Blandrent Investment Developments Ltd v British Gas Corporation
(Before Lord Justice STEPHENSON, Lord Justice Geoffrey LANE and Lord Justice CUMMING-BRUCE)
Compensation for acquisition by British Gas Corporation of easement to lay gas mains or pipes–Entitlement based on deed of grant by claimants’ predecessors in title–Whether compensation covered injurious affection to certain other land of claimants–Predecessors had no interest in such other land at date of grant to corporation but land then already owned by claimants–Majority of Court of Appeal reject construction that compensation provisions in deed covered injurious affection to land not owned by claimants’ predecessors at date of grant–Dissenting judgment by Stephenson LJ
This was an
appeal and cross-appeal by case stated from a decision of the Lands Tribunal (W
H Rees FRICS) on a reference by the claimants, Blandrent Investment
Developments Ltd, to determine the amount payable by the British Gas
Corporation in certain events in accordance with a deed of grant by the
claimants’ predecessors in title, who were the British Railways Board. The deed
granted to the corporation an easement to lay, maintain, inspect and replace
gas mains or pipes in, through, upon or over a narrow strip of land which was
subsequently conveyed to the claimants. The deed contained provisions for the
payment of compensation where the grantor’s covenants prevented benefit from
being derived from development with actual or probable planning permission. The
effect of the Lands Tribunal’s decision and the issues raised in the appeals
are set out in the dissenting judgment of Stephenson LJ.
Gerald
Moriarty QC and Guy Roots (instructed by Belmont & Co) appeared on behalf
of the appellants (the claimants, Blandrent Investment Developments Ltd); John
Drinkwater QC, Gerard Ryan and Charles George (instructed by Michael A E Louks)
represented the British Gas Corporation.
Compensation for acquisition by British Gas Corporation of easement to lay gas mains or pipes–Entitlement based on deed of grant by claimants’ predecessors in title–Whether compensation covered injurious affection to certain other land of claimants–Predecessors had no interest in such other land at date of grant to corporation but land then already owned by claimants–Majority of Court of Appeal reject construction that compensation provisions in deed covered injurious affection to land not owned by claimants’ predecessors at date of grant–Dissenting judgment by Stephenson LJ
This was an
appeal and cross-appeal by case stated from a decision of the Lands Tribunal (W
H Rees FRICS) on a reference by the claimants, Blandrent Investment
Developments Ltd, to determine the amount payable by the British Gas
Corporation in certain events in accordance with a deed of grant by the
claimants’ predecessors in title, who were the British Railways Board. The deed
granted to the corporation an easement to lay, maintain, inspect and replace
gas mains or pipes in, through, upon or over a narrow strip of land which was
subsequently conveyed to the claimants. The deed contained provisions for the
payment of compensation where the grantor’s covenants prevented benefit from
being derived from development with actual or probable planning permission. The
effect of the Lands Tribunal’s decision and the issues raised in the appeals
are set out in the dissenting judgment of Stephenson LJ.
Gerald
Moriarty QC and Guy Roots (instructed by Belmont & Co) appeared on behalf
of the appellants (the claimants, Blandrent Investment Developments Ltd); John
Drinkwater QC, Gerard Ryan and Charles George (instructed by Michael A E Louks)
represented the British Gas Corporation.
Giving
judgment, STEPHENSON LJ said: This is an appeal by way of case stated from a
decision of the Lands Tribunal (W H Rees Esq, FRICS) dated April 8 1976. The
decision was given on a reference by the appellant claimants, Blandrent
Investment Developments Ltd, under clause 6(iv) of a deed of grant dated May 17
1973, to determine the compensation payable under that deed by the respondent authority,
the British Gas Corporation. Two bases of compensation were put before the
tribunal by the claimants and a third by the corporation, should the tribunal
find that the claimants were entitled to claim any compensation. The tribunal
decided (1) that an outline planning consent of November 20 1973 gave rise to a
claim to compensation under clause 6 of the deed; (2) that the amounts payable
on the three bases put before it were £85,000, £45,000 and £5,100 respectively
(in each case less £224 already paid under clause 1 of the deed); (3) that the
second basis (‘Valuation II’) was the correct basis and the compensation was
accordingly £44,776. The question on which our decision is desired is whether
upon the facts found the tribunal came to correct decisions in point of law.
There is no
dispute about the three figures as figures, and counsel are agreed that there
are therefore two questions for the court: (1) whether on the agreed facts the
planning permission of November 20 1973 brings into operation clause 6 of the
deed of May 17 1973 and qualifies the claimants for compensation thereunder and
(2) if it does, what is the proper basis of that compensation. The claimants
ask us to uphold the tribunal by answering the first question ‘yes’, but to
substitute Valuation I (£85,000 less £224) for Valuation II. The corporation
asks us to answer the first question ‘no’, and alternatively, if the answer to
it is ‘yes’, to substitute Valuation III (£5,100 less £224) for Valuation II.
The dispute
which the tribunal has decided arises out of the laying and maintaining of gas
pipes in and under land near Rainham railway station in Essex. In 1962 and 1964
the corporation and its predecessors laid a 4-in gas pipe and a 6-in gas pipe
in and through a 20-ft-wide strip south of the railway station and lines (and
in 1971 a 24-in gas main a little to the north of the pipes, but there is no
relevant agreement or dispute in respect of that main). On January 11 1973
another company conveyed about 20 acres of land south of the strip to the
claimants (‘the blue land’). On March 21 1973 the corporation wrote a letter to
the British Railways Board approving the deed, which was11
executed on May 17 1973. On April 4 1973 the board agreed to sell and the
claimants agreed to purchase a long and narrow parcel of land 2.6 acres in size
lying between the blue land and the railway line (‘the red land’). It runs for
about 1,100 ft from a frontage 135 ft wide on Ferry Road to the east, narrowing
to 75 ft at Rainham Creek at the rear or western end. On June 7 1973 the board
conveyed the red land to the claimants for £27,500. But between the contract in
April and the conveyance in June the board granted the corporation on May 17 an
easement to lay, maintain, inspect and replace gas mains or pipes in, through,
upon or over the 20-ft strip, and the red land was conveyed subject to that
grant.
