Hillingdon London Borough Council v ARC Ltd
MR STANLEY BURTON QC, sitting as deputy judge of the division
Compulsory purchase — Compensation — Entry under section 11 of Compulsory Purchase Act 1965 — Whether claim for compensation subject to limitation period under section 9 of Limitation Act 1980 — Whether cause of action accrues on entry of acquiring authority — Whether reference to Lands Tribunal an action to recover sums
On December 24 1980 the plaintiff council
made a compulsory purchase order which related, inter alia, to land of
which the defendant held a lease. On April 26 1982, the council entered and
took possession of the defendant’s land pursuant to the service of a notice to
treat and notice of intention to enter served on April 7 1982. On April 19 1982
the defendant served a notice of claim in response to the notice to treat. On
January 2 1992 the defendant’s claim relating to the works carried out by the
council was received by the council and rejected. On October 25 1993 a further
claim was made and rejected. On September 6 1995 the defendant made a reference
to the Lands Tribunal. On May 21 the Lands Tribunal declined jurisdiction to
decide whether the defendant’s claim was statute-barred by section 9 of the
Limitation Act 1980. The council commenced the present proceedings to have that
question decided.
Held: The cause of action of the defendant
for the purposes of section 9 of the Limitation Act 1980 accrued on April 26
1982, on the council’s entry on the land under section 11 of the Compulsory
Purchase Act 1965. Subject to any question of estoppel, the limitation period
within which the defendant should have commenced an action to recover
compensation had expired.
Compulsory purchase — Compensation — Entry under section 11 of Compulsory Purchase Act 1965 — Whether claim for compensation subject to limitation period under section 9 of Limitation Act 1980 — Whether cause of action accrues on entry of acquiring authority — Whether reference to Lands Tribunal an action to recover sums
On December 24 1980 the plaintiff council
made a compulsory purchase order which related, inter alia, to land of
which the defendant held a lease. On April 26 1982, the council entered and
took possession of the defendant’s land pursuant to the service of a notice to
treat and notice of intention to enter served on April 7 1982. On April 19 1982
the defendant served a notice of claim in response to the notice to treat. On
January 2 1992 the defendant’s claim relating to the works carried out by the
council was received by the council and rejected. On October 25 1993 a further
claim was made and rejected. On September 6 1995 the defendant made a reference
to the Lands Tribunal. On May 21 the Lands Tribunal declined jurisdiction to
decide whether the defendant’s claim was statute-barred by section 9 of the
Limitation Act 1980. The council commenced the present proceedings to have that
question decided.
Held: The cause of action of the defendant
for the purposes of section 9 of the Limitation Act 1980 accrued on April 26
1982, on the council’s entry on the land under section 11 of the Compulsory
Purchase Act 1965. Subject to any question of estoppel, the limitation period
within which the defendant should have commenced an action to recover
compensation had expired.
Obiter: The Lands Tribunal is a court of law
within the meaning of the 1980 Act and can order the payment of compensation. A
reference to the Lands Tribunal is an action to recover a sum of money for the
purposes of the period of limitation under the 1980 Act.
The following cases are referred to in
this report.
Attorney-General v BBC [1981] AC 303;
[1980] 3 WLR 109; [1980] 3 All ER 161, HL
Central Electricity Generating Board v Halifax Corporation
[1963] AC 785
China v Harrow Urban District Council
[1954] 1 QB 178; [1953] 3 WLR 885; [1953] 2 All ER 1296; (1953) 51 LGR 681
Co-operative Wholesale Society v Chester le Street
District Council (1996) 73 P&CR 111; [1996] 2 EGLR 143; [1996] 46 EG
158
Coburn v Colledge (1897) 1 QB 702
Pegler v Railway Executive [1948] AC 332;
[1948] 1 All ER 559; (1948) 64 TLR 212, HL
Scott v Avery (1856) 5 HLC 811
Swansea City Council v Glass (Executor)
[1992] QB 844; [1992] 3 WLR 123; [1992] 2 All ER 680; (1992) 90 LGR 265; [1992]
1 EGLR 303
Turner v Midland Railway Co [1911] 1 KB
832
West Riding County Council v Huddersfield Corporation
[1957] 1 QB 540; [1957] 2 WLR 428; [1957] 1 All ER 669; (1957) 55 LGR 153
This was the hearing of an originating
summons issued by the plaintiffs, Hillingdon London Borough Council; the
defendant was ARC Ltd.
