
the proposal to acquire, namely January 30 1986.
Held: The decisions were quashed. Jelson Ltd v Minister of
Housing and Local Government [1970] 1 QB 243 is binding authority; the
relevant date for the purposes of considering the application of current and
reasonably foreseeable planning policies is the date of the proposal to
acquire, namely January 30 1986. On the relevant date, policy would have
supported the grant of planning permission for residential development if it
had not been proposed for acquisition for construction of the bypass. The
Secretary of State for the Environment was in error in failing to discount the
effect of the proposal to acquire the land before the date of the proposed
acquisition. He was not required to take the policies and facts on the relevant
date as if the scheme had been cancelled on that date; he was required to
assume the scheme had never been conceived at all.
The following
cases are referred to in this report.
Associated
Provincial Picture Houses Ltd v Wednesbury
Corporation [1948] 1 KB 223; [1947] 2 All ER 680; (1947) 45 LGR 635, CA
Fox v Secretary of State for the Environment (1991) 62 P&CR
459; [1991] 2 EGLR 13; [1991] 40 EG 116; [1991] RVR 171
Grampian
Regional Council v Secretary of State for
Scotland [1983] 1 WLR 1340; [1983] 3 All ER 673; (1983) 47 P&CR 540; 23
RVR 263; [1984] 2 EGLR 175; [1984] EGD 1073; 271 EG 625, HL
Jelson
Ltd v Blaby District Council [1977] 1 WLR
1020; [1978] 1 All ER 548; (1977) 75 LGR 624; 34 P&CR 77; [1977] 2 EGLR 14;
[1977] EGD 309; 243 EG 47; [1977] JPL 579, CA
Jelson
Ltd v Minister of Housing and Local Government;
George Wimpey & Co v Minister of Housing and Local Government
[1970] 1 QB 243; [1969] 3 WLR 282; [1969] 3 All ER 147; (1969) 67 LGR 543; 20
P&CR 663, CA
Pointe
Gourde Quarrying & Transport Co Ltd v Sub-Intendent
of Crown Lands [1947] AC 565, PC
Prest v Secretary of State for Wales (1982) 81 LGR 193; [1983] 1
EGLR 17; [1983] EGD 282; 266 EG 527, CA
Robert
Hitchins Builders Ltd v Secretary of State for
the Environment (1978) 37 P&CR 140; [1978] 2 EGLR 125; [1978] EGD 945;
248 EG 689; [1978] JPL 824
Secretary
of State for Education and Science v Tameside
Metropolitan Borough Council [1977] AC 1014; [1976] 3 WLR 641; [1976] 3 All
ER 665; (1976) 75 LGR 190, CA and HL
These were
applications by Fletcher Estates (Harlescott) Ltd and the executors of JV
Longmore under section 21 of the Land Compensation Act 1961 to quash the
decisions of the first respondent, the Secretary of State for the Environment,
who allowed appeals by the second respondent, the Secretary of State for
Transport, against certificates of appropriate alternative development issued
by the local planning authority.
Robin Purchas
QC and Timothy Comyn (instructed by Manby & Steward, of Telford) appeared
for the applicants, Fletcher Estates (Harlescott) Ltd and the executors of JV
Longmore; Jeremy Sullivan QC and Rabinder Singh (instructed by the Treasury
Solicitor) represented the first respondent, the Secretary of State for the
Environment; the second respondent, the Secretary of State for Transport, did
not appear and was not represented.
Giving
judgment, DYSON J said: There are before me two applications under
section 21 of the Land Compensation Act 1961 (the 1961 Act) to quash decisions
of the first respondent made under section 18 of the 1961 Act, whereby he
allowed appeals by the second respondent against certificates of appropriate
alternative development in respect of two parcels of land at Sundorne,
Shrewsbury. The land, which I will refer to as ‘the Longmore land’ and ‘the
Fletcher land’ was proposed for compulsory purchase by the second respondent
for the purpose of constructing the A49 Shrewsbury bypass. The date of the
proposal to acquire as defined under section 22(2) of the 1961 Act was January
30 1986. The date of entry in each case was July 5 1990. On October 19 1992 (in
respect of the Fletcher land) and December 4 1992 (in respect of the Longmore
land) the applicants applied for certificates of appropriate alternative
development under section 17. The local authority issued certificates on May 8
1993 for residential and industrial development (in the case of the Longmore
land) and residential development (in the case of the Fletcher land). The
second respondent appealed against the certificates under section 18. By his
decision letter dated July 4 1996 the first respondent allowed the appeals
substituting negative certificates in each case under section 17(4)(b)
of the 1961 Act.
8
Legislative
framework
The principal
relevant provisions of the 1961 Act in the form in which it was at the time
that is material for the purposes of these applications were as follows:
17.
Certification of appropriate alternative development
(1) Where an
interest in land is proposed to be acquired by an authority possessing
compulsory purchase powers, and that land or part thereof does not consist or
form part of —
(a) an
area defined in the development plan as an area of comprehensive development,
or
(b) an
area shown in the development plan as an area allocated primarily for a use
which is of a residential, commercial or industrial character, or for a range
of two or more uses any of which is of such a character,
then, subject
to subsection (2) of this section, either of the parties directly concerned may
apply to the local planning authority for a certificate under this section …
(3) An
application for a certificate under this section —
(a)
shall state whether or not there are, in the applicant’s opinion, any classes
of development which, either immediately or at a future time, would be
appropriate for the land in question if it were not proposed to be acquired by
any authority possessing compulsory purchase powers and, if so, shall specify
the classes of development and the times at which they would be so appropriate;
(b)
shall state the applicant’s grounds for holding that opinion; and
(c)
shall be accompanied by a statement specifying the date on which a copy of the
application has been or will be served on the other party directly concerned.