The
development of the red land depends upon access to it from the blue land. There
is a history of outline planning applications and consents relating to the red
and blue lands from December 14 1971 to June 30 1975. I need refer to four
only. (1) On December 14 1971 outline consent was granted for the lay-out of
roads and services for industrial/warehouse development on land which included
the whole of the blue land and a small portion of the red at its western end.
(2) On October 25 1972 outline consent was granted for parking, loading and
stacking on an area of 2.16 acres, together with a building of 12,000 sq ft on
part of the red and part of the blue lands. (3) On November 20 1973 outline
consent was granted for three warehouse units with individual access and
parking with ancillary offices to each unit in one block on part of the red
land and part of the blue land. (4) On May 14 1974 outline consent was granted
for 10,000 sq ft of offices on part of the red land at the eastern end.
Permission no (3) alone is relied on as activating clause 6. It was ultimately
conceded that permission no (4) is not relevant to this appeal.
Both counsel
concede that the answers to both questions turn on the true construction of the
deed of May 17 1973. Mr Moriarty for the claimants asks us to construe it
against the background of the statutory provisions which regulate compensation
for compulsorily-acquired land and interests in land and of the equitable
interest conferred upon the claimants by the contract of April 4 1973. Mr
Drinkwater for the corporation was, I think, compelled by the language of
clause 6(i)(c) of the deed to resile from his submission that those statutory
provisions were irrelevant; but he asked us to keep them very much in the
background and he maintained to the end that the claimants’ equitable ownership
of the red land was irrelevant. He tells us that this deed is in a standard
form which has had long and extensive use and its construction is therefore of
interest to others than the two parties to it; yet we are also to bear in mind
that it should be construed as an agreement between two statutory undertakers.
The relevant
parts of the deed are these:
This Deed of grant
is made the 17th day of May 1973 between British Railways Board (hereinafter
called ‘the Grantor’ which expression where the context so admits shall be
deemed to include its successors in title and assigns) of the one part and
British Gas Corporation whose North Thames Regional Office is at 30 Kensington
Church Street, London W8 (hereinafter called ‘the Corporation’ which expression
where the context so admits shall be deemed to include their successors and
assigns) of the other part.
Whereas: (1)
the Grantor is seised in unencumbered fee simple in possession of the land
referred to in the first Schedule hereto (hereinafter called ‘the said land’)
and (2) the Corporation are a statutory corporation established under the
provisions of the Gas Act 1972 and are the owners of a statutory gas
undertaking and desire to lay and thereafter maintain mains pipes and ancillary
apparatus in the said land and (3) the Grantor has agreed to grant to the
Corporation the easements rights and privileges hereinafter mentioned and the
Corporation have agreed to enter into the covenants hereinafter contained. Now
this Deed witnesseth as follows:
1. In
pursuance of the said agreement and in consideration of the sum of £224 now
paid by the Corporation to the Grantor (the receipt whereof the Grantor hereby
acknowledges) and of the Corporation’s covenants hereinafter contained the
Grantor as Beneficial Owner (and to the intent that the easements rights and
privileges hereby granted shall be appurtenant to the statutory gas undertaking
of the Corporation) hereby grants unto the Corporation all those easements to
lay construct erect use maintain inspect alter enlarge renew replace remove or
render unusable mains or pipes for the transmission or storage of gas or other
materials connected with the exercise and performance of the functions of the
Corporation all necessary apparatus ancillary thereto (all hereinafter together
called ‘the said works’) in through upon and over a strip of the said land 20
feet in width indicated for identification purposes only on the plan No 3564
annexed hereto and thereon coloured pink (hereinafter called ‘the said strip of
land’) and to pass over the said strip of land for the purposes of the said
works and of any works of the Corporation contiguous therewith and over the
said land for the purpose of access to the said strip of land with all
necessary workmen vehicles machinery and apparatus at all reasonable time and
in an emergency at any time To hold the same unto the Corporation in fee
simple.
2. The Corporation
(to the intent and so as to bind the easements rights and privileges hereby
granted into whosesoever hands the same may come and to benefit and protect the
said land and every part thereof) hereby covenant with the Grantor as follows:
(i) In exercising the easements rights and
privileges hereby granted the Corporation shall not unreasonably obstruct or
interfere with the user of the said land nor cause further than is reasonably
necessary any damage or injury thereto.
(ii) The Corporation shall so far as is reasonably
practicable make good all damage or injury to the said land caused by the
exercise by the Corporation of the easements rights and privileges hereby
granted and shall make full compensation to the Grantor in respect of any such
damage or injury in so far as the same shall not have been made good as
aforesaid.
Then:
3 The Grantor (to the intent and so as to bind
the said land and every part thereof into whosesoever hands the same may come
and to benefit and protect the easements rights and privileges hereby granted)
hereby covenants with the Corporation as follows:
(i) The Grantor shall not do or cause or permit
to be done on the said land anything calculated or likely to cause damage or
injury to the said works and will take all reasonable precautions to prevent
such damage or injury.
(ii) The Grantor shall not without the consent in
writing of the Corporation (such consent not to be unreasonably withheld) make
or cause or permit to be made any material alteration to or any deposit of any
thing upon any part of the said strip of land or any part of the said land
being a part nearer than 10 feet measured in any direction from the said strip
of land so as to interfere with or obstruct the access thereto or to the said
works by the Corporation or so as to lessen or in any way interfere with the
support afforded to the said works by the surrounding soil including minerals
or so as materially to reduce the depth of soil above the said works.
(iii) The Grantor shall not without the consent in
writing of the Corporation (which shall be in the absolute discretion of the
Corporation) erect or install or cause or permit to be erected or installed any
building or structure or permanent apparatus in through upon or over the said
strip of land nor save with the consent in writing of the Corporation (which
consent shall not be unreasonably withheld) any part of the said land being a
part nearer than 10 feet measured in any direction from the said strip of land.