Joseph Harper QC (instructed by the
solicitor to Hillingdon London Borough Council) appeared for the plaintiffs;
Neil King (instructed by Lawrence Tucketts) represented the defendant.
Giving judgment, MR STANLEY BURTON QC said: This case raises an interesting
and important point of law. The sole question before me is whether a claim for
compensation for compulsory purchase, resulting from the entry by an acquiring
authority on land pursuant to section 11 of the Compulsory Purchase Act 1965,
is subject to the limitation period laid down in section 9 of the Limitation
Act 1980, notwithstanding that the amount of compensation payable has not been
agreed or determined by the Lands Tribunal.
It is widely assumed, on the basis of the
decision of the Divisional Court in Turner v Midland Railway Co
[1911] 1 KB 832, that no limitation period is applicable until the amount of
compensation has been agreed or determined. For example, in Co-operative
Wholesale Society v Chester le Street District Council (1996) 73
P&CR 111*, the President, Judge Bernard Marder QC, said, at p120:
*Editor’s note: Also reported at [1996] 2
EGLR 143
… where an acquiring authority chooses to
proceed in pursuance of a Compulsory Purchase Order by the more conventional
route of a Notice to Treat followed by Notice of Entry, there is no statutory
time limit for a reference of disputed compensation to the Lands Tribunal.
The plaintiff contends that this
assumption is incorrect.
I add that there is also an issue between
the parties as to whether, if the defendant’s claim for compensation would
otherwise be statute-barred, by their conduct the plaintiffs have precluded
themselves from relying on the limitation defence, or have waived the
limitation period. That issue only arises if the plaintiffs succeed on the
point of law, and will be determined subsequently if necessary.
The facts
The facts of this case for present
purposes are not in dispute. On March 23 1972 the defendant became the lessee
of land bordering the Grand Union Canal and known as the West Drayton
Aggregates Depot under a lease for 35 years from December 24 1970. On December
24 1980, the plaintiffs made a compulsory purchase order which related, inter
alia, to land which was part of that depot. The compulsory purchase order
was the London Borough of Hillingdon Yiewsley By-Pass (Cherry Lane Roundabout
to High Street Yiewsley) compulsory purchase order (No 1) 1980 (‘the compulsory
purchase order’). In relation to this litigation, it involved principally land
on which supports for a single carriageway road was to rest and to the airspace
that the road would go through. On December 21 1981 the Secretary of State
confirmed the compulsory purchase order without amendment.
22
On March 22 1982 the plaintiffs served a
notice to treat in respect of the defendant’s land, and on April 7 1982 the
plaintiffs served a notice of intention to enter. On April 19 1982 the
defendant served a claimant’s claim in answer to notice to treat. On April 26
1982 the plaintiffs entered and commenced what are referred as ‘the Phase I
Works’. (The phase II works, which involved dualling a single carriageway, came
later and did not result from a compulsory acquisition.) The phase I works were
completed in April 1984, and on May 11 1984 the (first) carriageway opened. On
March 29 1991 the freehold reversion of land and rights relating to acquired
land (and the phase II land); were conveyed to the plaintiffs by the British
Waterways Board. On January 2 1992, the defendant’s claim relating to the above
(phase I) works and further (phase II) works was received by the plaintiffs
(and rejected). On the October 25 1993 a further claim was submitted by the
defendant (and rejected by the plaintiffs).