(4) Where an
application is made to the local planning authority for a certificate under
this section in respect of an interest in land, the local planning authority
shall, not earlier than 21 days after the date specified in the statement
mentioned in paragraph (c) of subsection (3) of this section, issue to
the applicant a certificate stating either of the following to be the opinion
of the local planning authority regarding the grant of planning permission in
respect of the land in question, if it were not proposed to be acquired by an
authority possessing compulsory purchase powers, that is to say —
(a)
that planning permission for the development of one or more classes specified
in the certificate (whether specified in the application or not) would have
been granted; or
(b)
that planning permission would not have been granted for any development other
than the development (if any) which is proposed to be carried out by the
authority by whom the interest is proposed to be acquired…
(7) In
determining, for the purposes of the issue of a certificate under this section,
whether planning permission for any particular class of development would have
been granted in respect of any land, the local planning authority shall not
treat development of that class as development for which planning permission
would have been refused by reason only that it would have involved development
of the land in question (or of that land together with other land) otherwise
than in accordance with the provisions of the development plan relating
thereto…
18(2) On any
appeal under this section against a certificate the Minister shall consider the
matters to which the certificate relates as if the application for a
certificate under section 17 of this Act had been made to him in the first
instance, and shall either confirm the certificate, or vary it, or cancel it
and issue a different certificate in its place, as he may consider appropriate
…
22(2) For the
purposes of section 17 and 18 of this Act, an interest in land shall be taken
to be an interest proposed to be acquired by an authority possessing compulsory
purchase powers in the following (but no other) circumstances, that is to say —
(a)
where, for the purpose of a compulsory acquisition by that authority of land
consisting of or including land in which that interest subsists, a notice
required to be published or served in connection with that acquisition, either
by an Act or by any Standing Order of either House of Parliament relating to
petitions for private bills, has been published or served in accordance with
that Act or Order; or
(b)
where a notice requiring the purchase of that interest has been served under
any enactment, and in accordance with that enactment that authority are to be
deemed to have served a notice to treat in respect of that interest; or
(c)
where an offer in writing has been made by or on behalf of that authority to
negotiate for the purchase of that interest.
Issues
1. Was the
first respondent correct in adopting July 6 1990 (the date of entry) as the
relevant date for the purposes of considering the application of current and
reasonably foreseeable planning policies?
2. In his
application of section 17 of the 1961 Act, was the first respondent correct in
not discounting the effect of the proposal to acquire the land before the date
of the proposal to acquire, namely January 30 1986?
3. In
rejecting the inspector’s conclusion at para 14.13 of his report, did the first
respondent err in relying upon the fact that the route immediately to the east
of the bypass (the alternative route) had not been subject to a highway
inquiry?
4. Further or
alternatively, did the first respondent err in failing to give the applicants
the opportunity to provide evidence or otherwise deal with the question of
comparative costs and engineering evidence; alternatively, was the decision in
that respect in breach of natural justice?
5. Further or
alternatively, were adequate reasons given by the first respondent for his
conclusions at para 17 of the decision letter?
The first two
issues raise questions of some general importance. It will be seen that issues
3 to 5 involve a consideration of the details of the inspector’s report and the
decision letter. I shall set out the relevant passages in those documents when
I come to deal with those issues.
First
issue
I shall refer
to the relevant date for the purposes of considering the application of current
and reasonably foreseeable planning policies as ‘the relevant date’. For the
applicants it is submitted that the relevant date was January 30 1986, the date
of the proposal to acquire as defined by section 22(2)(a) of the 1961
Act. For the first respondent it is submitted that the relevant date was the
date of entry. It is common ground that the Court of Appeal decision of Jelson
Ltd v Minister of Housing and Local Government [1970] 1 QB 243
obliged the first respondent to treat the section 22(2)(a) date as the
relevant date for the purposes of determining the physical state of the land.
In my view,
the language of section 17 when read literally does not provide the answer to
the question raised by this issue. Section 17(1) merely provides that it is a
prerequisite of an application for a certificate of appropriate alternative
development that one of the events referred to in section 22(2) has occurred. The
phrase ‘immediately or at a future time’ in section 17(3)(a) does not
point to one date rather than another. Nor does the language of section 17(4)
provide the answer: note the words ‘would have been granted’ and ‘would not
have been granted’.
It is clear
that the purpose of certificates issued under section 17 is that they should be
an aid to the assessment of compensation: see, eg per Lord Bridge in Grampian
Regional Council v Secretary of State for Scotland (1983) 47
P&CR 540*, at p574. It assists in the process of assessment because the
parties or, in default of agreement, the Lands Tribunal, need to know what
assumptions to make as to planning permission in determining the price to be
paid by the acquiring authority. It is also well established that the date for
assessment of compensation is the date of entry or the date of the hearing,
whichever is the earlier.
*Editor’s
note: Also reported at [1984] 2 EGLR 175
Accordingly,
if the matter were free from authority, then in view of the purpose of section
17 certificates, like Sir Douglas Frank QC in Robert Hitchins Builders Ltd
v Secretary of State for the Environment (1978) 37 P&CR 140*, I
would have been inclined to decide that the relevant date in this case was the
date of entry. The question is whether there is binding authority that requires
me to hold that the relevant date is the section 22(2)(a) date. For the
applicants it is submitted that Jelson is such binding authority, and
that the approach in Jelson is also consistent with Grampian. On
behalf of the first respondent it is submitted that I should follow Hitchins
and distinguish Jelson.
*Editor’s
note: Also reported at [1978] 2 EGLR 125
9
I start with Jelson.