Provided that
nothing in this Clause shall prevent the Grantor from installing necessary
services under the supervision of the Corporation or carrying on normal
agricultural operations or acts of good husbandry including fencing hedging and
ditching not causing such interference obstruction or material reduction of the
depth of soil as aforesaid.
4. If any
interference with or disturbance of the functioning of any drain or drainage
system in on or under the said strip of land or the adjoining land of the
Grantor can be shown by the Grantor to have been caused by the laying of any
main or pipe in the exercise of the easements rights and privileges hereby
granted then the Corporation shall so far as is reasonably practicable make
good any damage or injury thereby caused and shall make full compensation to
the Grantor in respect thereof in so far as the same shall not have been made
good as aforesaid.
5. Any
dispute arising under Clauses 2, 3, and 4 hereof shall be determined in default
of agreement by a single arbitrator to be agreed upon between the parties
hereto or failing agreement to be appointed on the application of either party
(after notice in writing to the other party) by the President of the Royal
Institution of Chartered Surveyors and save as aforesaid the provisions of the
Arbitration Act 1950 and of any statutory modification or re-enactment thereof
for the time being in force shall apply to any such reference and
determination.
6. (i) If at
any time (a) permission is granted under Part III of the Town and Country
Planning Act 1962 or any statutory modification or re-enactment thereof for the
time being in force (otherwise than by a development order) for development
which consists of or includes building or mining operations which the Grantor
is prevented by the covenants in Clause 3 hereof from carrying out or it is
shown that but for the said works such permission might reasonably have been
expected to be granted and (b) the said developments whether in the form for
which permission is granted as aforesaid or in any alternative form of
equivalent value for which permission might reasonably be expected to be
granted cannot reasonably be carried out elsewhere on the said land
consistently with the Grantor’s covenants in Clause 3 hereof and (c) the
principal amount of compensation which would have been payable in respect of a
compulsory acquisition by the Corporation of the easements hereby granted in
pursuance of a notice to treat served on the date hereof if such permission had
previously been granted exceeds the sum set out in Clause 1 hereof (which is
calculated without reference to the prospect of any such operations) then
subject to the provisions of this Clause the Corporation shall pay to the
Grantor a sum equal to the excess.
(ii) If the Grantor claims to be entitled to a
payment under the last foregoing sub-clause hereof he shall give notice in
writing to the Corporation of such claim and shall furnish all such particulars
in relation thereto as the Corporation may reasonably require.
(iii) There shall be deducted from any such sum
which would otherwise be payable under this Clause an amount equal to any sum
previously so paid in respect of the same land.
(iv) Any dispute arising out of the provisions of
this Clause shall be referred to a single arbitrator to be agreed upon between
the parties hereto and in default of such agreement to the Lands Tribunal.
The First
Schedule is: All that piece of land situate at Rainham in the London Borough of
Havering containing 2 acres 3,299 square yards or thereabouts shown edged green
on the plan annexed hereto.
(It is to be
noted that the land edged in green described in that Schedule is what is called
by the tribunal ‘the red land’).
Some things
about the deed are clear. 1. It binds the successors in title and assignees of
the two parties ‘where the context so admits.’
2. It recites that the board is seised in unencumbered fee simple in
possession of the red land–untruly, as the fee simple was already encumbered
with the equitable interest conferred on the claimants by the contract of April
4 1973. 3. It recites that the corporation desires to lay mains and pipes as
well as to maintain them in the red land–misleadingly, as they were already
laid. 4. The corporation is exercising and performing its functions under
sections 2 and 6 of the Gas Act 1972 and the Second Schedule to the Act in
taking the easement to do the works set out in the deed (‘the said works’) in
the 20 ft strip of the red land (Clause 1).
I read section
2 of the Gas Act 1972 and section 6 (1) and (5):
2.–(1) It shall be the duty of the Corporation to
develop and maintain an efficient, co-ordinated and economical system of gas
supply for Great Britain, and to satisfy, so far as it is economical to do so,
all reasonable demands for gas in Great Britain. . . .
6.–(1) Subject to subsections (2) and (3) below, the
Corporation shall have power to do any thing, and to enter into any transaction
(whether or not involving the expenditure of money, the borrowing of money, the
lending of money, the acquisition of any property or rights or the disposal of
any property or rights), which in their opinion is calculated to facilitate the
exercise or performance of their functions under any enactment other than this
subsection (including any enactment passed or made after the passing of this
Act), or is incidental or conducive to the exercise or performance of any such
function. . . .
(5) The provisions of Schedule 2 to this Act
shall have effect with respect to the acquisition of land by the Corporation
(and without prejudice to the generality of the said subsection (1) so far as
they concern its acquisition by agreement).
Paragraphs 5
to 19 of the Second Schedule deal with the creation of a new right and I shall
refer to paragraph 13 later.
5. The red
land and the easements are bound and protected from injury and interference by
the covenants of the Grantor and the Corporation (clauses 2 and 3).
6. There are
numerous references to the red land (‘the said land’) throughout the deed and the
only possible reference in the deed to any other land than the red land is the
reference in clause 4 to ‘the adjoining land of the Grantor,’ which might mean
either (a) the part of the red land adjoining the strip of land or (b) other
land of the Grantor adjoining the red land–that is the railway land to the
north. ‘The same land’ in clause 6(iii) refers to the land in respect of which
compensation has been previously paid under the clause but does not help to
identify what that land should be.
7. Compensation
to the Grantor for damage or injury to the red land from the easement works and
for interference with drains in the strip or adjoining land of the Grantor is
to be ‘full’–without further elaboration or definition (Clauses 2(ii) and 4)
and to be determined in default of agreement by a single arbitrator or, failing
agreement, the President of the Royal Institution of Chartered Surveyors
(clause 5). Those clauses leave to clause 6 provision for compensating the
Grantor (or its successors in title or assignees) in the future for loss of
development rights or value (such development as permitted building or mining
operations) if the loss exceeds £224.