Eventually, on September 6 1995 the
defendant made its reference to the Lands Tribunal. On December 12 1995, the
registrar of the Lands Tribunal ordered, among other things, that the following
point of law be determined, namely:
(1) Whether any claim for compensation by
ARC Limited arising from the exercise by the London Borough of Hillingdon of
its powers under the (Compulsory Purchase Order) is now barred as a result of
the provisions of (section 9(1)) of the Limitation Act, 1980.
On May 21 1996, the Lands Tribunal
declined jurisdiction to decide that issue. These proceedings were commenced by
originating summons on July 9 1996.
Statutory framework
(a) Compulsory purchase
The defendant’s right to compensation (in
respect of the phase I works) arose under the Compulsory Purchase Act 1965, as
a result of the expropriation of land by virtue of a confirmed compulsory
purchase order.
Section 1 of the 1965 Act provides:
This Act shall apply in relation to any
compulsory purchase to which Part II of the Acquisition of Land Act 1981 or
Schedule 1 to that Act applies
The defendant’s entitlement to
compensation arose as a result of the entry on the land by the acquiring authority,
on April 26 1982. Section 11 of the 1965 Act, so far as is material, is as
follows:
(1) If the acquiring authority have
served notice to treat in respect of any of the land and have served on the
owner, lessee and occupier of that land not less than fourteen days notice, the
acquiring authority may enter on and take possession of that land, or of such
part of that land as is specified in the notice; and then any compensation
agreed or awarded for the land of which possession is taken shall carry interest
… from the time of entry until the compensation is paid, or is paid into court
in accordance with this Act.
…
(2) The acquiring authority may also
enter on and take possession of any of the land by following the procedure in
Schedule 3 to this Act.
(3) …
(4) Except as provided by the foregoing
provisions … the acquiring authority shall not, except with the consent of the
owners and occupiers, enter on any of the land subject to compulsory purchase
until the compensation payable for the respective interests in that land has
been agreed or awarded, and has been paid …
Schedule 3 to the 1965 Act provides an
alternative procedure for obtaining right of entry. Basically this involves the
acquiring authority securing the compensation in order to obtain entry. The
security can be paid into court or a bond can be given; and the amount is such
as is determined by an independent surveyor appointed by two justices of the
peace.
Section 7 of the 1965 Act provides:
In assessing the compensation to be paid
by the acquiring authority under this Act regard shall be had not only to the
value of the land to be purchased by the acquiring authority, but also to the
damage, if any, to be sustained by the owner of the land by reason of the
severing of the land purchased from the other land of the owner, or otherwise
injuriously affecting that other land by the exercise of the powers conferred
by this or the special Act.
In relation to disputed compensation,
section 6 provides:
If a person served with a notice to treat
does not within twenty-one days from the service of the notice state the
particulars of his claim or treat with the acquiring authority in respect of his
claim, or if he and the acquiring authority do not agree as to the amount of
compensation to be paid by the acquiring authority for the interest belonging
to him, or which he has the power to sell, or for any damage which may be
sustained by him by reason of the execution of the works, the question of
disputed compensation shall be referred to the Lands Tribunal.
This is consistent with section 1 of the
Land Compensation Act, 1961:
Where by or under any statute … land is
authorised to be acquired compulsorily, any question of disputed compensation …
shall be referred to the Lands Tribunal and shall be determined by the Tribunal
in accordance with the following provisions of this Act.
(b) Limitations
It is common ground between the parties
that the applicable provision of the Limitation Act 1980 is section 9(1):
An action to recover any sum recoverable
by virtue of any enactment shall not be brought after the expiration of six
years from the date on which the cause of action accrued.
The Compulsory Purchase Act 1965 does not
contain any provision concerned expressly with limitation of actions. However,
section 10 of the Compulsory Purchase (Vesting Declarations) Act 1981 provides
as follows:
10 Acquiring authority’s liability
arising on vesting of land
(1) Where any of the land specified in a
general vesting declaration has become vested in an acquiring authority by
virtue of Part III of this Act, the acquiring authority shall be liable to pay
the like compensation, and the like interest on the compensation agreed or
awarded, as they would have been required to pay if they had taken possession
of the land under section 11(1) of the Compulsory Purchase Act 1965.