The facts briefly were these. In 1951 a county development plan showed a
proposed ring road round Leicester. The land on either side of the proposed
road was shown as allocated primarily for residential purposes. The owners
built large housing estates adjoining the proposed ring road, leaving a narrow
strip of land for the proposed road. In 1962 the proposed ring road was
abandoned. The owners applied for planning permission to develop the site of
the proposed road for residential purposes. Permission was refused because of
the existing housing estates. The owners served notices requiring purchase of
their land. The minister confirmed the purchase notices and directed that the
local authority were to be deemed to have served notice to treat on September
28 1965. The owners applied for certificates under section 17(4)(a) of
the 1961 Act of appropriate alternative residential development. On appeals,
the minister confirmed the ‘nil certificates’ under section 17(4)(b).
I should
interject before going further that it is important to distinguish between the
two questions that are reflected in issues 1 and 2 in the present case. The
questions are related, but distinct. The first question is: what is the
appropriate date at which the relevant facts (the physical state of the land
and the present and future planning policies affecting it) are to be
considered, in order to determine the classes of development (if any) for which
planning permission would at that date have been granted? The second
question is: what assumptions have to be made and what facts taken into account
in deciding for what classes of development (if any) planning permission would
have been granted at that date? For this distinction, see Lord Dunpark in Grampian
at p548.
In Jelson
the applicants argued that the question whether planning permission might
reasonably have been expected to be granted should be decided without regard to
any particular time (at some time before there was any proposal for a ring
road), and not at the section 22(2)(b) date. The Court of Appeal
decided, as a matter of construction of section 17(4) and 22(2), that the
relevant date was the section 22(2) date. Lord Denning MR said that the crucial
word in section 17(4) and 22(2) was ‘proposed’. At p251A, he said:
that
definition shows that the word ‘proposed’ refers to the proposal contained in
an actual or deemed notice to treat or in an offer to purchase. That gives a
good clue to the date of the proposal. It is the date of the actual or deemed
notice to treat or of the offer to purchase, as the case may be.
In the light
of that definition, section 17(4) means that the planning authority must form
an opinion as to what planning permission might reasonably have been expected
to be granted at the date of the actual notice to treat, or the deemed notice
to treat, or the offer to purchase, as the case may be.
The reference
to ‘actual notice to treat’ is in error for a notice of compulsory purchase,
but it is clear from p250H that Lord Denning was intending to treat the
relevant date for all three cases mentioned in section 22(2) as the same.
Sachs LJ
agreed with Lord Denning’s construction ‘without enthusiasm’, and Phillimore LJ
agreed in the result both on the construction point and on wider grounds to
which I shall come when I turn to issue 2.
On the face of
it, there can be no doubt that Jelson decides the first issue in favour
of the applicants: the relevant date is the section 22(2)(a) date.
The next case
to consider is Hitchins. That was a section 22(2)(c) case. The
local authority offered to purchase a site owned by the applicants for the
purpose of a school extension. The applicants applied to the local planning
authority for a certificate under section 17, specifying residential
development as the development for which planning permission might have been
expected to have been granted if it were not proposed to be acquired
compulsorily. The local planning authority issued a certificate stating that
planning permission might reasonably have been expected to be granted for only
an open form of development. The Secretary of State confirmed the certificate.
He took the view that the relevant date was the section 22(2) date. The
applicants argued that the relevant date should have been the date of his
decision. Sir Douglas Frank QC quashed the decision holding that the relevant
date was the date of the decision. Of Jelson, he said, at p149:
Now, it seems
to me to follow that what the Court of Appeal decided was that the land was to
be taken in its existing state at whichever of the three specified dates
applied. What the Court of Appeal did not decide was whether it was necessary
that the Secretary of State should have regard only to the planning policies
operative on the date specified and not, as he had contended, also to any
policies extant at the time of making his decision. For that reason Jelson’s
case appears to me to be distinguishable. It seems to me having regard to the
scheme of the Act and ratio decidendi of Browne J (with which the Court
of Appeal agreed), that the application of the planning policies should as
nearly as possible coincide with the date of the assessment of compensation.
Thus, I think, on the true analysis of Jelson’s case, the land and the area
in which it is situated must be taken rebus sic stantibus as it was on
the appropriate date as I have specified, but subject to that rule, the
Secretary of State should deal with the matter in the same way as he deals with
a planning appeal, ie he should take into account his then current planning
policies.
The next
relevant authority is Grampian. That, too, was a section 22(2)(c)
case. The education authority by agreement acquired two parcels of land from
the second respondent for sites for schools. The agreement provided that the
second respondent should receive the same compensation as if the land had been
compulsorily acquired. The second respondent applied to the local planning
authority for a certificate under the provision in the equivalent Scottish
legislation that corresponds with section 17 of the 1961 Act. Certificates were
issued stating that planning permission would not have been granted for any
development other than that proposed by the education authority, ie for
schools. On appeal, the Secretary of State certified that planning permission
would have been granted in respect of the land for residential development. On
appeal, the Second Division of the Inner House of Court of Session (Lord
Avonside dissenting) affirmed the Secretary of State’s decision. Much of the
speeches both in the Court of Session and the House of Lords was concerned with
the second issue which arises in the present case. The appellants also
contended, however, that the relevant date by reference to which the application
for a certificate should be determined was the date of the application or the
date when the public local inquiry began. In other words, they were contending
neither for the section 22(2) date nor the date of entry. The dates of the two
offers to purchase were December 15 1976 and January 13 1977. The date of entry
in each case was December 20 1976. On the facts of that case, it made no
difference to the result whether the relevant date was the section 22(2) date
or the date of entry: this immateriality was pointed out by Lord Dunpark, at
p556. There is no doubt, in my judgment, that both Lord Dunpark and Lord
McDonald held that the relevant date was the section 22(2) date: see pp557, 559
and 565. But that decision must be viewed in the light of the issue that arose
in the case. There was no argument as to whether the relevant date should have
been the date of entry, because on the facts the distinction between the
section 22(2) date and the date of entry was immaterial. At p559, Lord Dunpark
said:
In my opinion
the 1975 amendment was not intended to, and did not, substitute the date of the
application, or any other subsequent date, for the dates fixed by section
30(2), or, if the date of entry now be the relevant date, for that date.