8. By clause
6(i)(a) this compensation is to be payable if at any time permission for
certain developments is granted or might reasonably have been expected to be
granted but for the restrictions imposed on the Grantor (or its successors) by
clause 3. By clause 6(i)(b) it is nevertheless not to be payable then if those
developments could reasonably be carried out elsewhere on the red land. By
clause 6(i)(b) it is nevertheless not to be payable then if those developments
could reasonably be carried out elsewhere on the red land. By clause 6(i)(c) it
is to be payable if the permission required by clause 6(i)(a) has been or would
be granted for developments within clause 6(i)(a) which cannot reasonably be
carried out elsewhere on the red land and if the amount of compensation
prescribed by clause 6(i)(c) exceeds £224. If the Grantor claims to be entitled
to payment under subclause (i), it must give notice to the Corporation under
subclause (ii), by subclause (iii) any sum previously paid under the same
subclause in respect of the same land must be deducted and by subclause (iv)
its claim if disputed is referred to a single arbitrator and in default of
agreement to the Lands Tribunal. Subclause (i)(c) appears to provide a deferred
means of assessing compensation with reference to the prospect of such
operations as building or mining operations, the £224 paid under clause 1
having already been assessed without reference to such prospect. The assessor
is required to take the permission, actual or potential, which qualifies for
payment of compensation under subclause (i)(a), to treat that permission as
granted before the date of the deed, to assume that a notice to treat had been
given on the same date in respect of a compulsory acquisition by the
Corporation of the easements granted to it by the deed and to determine what
principal amount of compensation would then have been payable for that
notionally permitted development.
Now at the
date of the deed the parties were concerned with the red land, an easement over
part of it and how its development value might be restricted by the easement.
But it was a small piece of land lacking access and any development of it would
have to be carried out by using the blue land and might well be carried out in
conjunction with development on the blue land. Indeed, outline consents already
mentioned had been granted for development on the red land and the blue land
together on December 14 1971 and October 25 1972. Furthermore, it was at the
date of the deed the law, and had been the law at least since 1845, that
compensation payable to a landowner whose lands had been compulsorily acquired
included with the value of the land taken (the purchase money) compensation for
damage sustained by severing of the land taken from other lands of his and for
injurious affection of other lands of his by the exercise of the compulsory
powers: see Lands Clauses Consolidation Act 1845, sections 48, 63 and 68. The
right to compensation for the injurious affection to land retained, as well as
for land taken, is preserved by section 7 of the Compulsory Purchase Act 1965,
as modified by paragraph 13 of Schedule 2 to the Gas Act 1972, which provides
as follows:
For section 7
of that Act (that is the 1965 Act) (measure of compensation) there shall be
substituted the following: ‘7. In assessing the compensation to be paid by the
acquiring authority under this Act regard shall be had not only to the extent
(if any) to which the value of the land over which the right is to be acquired
is depreciated by the acquisition of the right but also to the damage (if any)
to be sustained by the owner of the land by reason of its severance from other
land of his, or injuriously affecting that other land by the exercise of the
powers conferred by this or the special Act’
In spite of
the difficulty of attaching the words ‘injuriously affecting’ to any particular
preceding words in this or earlier statutory versions, and although no land was
in fact taken by12
the corporation but the land was merely subjected to the corporation’s
easement, compensation would clearly in law have been payable in respect of a
compulsory acquisition by the corporation of the easements granted by the deed
in pursuance of a notice to treat served on the claimants and the board (see
section 5 of the Compulsory Purchase Act 1965) on May 17 1973, if permission
for development within clause 6(i)(a) had previously been granted, for the
extent to which the value of the red land had been depreciated by the
acquisition of the easement and the right to carry out the ancillary works and
also for injurious affection to the blue land by the exercise of the powers
conferred by sections 2 and 6 and by the execution of the ancillary works. If
the creation and acquisition of the new right of an easement over the red land
and its exercise not only depreciated the value of the red land but injuriously
affected the blue land by restricting development on parts of both lands,
compensation would be payable both for that depreciation and for that injurious
affection under paragraph 13 of the Second Schedule and therefore, in my
judgment, under clause 6(i)(c) of the deed, provided the total exceeded £224.
The injurious affection would be a head of compensation payable ‘in respect of’
the compulsory acquisition no less than the depreciation.
A third factor
is that at the date of the deed the claimants had a contract to purchase the
red land and so were equitable owners of it and were already legal owners of
the blue land. There is authority–not binding on us, but not challenged by the
corporation–for holding that they, not the board, although both should have
been served with the notice to treat, were therefore to be treated at the date
of the notice to treat as the party entitled to compensation: Hillingdon
Estates Co v Stonefield Estates Ltd [1952] Ch 627; and that as
owners of the blue land they were entitled to be paid compensation for any loss
(or a fortiori for any depreciation) of their equitable interest in the red
land which injuriously affected the blue land: Oppenheimer v Ministry
of Transport [1942] 1 KB 242.
There was no
evidence that the corporation knew of the claimants’ contract of purchase or
that it was registered as a land charge so as to affect the corporation with
notice of it; and I for my part do not think that any duty of the corporation
to make diligent inquiry under section 5 of the Compulsory Purchase Act 1965 comes
into the questions we have to decide.
The only
qualifying permission on which the claimants rely for an affirmative answer to
the first question is the outline consent for warehouses and offices on part of
the red land and part of the blue land. It was on that planning consent that
the claim was founded and the tribunal held that it succeeded. Does that
permission fall within clause 6(i)(a) on its true construction? If it does, there is no dispute that it is
not disqualified by subclause (i)(b).