(2) …
(3) The time within which a question of
disputed compensation arising out of an acquisition of an interest in land in
respect of which a notice to treat is deemed to have been served by virtue of
Part III of this Act may be referred to the Lands Tribunal shall be 6 years
from the date at which the person claiming compensation, or a person under whom
he derives title, first knew, or could reasonably be expected to have known, of
the vesting of the interest by virtue of Part III of this Act.
This subsection shall be construed as one
with Part I of the Limitation Act 1980.
I must also mention section 3(6)(a)
of the Lands Tribunal Act 1949:
3 Procedure, appeals, costs and fees
…
(6) Subject to the provisions of this
Act, rules may be made for 10 regulating proceedings before the Lands Tribunal
… and may in particular —
(a) make provision —
(i) …
(ii) as to the time within which any
proceedings before the Lands Tribunal are to be instituted;
Neither the Lands Tribunal Rules 1975 nor
the Lands Tribunal Rules 1996 make any such provision.
The issues
Mr Joseph Harper QC, for the plaintiffs,
submitted that the defendant’s cause of action arose when the plaintiff entered
upon and took possession of the land in question in accordance with the
procedure laid down in section 11 of the 1965 Act. From that date, the
defendant had a right to compensation, and indeed to interest on that
compensation. The compensation to which the defendant was entitled was ‘a sum
recoverable by virtue of any enactment’ within the meaning of section 9 of the
Limitation Act 1980, irrespective of 23
whether the compensation had been quantified by agreement or by the Lands
Tribunal, and the defendant’s cause of action accrued on the plaintiffs’ entry
upon the land. It followed that an action to recover such compensation cannot
be brought after the expiration of six years from the date of the plaintiffs’
entry, namely April 26 1982. On this basis, the applicable limitation period
expired long ago, in 1988.
Mr Neil King, for the defendant,
submitted that the defendant’s cause of action was not complete, and therefore
did not accrue, until the amount of its compensation was either agreed or
determined by the Lands Tribunal. Until then, there is no ‘sum recoverable by
virtue of any enactment’. Since there has been no such agreement or
determination, and the defendant’s compensation remains unquantified, the
limitation period in respect of its claim has not started to run, let alone
expired.
Neither of these submissions as enlarged
upon in the course of argument, would if accepted produce a particularly
attractive result. Mr Harper submitted that an ‘action’ within the meaning of
section 9 of the Limitation Act, 1980 is an action in the High Court (or
presumably in appropriate cases the county court). Since the claimant’s cause
of action accrues on entry, he argued that in order to stop the limitation period
from running, a claimant must issue a writ claiming his compensation from the
acquiring authority before the expiration of six years from the date of entry,
whether or not his claim has been referred to the Lands Tribunal. He submitted
that the function of the Lands Tribunal was merely to quantify the amount of
compensation, so that a writ could be issued claiming compensation in such
amount as may be determined by the Lands Tribunal. In practice, no steps would
normally be taken to prosecute an action so commenced prior to the decision of
the Lands Tribunal, but the action could be struck out if the claimant failed
diligently to seek a decision by the Lands Tribunal as to his compensation. In
this way, an acquiring authority would have some sanction available to them in
the event of delay on the part of a claimant in presenting or in prosecuting
his claim to compensation.