Accordingly, the reporter and the Secretary of State applied the relevant dates
for section 25(4) certificates.
(Emphasis
supplied.)
The words
emphasised show clearly that Lord Dunpark was not deciding as between the
section 22(2) date (the equivalent of section 30(2) in the Scottish
legislation) and the date of entry.
Lord Dunpark
did, however, appear to approve of Hitchins: see top of p556. He also
said, lower down the same page:
If one is
looking, as in my opinion one should be looking, for a date at which all
relevant facts have to be considered by the grantor of a section 25(4)
certificate, the nearer that date to the date of entry the greater the
assistance which the certificate will give to the Lands Tribunal in assessing
the open market value of the land.
He mentioned Jelson,
and said, at p557:
10
The point of
distinction which Sir Douglas Frank made in the Hitchins case is not
applicable to the present case. We are not here concerned with any change in
planning policy. The point in this case is whether the Secretary of State ought
to have granted a (4)(b) certificate because these schools had to be
built on these sites.
Mr Robin
Purchas QC and Mr Jeremy Sullivan QC both rely on Lord Dunpark’s judgment, but
for different purposes. Mr Purchas relies on it (as well as on the judgment of
Lord McDonald) for the clear statement that the relevant date was the section
22(2) date, pointing out that, although Jelson was mentioned, there was
no criticism of it. Mr Sullivan relies on it for the endorsement of Hitchins
and the way in which Sir Douglas Frank distinguished Jelson by reference
to the question of changes in planning policies.
I should refer
at this stage to the speech of Lord Bridge, because he dealt briefly, and obiter,
with the question of relevant date at pp573 and 574. He agreed with Lord
Dunpark’s reasons for rejecting the date of application as the relevant date,
but did not discuss Jelson, Hitchins or the choice between the
section 22(2) date and the date of entry.
I have
referred at some length to Grampian, but for the reasons that I have
mentioned I consider that the judgment of Lord Dunpark is of limited value in
helping to resolve the issue before me.
Finally in
this review of authorities, I should refer to Fox v Secretary of
State for the Environment (1991) 62 P&CR 459*, a decision of Roch J.
The facts there, were that in 1977 the applicants were refused planning
permission to build houses on land that they owned on the ground that there was
a sufficient supply of housing land. In 1980 the local authority decided that
the land should be used for recreational purposes. In 1981 a second application
for planning permission for residential development was refused on the ground
that there was an adequate supply of housing land. In 1985 the local development
plan was adopted which provided that the applicant’s land would be open space.
In March 1987 the local authority made an offer to purchase. In September 1987
a third application for planning permission for residential development was
refused. In March 1988 the local authority issued a certificate under section
17(4) stating that planning permission would not be granted for any development
on the applicants’ land other than for recreational and similar usage. There
was an appeal to the Secretary of State, who ruled that he had to consider the
state of the appeal land at the time of the written offer to purchase, but that
he had to have regard to the relevant planning policies current and reasonably
forseeable at the date when he came to consider the appeal, namely October
1989, when housing was no longer in short supply. He took that date because
there had been no entry by then. The Secretary of State issued a new
certificate of appropriate alternative development for private open space or
private open recreational use. On appeal by the landowners, Roch J held that
the Secretary of State should have considered the relevant policies current and
reasonably foreseeable at the section 22(2) date, and not at the date of the
hearing. The Secretary of State had followed Hitchins and adopted the
‘split approach’ of considering the physical state of the land as at the
section 22(2) date, but the relevant policies as at the later date. The
Secretary of State has adopted the same approach in the present case. Roch J declined
to follow Hitchins. He held (at p472) that the proper interpretation of
the 1961 Act supported the section 22(2) date, although it seems to me that the
conclusion that he reached on this point was based largely on the Grampian
case which, for the reasons which I have already stated, I think should be
viewed with caution on this point.
*Editor’s
note: Also reported at [1991] 2 EGLR 13
The conclusion
that I have reached is that the Secretary of State ought to have treated the
section 22(2) date as the relevant date because I think that Jelson
obliges me so to decide. In my judgment, it is at least part of the ratio of Jelson
that the section 22(2) date is the date at which all relevant facts are
to be considered in order to determine the classes of development for which
planning permission would then have been granted. The Court of Appeal decided
the question that was before it as a matter of statutory interpretation. I can
see no warrant in the statute for interpreting the relevant date as one date
for considering some of the relevant facts (ie the physical state of the land),
and another date for considering other relevant facts (ie the relevant and
future planning policies). I do not believe that the language of the statute
permits such a distinction to be drawn. Nor can I see any rational basis for
drawing such a distinction. Mr Sullivan did not suggest that there was one.
Surely, both the physical state of the land and the planning policies are relevant
to the hypothetical question of what planning permission would have been
granted, absent the proposal for compulsory acquisition. It is tempting to
interpret the statute in such a way as would give effect to the overriding
purpose of section 17 certificates as it was explained in Grampian, both
in the Court of Session and in the House of Lords: greater assistance in the
assessing of compensation would be provided if the relevant date was nearer to
the date when compensation falls to be assessed. Sir Douglas Frank did not seek
to justify his distinguishing of Jelson by reference to any statutory
words which supported the split approach. He sought to limit Jelson to
the factual situation that arose in that case. In my judgment, he was wrong to
do so. In saying this, I recognise that in Grampian Lord Dunpark
appeared to endorse the distinction drawn by Sir Douglas Frank. It was,
however, immaterial in Grampian to decide between the section 22(2) date
and the date of entry, and was therefore unnecessary to decide whether Sir
Douglas Frank was right in distinguishing Jelson in the way that he
sought to do.