The reasons
for the tribunal’s decision on this first question are not altogether clear and
the construction of subclause (i)(a) on which counsel for the claimants relied
to support his decision shifted between the opening and the close of the appeal
hearing. I cannot myself doubt that it refers to permission for development of
the said land which consists of or includes building or mining operations on
the said land and that the words ‘or includes’ do not embrace such operations
outside the said land, but are inserted, as counsel for the corporation
submitted, to cover material changes of use, the other category of development
than such operations. The words ‘of the said land’ are too obvious to need
insertion in subclause (i)(a) and their insertion in subclause (i)(b) supports
their implication in subclause (i)(a). But this construction of clause 6(i)(a)
does not determine the first question, for granted that the qualifying
permission must be a permission to develop the red land, must it be a
permission to develop that land alone and not other land with it? Does the inclusion in the permission of
November 20 1973 of other land than the red land with the red land qualify or
disqualify the permission? Does
subclause (i)(c) indicate or decide the correct answer? By going through the hypothetical motions of
backdating the permission of November 20 1973 to May 17 1973 or before it and
supposing a notice to treat for the purchase of the easement on that day and a
compulsory acquisition of the easement by the corporation, does one end up
inside or outside the area of subclause (i)?
By putting the permission through this process, does it emerge qualified
or disqualified?
If the clock
is put back to May 17 1973, and notice to treat is assumed to be given then, it
seems to me to follow: (1) from the unchallenged authorities cited to us that
the claimants would be the party entitled to be compensated for the compulsory
purchase of the easement, just as much as they would have been if the
conveyance of the red land to them had also been backdated from June 7 1973 to
the same date and had made them assignees three weeks earlier than in fact they
were; (2) from paragraph 13 of the Second Schedule to the Gas Act 1972, that
the claimants would be entitled to compensation for any permitted development
which the existence of the easement and clause 3 of the deed prevented them
from carrying out not only on the red land, but also on the blue land. Those
consequences would indicate that the permission to develop partly on the red
land and partly on the blue does qualify for inclusion in subclause (i)(a)
unless that would be repugnant to other provisions of the deed or the whole
tenor of the deed. If I am right in thinking that an assignee of the red land
with the legal ownership of both red and blue land would have been entitled to
compensation, the problem would seem to be whether the context, of clause 6 in
particular, admits that the expression ‘the grantor’ includes its successors in
title or assignees. If it does, it also admits the equitable owner of the red
land with the consequences I have just stated; if it does not, it excludes that
owner and the blue land from consideration.
There is a
strong case for saying that the deed read as a whole is concerned only with the
red land as at May 17 1973 and its development thereafter, that the rights of
the claimants under the deed against the corporation are the rights of the
board under it as at that date, and that the fact that the red land was already
in equitable ownership of a third party which had the legal ownership of the
adjoining blue land is an irrelevant accident which should not be allowed to
increase the value of the red land by thousands of pounds. But counsel for the
corporation had eventually to concede that the statutory background of
compensation for compulsorily acquired land or interests in land was introduced
into the picture by clause 6(i)(c), and the question seems to me to be whether
you can or must cut down the consequences of its introduction by eliminating
some of them in deference to the intent of the deed as a whole.
With
considerable hesitation I have come to the conclusion that there is nothing to
be collected from the deed, its wording or the circumstances which surrounded
its making, which is clear to establish an intention to cut down the right to
compensation which subclause (i)(c) would appear in its ordinary meaning to
confer upon the claimants. I would therefore hold that the Lands Tribunal came
to a correct decision in point of law in answering the first question in favour
of the claimants and holding that the permission of November 20 1973 entitled
them to claim compensation under clause 6.
Then comes the
second question: what is the correct basis of valuation? Was it Valuation II? I find it as difficult as I think the
tribunal and counsel have found it to keep the two questions separate. But I
think that it follows from the claimants’ common ownership of the red and blue
lands and their consequent right to claim compensation for injurious affection
of the blue land by prevention of development on the red land that they are
entitled to compensation for being prevented from joint development of the red
and blue lands and that Valuation I is right. That may be said to result in a
windfall for the claimants, an open-ended commitment for the corporation and an
arbitrary and capricious increase of the burden imposed by the one on the
other, or rather by the board on the corporation. I13
express no opinion on the question whether that might give the corporation any
sort of claim against the board. But if the burden imposed on the red land by
the easement injuriously affects the blue land, the basis of compensating the
common owner must be the joint development which the easement prevents. I would
therefore hold that Valuation I is the correct basis, hold that the tribunal
came to a wrong decision in law in awarding compensation on the basis of
Valuation II and substitute for the tribunal’s award of £44,776 an award of
£84,776.
If I am wrong
in holding that Valuation I applies, I would uphold the tribunal’s preference
for Valuation II over Valuation III. The choice between them depends on
deciding whether rule (3) of section 5 of the Land Compensation Act 1961,
applies to the facts which have been agreed by the parties or found by the
tribunal. That section provides:
Compensation
in respect of any compulsory acquisition shall be assessed in accordance with
the following rules: (1) No allowance shall be made on account of the
acquisition being compulsory: (2) The value of land shall, subject as
hereinafter provided, be taken to be the amount which the land if sold in the
open market by a willing seller might be expected to realise: (3) The special
suitability or adaptability of the land for any purpose shall not be taken into
account if that purpose is a purpose to which it could be applied only in
pursuance of statutory powers, or for which there is no market apart from the special
needs of a particular purchaser or the requirements of any authority possessing
compulsory purchase powers.
Counsel for
the claimants contends that there is a market for the purpose of the
development for which the red land is suitable or adaptable apart from the
special needs of the claimants; for the tribunal has found that there would be
purchasers for the red land other than the claimants, including the board, a
person who might wish to use the red land for a car park, a speculator, a
purchaser of the red and blue lands together and a purchaser of the red land
hoping for access from the blue. And he relied on Corrie v Central
Land Board (1954) 4 P & CR 276. But, as counsel for the corporation
points out, the rule does not refer to a market for the land but a market for a
purpose of its owner alone and the purpose must be a purpose for which the
quality of the land is suitable or adaptable: Lambe v Secretary of
State for War [1955] 2 QB 612. There was no finding by the tribunal of any
market for such a purpose apart from the special needs of the claimants
themselves. The purpose for which they specially needed the red land was to
marry it with the blue land for joint development. In Corrie’s case
there were possible purchasers of the land other than the Coal Board for the
purpose of ‘tipping.’ So counsel for the
claimants changed his ground and submitted that the marriage of the red and
blue lands was not such a purpose, there was no such quality of the red land proved,
and if there was, no resulting enhancement of its value proved.