A writ seeking an order for the payment
of a sum to be ascertained by some other tribunal would be unusual, and its
issue would seem to have no point, where the defendant is necessarily a public
authority, and as such certain to pay in accordance with the decision of the
Lands Tribunal, except to prevent a limitation defence arising. Normally, the
only issues between the parties to such litigation would be those referred to
the Lands Tribunal. It is the Lands Tribunal, not the High Court, which must
determine ‘the question of disputed compensation’. It follows that the action
in the High Court would not result in any decision of the court on any of the
issues between the parties, or, because the obligor is always a public
authority, normally result in execution of any judgment obtained. It is however
fair to say that in practice, if Mr Harper’s submissions represent the law,
where a claim for compensation is being diligently pursued, one may expect the
parties to agree to extensions of the limitation period in order to avoid the
unnecessary costs of issuing and serving, and then dealing with, High Court
actions. None the less, Mr Harper’s submissions involve the proposition that a
claimant who has referred his claim to compensation to the Lands Tribunal, and
is diligently prosecuting his reference before the Lands Tribunal, may find his
claim for compensation statute-barred during the pendency of the Lands Tribunal
proceedings if he fails to issue a protective writ. Given that claims for
compensation for compulsory purchase are often not decided within the six-year
period, if Mr Harper’s submissions are correct, section 9 of the Limitation Act
1980 is indeed a trap for the unwary.
I find the consequences of Mr King’s
submissions equally unattractive. If he is correct, a claimant may delay in
referring his claim to compensation to the Lands Tribunal for 10 or 20 years
without losing his right to make a reference. In the present case, 13 years
elapsed between entry on the land and the reference to the Lands Tribunal, and
if Mr King is correct, the cause of action for compensation still has not
accrued. This would, in my view, be an ‘anomalous and inconvenient result’ (to
adopt the words of Lopes LJ in a somewhat different context in Coburn v Colledge
(1897) 1 QB 702, at p709). It is right that the acquiring authority can
themselves refer his claim to the Lands Tribunal; but to expect them to do so
is akin to expecting a potential defendant in ordinary litigation to issue
proceedings for a declaration as to the amount of his liability. Furthermore,
it is not clear why parliament should have provided for a limitation period
under section 10(3) of the 1981 Act, but none otherwise.
Section 10(3) of the 1981 Act suggests,
however, that a reference to the Lands Tribunal stops time running in the same
way that an action does in private litigation. This led me to consider whether
a reference to the Lands Tribunal is, ‘An action to recover any sum recoverable
by virtue of any enactment’ for the purposes of section 9 of the Limitation Act
1980. If it is, this would provide a sensible answer to the questions raised in
this case. A claimant would be bound to refer any question as to his
compensation to the Lands Tribunal within six years of his right to
compensation accruing, and it would be unnecessary for him in addition to
commence a pointless High Court action to preserve his cause of action.
However, I do not have to reach a conclusion on this point. The crucial
question before me is whether the defendant’s cause of action accrued in April
1982, on the plaintiffs’ entry on the land under section 11 of the 1965 Act. If
it did, and if the compensation payable by the plaintiffs is a sum recoverable
by virtue of an enactment, the limitation period applicable to the compensation
claim has expired, because no action to recover the compensation was brought
within the limitation period; and, subject to the issue of waiver, no such
action can now be brought.
I turn first to the authorities on the
question when a cause of action accrues for the purposes of limitations.
The authorities
(a) Prior to the Limitation Act 1939
Mr King submitted that there is
authority, binding on me, to the effect that the cause of action for
compensation for compulsory purchase does not accrue until the amount of
compensation is agreed or determined, namely the decision of the Divisional
Court in Turner v Midland Railway Co [1911] 1 KB 832. Indeed, it
is clear that it is this decision which is the basis for the common assumption
to that effect.
In Turner the plaintiff had been
the owner of houses which had been injuriously affected, within the meaning of
section 68 of the Lands Clauses Act 1845, by works carried out by the defendant
under a special Act of parliament. The works had been completed in April 1903.
The plaintiff made a claim for compensation for the first time in August 1909.