I conclude,
therefore, that the first defendant should have adopted the section 22(2)(a)
date as the relevant date, and I resolve the first issue in favour of the
applicants.
Second
issue
The relevant
factual background as found by the inspector and accepted by the first
respondent is as follows. The bypass was originally proposed as part of the
1952 town map. A protected route was defined across the Longmore land and the
Fletcher land in November 1970. Between 1963 and 1971 planning permission was
refused on six occasions for residential development of the Fletcher land
because of the bypass proposal. In 1973 the county council adopted the Sundorne
Advisory Plan for land to the west of the bypass route. The Shropshire County
Structure Plan 1980 required urgent identification of additional housing land.
In the local plan 1985 residential land was identified at the Moveage,
notwithstanding objections.
At the section
18 inquiry, the borough council and the applicants contended that the proposal
for acquisition should be discounted as a whole, including its effect on policies
and decisions before the relevant date. They contended that, but for that
effect, the land would have been released under the Sundorne Advisory Plan
and/or the local plan. In 1981 there was a shortfall in the five-year housing
supply. Thus, on the relevant date, policy would have supported the grant of
planning permission for residential development of the land if it had not been
proposed for acquisition for construction of the bypass. In other words, the
policies and facts applicable at the relevant date should have been viewed as
if the bypass scheme had never been conceived at all.
On the other
hand, the second respondent contended that the first respondent and the
inspector were required to take the policies and facts on the relevant date as
if the scheme had been cancelled on that date, and not as if the scheme had
never been conceived at all. Thus, policies would be as they in fact were on
the relevant date, including policies in the development plan that opposed the
release of further land for housing.
Both the
inspector and the first respondent accepted the submission of the second
respondent as to the correct approach.
At first
sight, the language of sections 17(3) and (4) and 22(2) might appear to support
the first respondent’s approach. It is precisely the same approach as that
which was characterised as ‘literalistic’ by Lord Bridge in Grampian.
The argument is that what has to be ignored in answering the hypothetical
question raised by an application under 11
section 17 is the immediately preceding event, which has resulted in the
applicant’s interest in land becoming one which ‘is proposed to be acquired by
an authority possessing compulsory purchase powers’ under section 17(1), in
this case the publishing of a notice of compulsory purchase. While that notice
must be ignored, so runs the argument, facts and policies resulting from the
underlying scheme which culminated in the publishing of the notice should not
be ignored.
Arguing for
this approach, Mr Sullivan submits as follows.
(i) The language
supports it. The crucial words in sections 17(3) and (4) are ‘if it were not
proposed to be acquired’. The applicants’ construction involves construing
those words as if they read ‘if it had never been proposed to be acquired’.
Moreover, the emphatic language of section 22(2), with its use of the words ‘in
the following (but no other) circumstances’, should be contrasted with section
9 of the 1961 Act, which provides that:
No account
shall be taken of any depreciation of value of the relevant interest which is
attributable to the fact that … an indication has been given that the relevant
land is, or is likely, to be acquired by an authority possessing compulsory
purchase powers.
(ii)
Accordingly, parliament has decided to restrict the relevant assumptions made
and facts taken into account to those applicable at the relevant date. You look
at the position as it would be, absent the section 22(2) event, and are not
concerned with any aspect of the earlier history which has contributed to that
position.
(iii) There is
nothing irrational in such an approach. Indeed, it avoids the uncertainties
that were referred to by Phillimore LJ in Jelson.
(iv) Nor does
it create injustice. Although the grant of a positive certificate under section
17(4)(a) is conclusive (see section 15(5)) the grant of a negative
certificate is not conclusive against a landowner. Section 14 of the 1961 Act
defines the assumptions as to planning permission that are to be made in
assessing compensation. Subsection (3) provides:
but in determining
whether planning permission or any development could in any particular
circumstances reasonably have been expected to be granted in respect of any
land, regard shall be had to any contrary opinion expressed in relation to that
land in any certificate issued under Part III of this Act.
Thus, if
adoption of the first respondent’s approach leads to a negative certificate, it
will still be open to a landowner whose interest has been acquired compulsorily
to adduce evidence before the Lands Tribunal as to the proper assessment of
compensation on ordinary Pointe Gourde [1947] AC 565 principles and/or
on the basis of sections 6 and 9 of the 1961 Act. Jelson is a case in
point. In that case a negative certificate was issued under section 17(4). The
owners took the case to the Lands Tribunal. Section 9 of the 1961 Act was
applied and, in awarding compensation, the tribunal disregarded the reduction
in the value of the land caused by the ‘indication’ of the scheme, which had
been abandoned by the relevant date.
(v) In any
event, Jelson is binding authority and obliges me to hold that the first
respondent’s approach was correct.
The
submissions of Mr Purchas may be summarised as follows:
(i) Parts II
and III of the 1961 Act are interdependent: see per Lord Bridge in Grampian
at p567. Note, for example, that areas of comprehensive development and primary
allocation are excluded under section 17(1), since they are specifically
provided for section 16(2) and (4); note too that the effect of certificates under
section 17(4)(a) and (b) is provided for in section 14(3) and
15(5) respectively.
(ii) The
discounting required by section 17(4) should be done in the same way as it is
done by the Lands Tribunal when assessing compensation. It is well established
that in applying section 6(1) and/or 9 of the 1961 Act, and/or the rule in Pointe
Gourde, one not only ignores the scheme underlying the acquisition, but
also considers what would have happened in the ‘no scheme world’.
(iii) There is
nothing unduly speculative or uncertain about the process. It is a necessary
and regular part of the evaluation carried out by the Lands Tribunal and
valuers.