On that fresh
ground, not apparently raised before the tribunal, which decided in favour of
Valuation II because the case was ‘on all fours with Corrie,’ I would
have preferred Valuation II to Valuation III, had I not decided that Valuation
I was the correct basis of compensation.
GEOFFREY LANE
LJ: This appeal concerns a reference by Blandrent Investment Developments Ltd
(hereinafter called ‘the claimants’) to the Lands Tribunal to determine the
amount of compensation payable by the British Gas Corporation in accordance
with a deed of grant dated May 17 1973 in respect of a parcel of land some 2.66
acres in area at Rainham. The member of the tribunal published his award on
October 19 1976 in the form permitted by Rules of the Supreme Court, Order 61,
rule 1 (4) and the practice direction of this court dated July 27 1956. That
was done because the parties found themselves unable to agree upon the manner
in which the points of law which they desired should be determined were to be
expressed.
There are
three areas of land which require description: (1) Furthest north is land owned
at all material times and still owned by British Railways Board (hereinafter
referred to as ‘British Rail’). That land carries Rainham railway station and
the permanent way. (2) Adjoining that to the south is the 2.66 acres in the
shape of a long narrow roughly rectangular area referred to throughout as ‘the
red land.’ Prior to April 1973 that land
had also been in the ownership both legal and equitable of British Rail. (3)
Further south still a much larger area of land, again roughly rectangular,
bounded on the north by the red land, on the west by Rainham Creek, and on the
east by Ferry Lane. That area is called ‘the blue land’ and at all material
times was owned by the claimants.
The history of
events is as follows. Before the events with which we are concerned the Gas
Board had laid three separate pipelines across a portion of the red land; in
1962 a 4-in pipe, in 1964 a 6-in, and in 1971 a 24-in pipe. These pipes run
under the red land, just to the north of and parallel with its boundary with
the blue land. On January 11 1973 the claimants took a conveyance of the blue
land. On March 21 1973 the Gas Corporation wrote to British Rail approving a
draft deed of grant in respect of the use of the land for the pipeline. On
April 4 1973 the claimants contracted to buy the red land from British Rail for
£27,500. On May 17 1973 the deed of grant was executed by British Rail in
favour of the Gas Corporation giving to the corporation an easement in respect
of their pipelines in consideration of the payment of £224. On June 7 1973–that
is to say, some three weeks after the execution of the deed of grant–the red
land was conveyed to the claimants by British Rail. By this date an estate road
was under construction on the blue land and the blue land was being filled to
raise it to the level of the red land.
The
configuration of these various plots is such that no development of the red
land would be allowed by means of access direct from Ferry Lane. Consequently,
it is essential, in order to make any profitable use of the red land, to gain
access to it from the blue land.
On November 20
1973 outline planning consent was given to the claimants for a warehouse and
offices to be built partly on the red land and partly on the blue land. It is
this consent which is the only one among many which is material to this appeal.
As appears
from the short statement of facts, the claimants derive their standing in this
action simply and solely from British Rail, their predecessors in title. That
being so, it seems to me that they possess the same rights against the Gas
Corporation as British Rail would have had, if they had at the date of the
hearing still been the freeholders of the land under which the pipes had been
laid. No one disputes that the material date for ascertaining those rights is
the date of the deed of grant; that is, May 17 1973. No one suggests that the
claimants are entitled to pray in aid anything which has happened since that
date to enlarge their claim. It follows that the claimants’ rights must be
determined by the terms of the deed of grant upon which British Rail’s rights
were founded. That document describes the situation unequivocally, if
inaccurately. The corporation desire to lay . . . pipes in the said land.
British Rail is seised, it declares, of an unencumbered fee simple in
possession of the land (the red land); they are the owners of the red land.
There is no mention of the other land owned by British Rail to the north and,
of course, there is no mention of the blue land which belongs to neither party
to the deed. There is no mention of any equitable rights vested in the
claimants or in anyone else. It seems to me to be a strange proposition that in
the face of that document and those assertions, on which this claim is
necessarily based, the claimants are entitled to say that the deed was wrong,
that there was an encumbrance; that the claimants had contracted to buy the red
land; that, moreover, they had already bought the blue land to the south;
accordingly that they are entitled to base their claim to compensation on the
injurious affection which the pipelines have caused not only to the red but
also to that blue land.
The claimants’
contention is based on the wording of clause 6 of the deed of grant, which runs
as follows:
6. (i) If at
any time (a) permission is granted . . . for development which consists of or
includes building . . . operations which the Grantor is prevented by the
covenants in Clause 3 hereof from carrying out . . .14
and (b) the said developments . . . cannot reasonably be carried out elsewhere
on the said land consistently with the Grantor’s covenants in Clause 3 hereof
and (c) the principal amount of compensation which would have been payable in
respect of a compulsory acquisition by the Corporation of the easements hereby
granted in pursuance of a notice to treat served on the date hereof if such
permission had previously been granted exceeds the sum set out in Clause 1
hereof (which is calculated without reference to the prospect of any such
operations), then subject to the provisions of this Clause the Corporation
shall pay to the Grantor a sum equal to the excess.
Mr Moriarty’s
argument, as I understand it, is based on these provisions of clause 6(i)(c),
and runs as follows. In order to come to a conclusion with regard to this
subsection, it is necessary to inquire what would have been the situation if
there had been a notice to treat on the date of the grant, namely May 17 1973.