The defendant refused to pay, and the matter went to arbitration. The
arbitrator awarded £10 8s as compensation, plus costs of £79. When the
plaintiff brought an action on the award in the county court, the defendant
contended that the action was barred by the Statute of Limitations 1623. The
county court judge held that the cause of action arose upon the presentation of
the claim for compensation, and that the action was consequently brought in
time. On appeal, Mr Danckwerts KC for the defendant appellant accepted that the
appeal must fail. He argued, however, that the judge below had applied the
wrong limitation period, and that the correct limitation period was 20 years,
under the Civil Procedure Act 1833, rather than six years under the Statute of
Limitations, on the basis that:
The action is not brought upon the award,
for the award does nothing more than fix the amount. The right of action is
given by the statutes authorizing the work, and the amount when assessed
becomes a statutory debt. The action is an action of debt upon the statute. But
an action for a statutory debt is treated as an action of debt upon a
specialty, and therefore falls within s 3 of 3 & 4 Will. 4, c. 42 [The
Civil Procedure Act 1833], and not within the statute of James I. The period of
limitation, therefore, is twenty years. The result is that this appeal must
fail; but it is desired to have the decision put on the true ground.
Perhaps not surprisingly, given that the
concession that the appeal must fail, counsel for the plaintiff was not called
upon.
Ridley J said:
24
Mr Danckwerts has not convinced me that
the Statute of Limitations applicable to this case is the 3 & 4 Will. 4, c.
42, under which the period of limitation would be twenty years instead of six.
I think that we ought to hold the case to fall within the statute of James I. The
effect of work being done under the authority of a statute is that any cause of
action in respect of damage caused by the execution of the work is prevented
from accruing, the work being made lawful. And even though the statute may
incorporate s 68 of the Lands Clauses Act, that will give no cause of action in
respect of the damage. That section gives, not a cause of action for a wrong,
but compensation for damage by a lawful act. At the date, therefore, of the
execution of the work, and down to the time of the arbitrator’s award, there is
no cause of action at all to which the Statute of Limitations can apply. But on
the making of the award a cause of action, in my opinion, for the first time
arises. The action is founded on the award and on the award alone, and it is
from the date of the award that the statute runs.
Avory J said:
I am of the same opinion. I agree that
there was no cause of action till the award was made. The statute which
empowered the defendants to do the work did not give rise to any cause of
action. The defendants in doing the work did something which they were
authorized to do. All that s 68 gave was a right to compensation, which is a
very different thing from a cause of action. But until the amount of that
compensation was ascertained by the award no action could be brought. With
regard to the period of limitation Mr Danckwerts says that the period
applicable is twenty years. With that I cannot agree.
Given the concession by the appellant
that the appeal must fail, I am not sure that the judgments in Turner
are binding authority. But in any event, it is impossible to understand them
without appreciating the provisions of the Statute of Limitations then in
force. Section 3 of the statute imposed a limitation period of six years for,
among other things, ‘all Actions of Trespass, … all Actions … upon the Case,
all Actions of Debt grounded upon any Lending or Contract without Specialty’.
Once the court had decided that the plaintiffs’ claim did not come within the
Civil Procedure Act 1833, debt was the only head under which her cause of
action could come. There was no 5 equivalent of section 9 of the 1980 Act.
Compensation for a lawful act, as Ridley J put it, was not a cause of action
for the purposes of the Statute. As Avory J put it:
All that s 68 gave was a right to
compensation, which is a very different thing from a cause of action.
The causes of action to which Avory J was
referring were those set out in the Statute 10 of Limitations. A debt is
necessarily a liquidated sum. It followed that there could be no completed
cause of action, among those set out in the Statute of Limitations, until the
compensation was quantified.
However, a right to compensation may be a
right to a ‘sum recoverable by virtue of (an) enactment’ within the meaning of
section 9 of the Limitation Act, 1980, and if it 15 is, there is a cause of
action for the purposes of section 9 of the 1980 Act. Turner cannot be
authority on this question, since there was no such provision when it was
decided.
Mr Harper sought to distinguish Turner
on the additional ground that it was a decision on compensation for injurious
affection, rather than for the taking of land by compulsory purchase. I do not
think that this is a valid ground for distinguishing that case from the present.