(iv) The first
respondent’s approach does create injustice. It does not fully discount the
scheme and compels the landowner to raise the discounting issue again before
the Lands Tribunal, with the disadvantage of having a negative certificate.
That this is a real disadvantage, notwithstanding the language of section
14(3), was a point made by Lord Bridge in Grampian, at p568.
(v) Jelson
is distinguishable. First, that case concerned a purchase notice. Acquisition
pursuant to a purchase notice is triggered by the owner of the land requiring
acquisition of his land. There is accordingly no ‘scheme’ underlying the
acquisition. Second, in Jelson the road scheme had been abandoned in
1962, some three years before the purchase notice was served. The argument
before the court did not seek to rely on the application of Pointe Gourde
or sections 6 and/or 9 of the 1961 Act. Rather, it was submitted that the
question of whether or not planning permission might have been expected to be
granted should be judged at any time back to 1952 when the road was first
proposed. The court approached that question as a matter of statutory
construction. It is true that Phillimore LJ at p255A–E dismissed the appeals
‘both as a matter of construction and on wider grounds’. The wider grounds (ie
‘hopelessly uncertain exercise’) did not, however, form part of the ratio of
the other two judgments.
In my judgment,
Mr Purchas is right and largely for the reasons that he has submitted. It seems
to me that Mr Sullivan’s argument is the same, mutatis mutandis, as that
which was rejected in Grampian. Lord Bridge dealt with it at p569:
sections 16, 25 and 30 of the Land Compensation (Scotland) Act 1963 correspond
exactly with sections 9, 17 and 22 of the 1961 Act. He said:
If it were
right to confine attention to section 25(3) and (4) and section 30(2) alone,
this literalistic argument might have some appeal. If, however, one considers
the wider statutory context and the function of certificates of appropriate
alternative development in the scheme of the Act as a whole, it becomes clear
that the argument is untenable
First, the
argument flies in the face of section 16 of the Act which provides:
No account
shall be taken of any depreciation of the value of the relevant interest which
is attributable to the fact that (whether by way of designation, allocation or
other particulars contained in the current development plan, or by any other
means) an indication has been given that the relevant land is, or is likely, to
be acquired by an authority possessing compulsory purchase powers.
As Lord
Dunpark succinctly puts it ‘it seems to me to follow from the fact that the
value of the land is not to be affected by the prospect of compulsory
acquisition, that its value is not to be affected by the development proposed
by the acquiring authority. One cannot discount the one without the other’.
Next I refer
to section 25(7) which provides:
In
determining, for the purposes of the issue of a certificate under this section,
whether planning permission for any particular class of development would have
been granted in respect of any land, the planning authority shall not treat
development of that class as development for which planning permission would
have been refused by reason only that it would have involved development of the
land in question (or of that land together with other land) otherwise than in
accordance with the provisions of the development plan relating thereto.
The primary
purpose of this provision, in my view, is to obviate the possibility that
where, as in the usual case, urban land is allocated in the development plan
for a necessary public purpose for which it will in due course need to be
acquired, that provision of the plan can be relied on to deny the landowner a
positive certificate. If the planning need to use land for a public purpose,
which underlies a proposed compulsory acquisition, is not a sufficient ground to
withold a positive certificate where that need is recognised and provided for
in the development plan, I do not see how the underlying planning need can ever
be such a sufficient ground.
But the
overriding consideration which impels me to reject the argument for the
appellants is that it would, in my opinion, if accepted, defeat the essential
purpose of the procedure for obtaining certificates of appropriate alternative
development, as part of the overall scheme of the Act to secure the payment of
fair compensation to landowners who are compulsorily expropriated, or,
expressed more specifically, to ensure that, when urban land, otherwise
available for some form of urban building development, is acquired for a
necessary public purpose, the compensation will reflect its urban development
value. Assuming, as I do, that every compulsory purchase of land can be
justified by reference to the public purpose for which the land is required, to
allow reliance on that public requirement to determine the 12
question raised by an application under section 25 would lead to the issue of a
negative certificate in every case. Counsel for the appellants, recognising
that this conclusion would be fatal to his argument, sought to avoid it by
contending that the applicant for a positive certificate would succeed if, but
only if, he could show that, at the date of his application, there were one or
more alternative sites available which could equally well or perhaps better be
used to meet the public need for which his own land was proposed to be taken. I
unhesitatingly reject this contention. An application for a certificate of
appropriate alternative development presupposes that the land to which it
relates is in fact to be acquired by an authority possessing compulsory
purchase powers and a certificate issued will only be of significance if the
acquisition proceeds to completion. The availability of alternative sites is
very relevant at the stage when a proposed compulsory acquisition is being
resisted. But once that it has been decided that site A, rather than site B or
site C, is to be acquired, the fact that site B or site C might have been
chosen instead can have no conceivable relevance in determining the fair basis
of compensation which the acquiring authority ought to pay the owner of site A.
In my view,
that reasoning is as fatal to Mr Sullivan’s submissions as it was to the
arguments advanced by the appellants in Grampian.
I turn,
therefore, to consider the argument that Jelson obliges me to hold that
the first respondent’s approach was correct. I start by observing that if Jelson
is not distinguishable, it is strange that no comment was made about it in
relation to this issue in Grampian. If it is not distinguishable, Jelson
and Grampian cannot both be right on this issue. Yet although Jelson
was cited in Grampian, it was only referred to in relation to the
relevant date point (our first issue) at p556 (Lord Dunpark) and at p564 (Lord
McDonald).
I have not
found it easy to discern whether Jelson is a second issue decision. Mr Purchas
submits that it is not. The arguments seem to me to have been directed both to
the relevant date point (p247C–G) and to the second issue point (p247B–C, G–H).