If there had been such a notice to treat it would, on the authorities, have had
to be served on the claimants as the holders of the equitable title to the
land, or at least upon both British Rail (the legal owners) and the claimants
(the equitable owners). That being the case, the claimants would have been
entitled to claim compensation in respect of injurious affection to any land of
which they were then the owners whether at law or in equity and accordingly
their claim in respect of the blue land is properly founded, because they were
at the time of the grant the equitable owners of the red land. It seems to me
that that argument is founded on a fallacy. It is perfectly true that clause
6(i), with its three subclauses, provides that certain matters must be established
before a claimant is entitled to compensation. That is, however, very far from
saying that clause 6 is capable of altering the basis upon which the grant was
made to the claimants’ predecessors in title. That would to my mind be giving
to the subclause an effect far beyond anything which the draftsman can have
intended.
No doubt, if
the decision of Vaisey J in Hillingdon Estates is correct and applicable
and if there had truly been a notice to treat, then things might have been
different. One observes that the situation in Hillingdon Estates was the
converse. There it was the notice to treat which was real and the contract and
the parties thereto which were notional. Here there was not a true notice to
treat. The only notice to treat is a notional one, and the notional notice to
treat should, as I see it, be a notice based on the actual grant, that is to
say a notice requiring treaty between British Rail and the Gas Corporation and
therefore confined to the land owned by British Rail at the date of the grant.
It is unnecessary to decide whether one should consider only the red land or
whether one should also include the other British Rail land to the north. As I
read clause 6 as a whole, it seems to me that it is referable only to
operations carried out on the ‘said land’ which is the red land. The reference
in subclause 6(i)(b) to the requirement that the developments must not be
capable of being carried out ‘elsewhere on the said land’ indicates clearly
that no other land is in contemplation and certainly no land belonging to a
person who is not a party to the deed. I find it impossible to construe 6(i)(c)
as in any way enlarging the rights of the grantor. If anything, it is
restricting his rights by imposing a condition which must be fulfilled before he
is entitled to compensation. Furthermore, the final words of this subclause
(‘which is calculated without reference to the prospect of any such
operations’) seem to me to refer to operations and developments on the ‘said’
or red land. It cannot be inferred from those words that the parties had it in
mind that other land owned by someone not a party to the deed should if
injuriously affected entitle the party to compensation. Those words imply the
opposite.
For those
reasons, it seems to me that the claimants fail to show that the blue land has
any relevance to the question of compensation. As I understand the situation,
it was not contended on behalf of the claimants that on this interpretation of
the deed any claim to compensation can arise by virtue of the planning
permission of November 20 1973. In any event, on the claimants’ own valuation
on this basis compensation is nil. The corporation nevertheless say they are
willing to pay compensation of £5,100 less the £224 consideration for the
grant. That is a matter for them. I would allow the appeal of the corporation
and substitute an order that the corporation is not bound to make any payment
by way of compensation to the claimants. I would dismiss the claimants’ appeal.
Agreeing with
Geoffrey Lane LJ, CUMMING-BRUCE LJ said: The first question is whether the
operative words of clause 6 impose an obligation on the grantee of the
easements to pay to the grantor’s successor in title compensation for injurious
affection to other land of that successor in title. By clause 6 (i)(c), the
measure of compensation is that sum which would have been payable in respect of
a compulsory acquisition by the grantee in pursuance of a notice to treat
served on the date of the deed, May 17 1973, less the sum set out in clause 1.
If the
corporation has compulsorily acquired the easements and served notice to treat
on May 17 1973, the claimant as owner of the equitable interest in the red land
would have been entitled to compensation for injurious affection to the blue
land being other land of the claimant within the meaning of paragraph 13 of the
Second Schedule to the Gas Act 1972, provided that it could show that planning
permission had been granted for joint development on the red and blue lands
which would be prevented by the grant of the easements. And such planning
permission was granted on November 20 1973. This follows from the combined
effect of the decisions in Oppenheimer and Hillingdon Estates. By
the former case the notice to treat identified ‘the interest’ of the claimants,
that is, their equitable interest in the red land; by the latter case an
equitable interest so identified entitles the claimants to compensation for
injurious affection not only to the red land but also to other land of theirs
pursuant to paragraph 13 of the Second Schedule to the Gas Act.
But this was
not a compulsory acquisition and notice to treat was never served. It is a
grant of the easement for an agreed measure of compensation against the
background that had agreement not been reached the procedure for compulsory
acquisition would have been pursued. The question therefore resolves itself
into a question of construction of clause 6 in order to determine what
compensation or measure of compensation the parties agreed.
Clause 6(i)
determines the measure of compensation by reference to three contingencies.
Clause 6(i)(a) defines the first contingency: ‘Permission is granted . . . for
development which consists of or includes building or mining operations which
the Grantor is prevented by the covenants in Clause 3 hereof from carrying out
or it is shown that but for the said works such permission might reasonably
have been expected to be granted.’ By
the introductory words of the deed, the expression ‘the Grantor’ where the
context so admits shall be deemed to include its successors in title and
assigns. In clause 6 (i)(a) the context does so admit, so that permission for
development including building fulfils the condition provided that the
permission relates to land contemplated by the clause. Mr. Moriarty submitted
that the phrase ‘which consists of or includes building or mining operations
which the Grantor is prevented from carrying out . . .’ was to be understood in
a geographical sense; that is, that if the permission related both to the red land
and to the blue land, the permission was permission ‘including’ the red land
even though the Grantor had not to be regarded as having an interest in the
blue land at the date of the deed. I cannot accept that ‘including’ is there
intended to carry such a meaning. The phrase ‘consists of or includes building
or mining operations’ defines the character of the relevant operations and does
not refer to the extent of the land upon which those operations are carried
out.
Clause 6(i)(b)
provides that compensation shall only be payable in respect of development
which cannot reasonably be carried out elsewhere ‘on the said land.’ The meaning of ‘the said land’ has to be
collected from the first recital and is the parcel of land described in the
First Schedule to the deed; that is, the red land. This is a strong indication
that in relation to15
compensation the parties were only contemplating development upon the red land.