In cases of injurious affection, as in cases of taking of land, it is possible
to identify when the event giving rise to the right to compensation occurs, and
in both cases the claim for compensation is unquantified until agreed or
determined by the appropriate tribunal.
I therefore turn to consider the
authorities on section 9 and its precursors.
(b) Authorities on the Limitation Acts
1939 and 1980
Section 2(1)(d) of the Limitation
Act 1939 was the precursor of section 9 of the Limitation Act 1980. It
provided:
(1) The following actions shall not be
brought after the expiration of six years from the date on which the cause of
action accrued, that is to say: —
…
(d) actions to recover any sum
recoverable by virtue of any enactment, other than a penalty or forfeiture or
sum by way of penalty or forfeiture.
Section 31(1) of the 1939 Act defined
‘action’ as follows:
In this Act, unless the context otherwise
requires …
‘action’ includes any proceedings in a
court of law, including an ecclesiastical court;
For present purposes, there is no
material difference between the terms of the 1939 Act and those of the 1980
Act.
The first case cited to me which was
decided under the 1939 Act was Pegler v Railway Executive [1948]
AC 332. In Pegler the claimant had claimed compensation on the ground
that he had suffered loss as a result of the postponement of his promotion as a
railway employee. The loss arose because in 1924 there had been a change in his
conditions of employment, which were alleged to be contrary to the provisions
of Schedule III of the Railways Act 1921. In immediate financial terms, his
loss was suffered in 1933, when a man who under the original conditions of employment
would have been junior to him, but who under the new conditions was senior to
him, was promoted to be a driver, whereas the claimant was not so promoted
until 1936. Schedule III created a right to compensation for his loss, and
provided that any question as to whether there had been a breach of the
relevant provision of the statute should be referred to statutory arbitration,
and that the arbitrator should award a claimant such sum as was sufficient to
compensate him for his loss. The claimant made a claim for compensation in
1942. The respondent argued that his claim was statute-barred. It was argued on
behalf of the claimant that no cause of action arose until the date of the
arbitration award, or when he made his claim for compensation, and at the earliest
when he first suffered any financial loss, in 1933, and that he continued to
suffer loss until he reached the maximum rate of pay in 1937.
The House of Lords held that the claim
was statute-barred. The fact that his claim was to be determined by arbitration
meant that references in the 1939 Act to ’cause of action’ had to be read as
’cause of arbitration’. The claimant’s cause of action accrued when his
conditions of employment were changed to his detriment, notwithstanding the
difficulties of then quantifying his loss.
Pegler is not authority on the meaning of ‘any
sum recoverable by virtue of any enactment’, because it was common ground
between the parties that the limitation period applicable to the claim was six
years, and there was no discussion as to whether these words applied to the
claim.
In China v Harrow Urban
District Council [1954] 1 QB 178, the respondent rating authority had
applied to the justices for a distress warrant to recover rates which had
fallen due before July 1940. Lord Goddard CJ held that the expression ‘action’
in the Limitation Act 1939 was to be widely construed, and included an
application for a distress warrant. Rates were a sum payable by virtue of an
enactment, and the cause of action in relation to them arose when demand was
made for their payment, which was more than six years before the application
for the distress warrant. Lord Goddard said, at p186:
But when I find reference both to
ecclesiastical courts and to all classes of arbitration in the present Act it
leads me to think that the legislature meant to bring every class of
litigation, before whatever tribunal it might come, within the ambit of the
statute.
Sellers LJ said, at p186:
In this special case the question has
been raised, apparently for the first time in the courts, whether the
provisions of section 2(1)(d) of the Limitation Act 1939, apply to
proceedings brought in a court of summary jurisdiction for the issue of a
distress warrant for the recovery of rates …
The main question which arises is whether
the definition of ‘action’ in section 31(1) of the Act of 1939 can be applied
to section 2. Section 31 (1), as far as it is material, is as follows — ‘In
this Act, unless the context otherwise requires … ‘Action’ includes any
proceeding in a court of law, including an ecclesiastical court.’