I have come to the conclusion that it cannot be regarded as a decision confined
to the relevant date point: see per Lord Denning at p251C–D, Sachs LJ at
p252B–F, p254B–E, and Phillimore LJ at p255C–E.
Nevertheless, Jelson
can and, in my view, should be distinguished for the reasons advanced by Mr
Purchas. As Lord Dunpark put it in Grampian, ‘the value of land is not
to be affected by the development proposed by the acquiring authority’ (p553).
If, at the relevant date, the acquiring authority no longer propose to carry
out the development, then the question of discounting the effect of that development
does not arise. In Grampian the acquiring authority did propose to
develop the land for use as schools at the relevant date. The issue was whether
the fact that the land had been earmarked for such use before the relevant date
meant that this proposed use did not fall to be discounted. The House of Lords
decided that it did fall to be discounted. In Jelson, however, by the
relevant date the acquiring authority had abandoned their proposal to develop
the strip of land as a road. The Court of Appeal decided that the planning
authority were required to look at the position at the relevant date and
certify under section 17(4) in the circumstances then existing. As the later Jelson
litigation demonstrated (Jelson Ltd v Blaby District Council
[1977] 1 WLR 1020) that did not prevent the applicants from claiming
compensation under section 9 of the 1961 Act for the reduction in value of the
land caused by the ‘indication’ of the road during the years preceding its
abandonment in 1962.
I should add
for completeness that Roch J followed Grampian in relation to the second
issue, and said, at p477:
It is now
clearly established that not only the proposal by the public authority to
acquire the land compulsorily must be ignored but also the planning policies
which underly such a proposal. The provision which requires the proposal of the
authority possessing compulsory purchase powers to be disregarded is section
17(4) itself.
He did not
refer to Jelson in relation to this issue. Fox was a case in
which at the relevant date the acquiring authority still proposed to develop
the land for the purposes for which they had made a written offer to purchase,
thereby bringing section 22(2)(c) into play.
I conclude,
therefore, that the first respondent was in error in failing to discount the
effect of the proposal to acquire the land before the date of the proposed
acquisition.
Third
issue
Three
alternative bypass routes were the subject of evidence and submissions before
the inspector: the route which has been built over the appeal land (the
preferred route); an alternative route, which ran for part of its length along
the line of the preferred route and for its remaining length close to but to
the east of the line of the preferred route (the alternative route); and OR4, a
route which ran roughly parallel to the preferred route, but substantially
further to the east. At the inquiry, the applicants put forward the case that,
in the absence of the preferred route, the probable alternative route for the
bypass would have been OR4, and that the alternative route was a possible, but
less probable, alternative to OR4. The second respondent’s case was that it was
uncertain whether there would be an alternative bypass or what route it would
have taken. At the public highway inquiry held in 1984, OR4 had been rejected
in favour of the preferred route. The second respondent submitted to the
inspector at the section 18 inquiry that, in the absence of the preferred
route, all other options would need to be evaluated.
The inspector
concluded that there would have been a bypass, and that in the absence of the
preferred route the alternative route would have been adopted. He set out at
paras 14.10 and 14.11 of his report the evidence which led him to this
conclusion. He then went on to decide that (whichever date was taken to be the
relevant date) residential development would not have been appropriate on the
appeal land on the basis of OR4, but that it would have been appropriate on the
basis of the alternative route.
The first
respondent agreed with the inspector that, in the absence of the preferred
route, an alternative bypass would have been built, but concluded that the
‘facts and other evidence lead to a different conclusion as the most likely
alignment of such a road’: para 15. At para 17, he said:
The view is
taken that the evidence of the 1984 inquiry is a very strong argument in favour
of the conclusion that, if the acquisition scheme had not been built on the
appeal sites, the most likely alignment would have been OR4. A conclusion that
some other route would have been chosen could only reasonably be reached if
there were stronger evidence in favour of another option. In this connection
the appeal Inspector concludes — in paragraph 14.11 of the report — that there
was such a possibility, namely a route immediately to the east of the actual
route but to the west of OR4; and that this was the alternative route that
would have been selected. However it is noted that, unlike the actual route and
OR4, this is not a costed route that has been considered in depth by engineers
and it has not been subject to the rigorous scrutiny of a highway inquiry. For
this reason, whilst such an alternative may have had the benefits ascribed to
it in paragraph 14.11 of the report, it has been given less weight than OR4 and
the Inspector’s conclusion is not accepted in this respect. Instead, the view
is taken that a by-pass would have been provided on route OR4 if the appeal
sites had not been compulsorily acquired. This would have been the position at
both the Fox and Hitchins dates.
Mr Purchas
submits that there was no reason to suppose that the overall costs or
engineering implications of the alternative route would materially differ from
those of the preferred route. Moreover, the considerations taken into account
by the first respondent, namely that the alternative route had not been costed,
considered in depth by engineers or been the subject of a highway inquiry, were
immaterial. Accordingly, the first respondent had regard to immaterial
considerations and/or reached a conclusion that was perverse.