If the parties
had had in contemplation development upon other land of the Grantor as well as the
land described in the schedule, it is to be expected that they would have also
disqualified for compensation development upon such other land which could be
carried out elsewhere upon that other land. Mr Moriarty accepts that the
limited extent of the exclusion indicates that the parties were then focusing
attention too exclusively upon rearrangement of development upon the red land,
but submits that that is an anomaly which should not be regarded as throwing
light on the intention of the parties to be collected from other paragraphs of
clause 6. I reject that submission.
Clause 6(i)(c)
sets out the measure of compensation. First it is necessary to calculate the
amount of compensation which would have been payable in respect of compulsory
acquisition. Had the grantor owned the legal and equitable interests in the red
land at the date of the deed, the only question of construction would have been
whether the parties contemplated compensation for injurious affection to other
land of the Grantor as well as to the red land which was specified in the First
Schedule to the deed. But in fact on April 4 1973 the Grantor entered into a
contract with the claimants to sell the red land to them. So that from that
date the equitable interest in the red land was vested in the claimants who
already owned the blue land. As a result, the principal amount of compensation
which would have been payable to them in respect of a compulsory acquisition by
the corporation in pursuance of a notice to treat served on May 17 would have
included compensation for injurious affection of the blue land which they
already owned. But did the clause contemplate that the Grantee should be under
an obligation to pay only such compensation as the British Railways Board would
have been entitled to on compulsory acquisition, or did it contemplate the
entitlement to compensation of a successor in title who already at the date of
the deed held the equitable interest in the red land and who already held the
legal interest in the blue land to the south of the red land? Clause 6(i)(c) itself is silent, and clause
6(i)(b) suggests that the parties were contemplating compensation for injurious
affection of the red land alone. There is sufficient uncertainty about the
intention of the parties to be collected from the words of clause 6(i)(c) to
entitle the court to look elsewhere in the deed and to have regard, if
necessary, to the recitals as an aid to construction of the operative words.
The observations of Lord Macnaghten in Orr v Mitchell [1893] AC
238, at p 254, apply:
When the
words in the dispositive or operative part of a deed of conveyance are clear
and unambiguous they cannot be corrected by reference to other parts of the
instrument. When those words are susceptible of two constructions the context may
properly be referred to for the purpose of determining which of the two
constructions is the true meaning. In order to justify a reference to the
context for this purpose, it is not necessary that the language of the
dispositive or operative clause should be ambiguous in the sense that without
some help you cannot tell which of the two meanings should be taken. The rule
applies though one of the two meanings is the more obvious one, and would
necessarily be preferred if no light could be derived from the rest of the
deed. For the purpose of construing the dispositive or operative clause, the
whole of the instrument may be referred to though the introductory narrative or
recitals leading up to that clause are, perhaps, more likely to furnish the key
to its true construction than the subsidiary clauses of the deed.
In the deed
dated May 17 the first recital describes the interest of the Grantor: ‘The
Grantor is seised in unencumbered fee simple in possession of the land referred
to in the first Schedule hereto (hereinafter called ‘the said land’).’ This recital clearly denies the existence of
any other person having any interest in the red land. The grantee contracted
with the Grantor on that basis. Though a successor in title could succeed to
the rights and privileges of the Grantor, he could not increase the burden of
compensation falling upon the Grantee. This suggests that the common intention
of the parties to the deed was that compensation for injurious affection in
clause 6(i)(c) should be limited to injurious affection of the interests in
land held by the Grantor on May 17 1973, an inference consistent with the
inference to be drawn from clause 6(i)(b).
The strongest
reason for doubt about the validity of this construction arises from the
statement of Mr Drinkwater that this deed was drafted from a pro forma which
had for years been used by the British Gas Corporation or its predecessors.
This explains the inaccuracy of the second recital. The corporation did not in
fact ‘desire to lay’ mains and pipes in the strip of the red land wherein the
easements were granted. The pipes had been laid in 1962 and 1964. So, if the
second recital contained a careless inaccuracy as a consequence of the use by
the corporation of a form with an inappropriate recital, it may be dangerous to
look to the first recital which turns out on the facts also to be inaccurate.
Against this background, Mr Moriarty submits that it is wrong to hold that the
construction of the operative words of clause 6 may be aided by looking at the
recitals. If it is right to have regard to Mr Drinkwater’s statement that the
deed was prepared from a pro forma frequently used by the Gas Corporation, it
is also right to have regard to the finding that a letter dated March 21 1973
was sent by the assistant solicitor to the compensation authority to the chief
legal adviser and solicitor to British Railways Board agreeing the draft of the
deed. This date was before the date of the contract whereby the Grantor agreed
to convey the red land to the claimants. At the date when the draft of the deed
was agreed, the first recital was accurate, and in my view it may be looked at
to clarify the uncertainty which exists upon the intention of the parties in
clause 6. I observe that it is a relevant feature of the history that by the
conveyance dated June 7 1973 the claimants acquired the red land with notice of
the deed of May 17 between British Railways Board and the Gas Corporation. So
the claimants took the red land with notice that the British Railways Board had
represented to the Gas Corporation that no one else had any interest in the red
land at the date of the deed whereby the measure of compensation for the grant
of the easement was agreed.
For those
reasons, I would hold that the claimants are not entitled to any compensation
for injurious affection caused by prevention of joint development by them upon
the red land and the blue land. Their rights are restricted to compensation for
prevention of development upon the red land alone. That compensation on the facts
found is nil, though the corporation are apparently willing to pay £5,100 less
the £224 consideration for the grant. I would allow the appeal of the
corporation and substitute the order proposed by Geoffrey Lane LJ. I would
dismiss the claimants’ appeal. Had I taken the same view as Stephenson LJ upon
the construction of the deed, I would respectfully agree with him that
Valuation I was the correct basis of compensation, for the reasons that he has
given.
The appeal of
the claimants, Blandrent Investment Developments Ltd, was dismissed with costs
in the Court of Appeal and below. The cross-appeal of the compensating
authority, British Gas Corporation, was allowed with costs in the Court of
Appeal and below.