I cannot
accept these submissions. As Mr Sullivan points out, the first respondent
concluded that the evidence at the 1984 highway inquiry was ‘a very strong
argument’ in favour of OR4. That was a conclusion that he was entitled to
reach. As the applicants had themselves emphasised at the section 18 inquiry,
the report of the inspector to the highway inquiry had concluded that the
choice between the preferred route and OR4 was ‘closely balanced’. In view of
this, it was reasonable for the first respondent to decide that he could opt
for an alternative to OR4 only if there was evidence to oust OR4 as the
runner-up to the preferred route. He considered this in the fourth and fifth
sentences of para 17 of the decision letter and concluded that there was
insufficient evidence to displace OR4. It should be 13
remembered that he was not acting as a reviewing authority of the inspector’s
decision, but deciding the issue de novo as if at first instance: see
section 18(2) of the 1961 Act. He had regard to the benefits of the alternative
route ascribed to it by the inspector at para 14.11 of his report, but
concluded that they were insufficient to outweigh the fact that, unlike the
preferred route and OR4, the alternative route had not been costed or
considered in depth by engineers, and not been subject to the rigorous scrutiny
of a highway inquiry. Matters of weight were for the first respondent. In my
judgment, given the fact that the choice between the preferred route and OR4
had been regarded as finely balanced at the highway inquiry, it was entirely
reasonable that the first respondent should have regarded the factors to which
he made reference as decisive. I reject the submission that he had regard to
immaterial considerations and/or that he reached a perverse conclusion. I
cannot leave this issue without commenting that it is ironic that the
applicants should now be characterising in this way the first respondent’s
adoption of the very submissions that they sought to persuade the inspector to
accept.
Fourth
issue
This issue
arises out of para 17 of the first respondent’s decision letter. The absence of
costings of the alternative route and the paucity of the engineering evidence
relating to it were not raised by or on behalf of the first respondent either
before, during or after the close of the inquiry. For the applicants, it is
submitted that if the first respondent considered that the evidence was
inadequate, and that such inadequacy was material (as it proved to be), he
should have: (i) obtained the relevant evidence for himself; and/or (ii) given
the applicants the opportunity of dealing with the point. In support of (i),
the applicants rely on Prest v Secretary of State for Wales
(1982) 81 LGR 193*. The argument in (ii) is a complaint that there was a breach
of the rules of natural justice.
*Editor’s
note: Also reported at [1983] 1 EGLR 17
Prest was a compulsory purchase case. The water authority wanted to make
a new sewage works on land owned by the applicants, and issued a compulsory
purchase order in respect of the land. The applicants offered alternative
sites. At the public inquiry, no evidence was given as to the costs of
acquiring the land for the site. The inspector’s report recommended to the
Secretary of State that the compulsory purchase order be confirmed on the basis
that the construction cost was likely to be greater at the applicants’
alternative sites than at the compulsory purchase order site. The applicants
wrote to the Secretary of State before he gave his decision, pointing out that
the material question of the relative land costs of the sites had not been
considered. They asked for the inquiry to be reopened. The Secretary of State
confirmed the compulsory purchase order on the basis of the comparative
construction costs of the two sites, and without considering the relevant land
costs.
The Court of
Appeal quashed the decision applying the well established principle of public
law that a decision maker must ‘call his own attention to the matters to which
he is bound to consider’: see Associated Provincial Picture Houses Ltd v
Wednesbury Corporation [1948] 1 KB 223, at p229. The same point was made
by Lord Diplock in Secretary of State for Education and Science v Tameside
Metropolitan Borough Council [1977] AC 1014, at p1065:
or put more
compendiously, the question for the court is, did the Secretary of State ask
himself the right question and take reasonable steps to acquaint himself with
the relevant information to enable him to answer it correctly?
It is not
difficult to see why in Prest it was considered that reasonable steps
did require the Secretary of State to acquaint himself with the information as
to the relative values of the competing sites. He had been specifically asked
to consider this issue, and the Court of Appeal decided that he could not
properly decide whether to confirm the compulsory purchase order without this
information.
I cannot
accept that in the present case the first respondent acted unreasonably or
unfairly in reaching his decision without information as to the cost and
without a detailed engineering appraisal of the alternative route. In judging
whether the first respondent acted reasonably and fairly, I consider the
following factors are material:
(i) He
accepted the applicants’ case in respect of OR4. This feature alone makes this
case very different from Prest. No party to the section 18 inquiry
argued as its primary case that the alternative route would have been chosen in
the absence of the preferred route. The applicants had put forward a detailed
and cogent case in support of OR4. The first respondent accepted it. The
applicants would not be complaining about that if the inspector and the first
respondent had not rejected their case as to the housing implications of OR4.
(ii) The
applicants had the opportunity to adduce evidence as to the costs and
engineering aspects of the alternative route, but chose not to do so because
they were advocating OR4. The first respondent did not act unreasonably or
unfairly in not himself seeking such evidence and in not giving the applicants
a further opportunity to adduce it.
(iii) Unlike
in Prest, the first respondent was not asked by the applicants to seek
such evidence or that they be given an opportunity themselves to adduce it.
(iv) Finally,
although it would presumably have been possible to cost the alternative route
and obtain a detailed engineering appraisal of it, the alternative route would
still not have been subject to the ‘rigorous scrutiny of a highway inquiry’,
and to that extent, in the eyes of the first respondent, it was bound to be and
to remain at a disadvantage as compared with OR4.
I conclude,
therefore, that Prest is distinguishable, and that the first respondent
did not fail to take reasonable steps to acquaint himself with the relevant
information so as to enable him to answer the question correctly. For the same
reasons, he did not act in breach of the rules of natural justice.
Fifth
issue
For the
applicants it is submitted that no adequate reasons were given for the
conclusions in para 17 of the first respondent’s decision letter. It is said
that the applicants are prejudiced in being left in substantial doubt whether
the decision was taken within the powers conferred on the first respondent by
the 1961 Act. Mr Purchas did not develop this submission and I can deal with it
quite shortly. In my view, the reasons given in para 17 are perfectly clear. Mr
Purchas subjected the paragraph to a detailed analysis, which formed the basis
of his submissions in relation to the third issue. The fact that it was
susceptible to such an analysis provides support for my view that the reasons
were both intelligible and clear. I reject this reasons challenge.
Conclusion
Accordingly, I
decide the first two issues in the applicants’ favour, and the remaining issues
in favour of the first respondent. In the result, the decisions must be
quashed.