It was submitted on behalf of the
respondents that the context in section 2 did require that some restriction
should be put on the words ‘any proceeding in 25
a court of law’ because the section makes the time of limitation run from the
date ‘on which the cause of action accrued,’ and it was said this was
inappropriate to the procedure by which and by which alone, rates can be
recovered. But whilst in the case of rates it cannot be said there is a cause
of action — Liverpool Corporation v Hope [1938] 1 KB 751 — there
does arise a cause of proceeding in a court of law. If the appropriate
proceedings are taken to enforce a debt for rates the hearing is a judicial
proceeding and not as the respondents apparently submitted before the justices
a ministerial matter: Potts v Hickman [1941] AC 212. In such a
judicial proceeding matters have to be proved by the applicant and issues may
be raised by a person so summoned before the court. The elements for
constituting a proceeding in a court of law are present. In Roberts v Metropolitan
Borough of Battersea (1914) 110 LT 566 Buckley LJ said (at ibid
568): ”Proceeding’ would be a word with a larger meaning than ‘action.’ Every
action is a proceeding, but it is not possible to say that every proceeding is
an action.’
The definition in the Act was obviously
intended to enlarge the more normal meaning of action and I do not think the
context of section 2 does require that the definition of ‘action’ should not be
applied to it. If the definition is applied, then the section should be read to
provide that the following proceedings in a court of law shall not be brought
after the expiration of six years from the date on which the cause of
proceedings in a court of law accrued, that is to say, (d) proceedings in a
court of law to recover any sum recoverable by virtue of any enactment. That
interpretation seems to me to be in harmony with the context, not repugnant to
it.
In Davis v Burrell and Lane
10 CB 821, Jervis CJ said (ibid 826): ‘When a rate is duly made and
published, it is the duty of the parties assessed to seek out the collector and
to pay it … The statute 43 Eliz. c. 6 [Apparently a reference to the Poor
Relief Act 1601] requires a personal demand before the rate can be distrained
for. That shows that a demand would otherwise be unnecessary.’ The cause of the
proceedings, therefore, for a rate might be said to arise when the rate is duly
made and published and is not paid, but a demand as a matter of procedure has
always been necessary before the recovery of the rate could be enforced. In
respect of a general rate, section 7 of the Rating and Valuation Act, 1925,
requires that information with respect to a number of matters shall be included
in the demand note on which the general rate is levied. As proceedings cannot
be taken until such a demand note has been given and the demand has not been
met, I think the cause of the proceedings for a rate should be held to be the
failure to pay on demand and, if I am right that section 2 can be applied to
the proceedings for a distress warrant, the period of six years in which the
proceedings must be taken would run from the time of the demand of the rate in
question. I agree that the justices came to an incorrect decision in law and I
would allow the appeal.
Havers J said, at p190:
In my opinion, it is clear that
proceedings for the recovery of rates do not fall within the category of
personal actions mentioned in section 3 of the Limitation Act, 1623, or within
any other Limitation Act which was in force prior to the Act of 1939. It is
perhaps somewhat surprising that, if it was intended to make a change in the
law for the first time since 1601 by imposing a limitation of time upon
proceedings for the recovery of rates, clearer language specifically referring
to rates should not have been used in section 2 of the Limitation Act of 1939.
The Act of 1939 is, however, an amending as well as a consolidating Act, and as
the language used in section 2(1)(d) and section 31 is apt to cover an
application to justices for the issue of a distress warrant for arrears of
rates, I see no good reason why such proceedings should be excluded. My view is
strengthened by a comparison between the definition of ‘action’ in section 225
of the Supreme Court of Judicature (Consolidation) Act, 1925, and in section 31
of the Limitation Act of 1939. In the former, ”Action’ means a civil
proceeding commenced by writ or in such other manner as may be prescribed by
rules of court, but does not include a criminal proceeding by the Crown.’ The
wide words of the definition in the Limitation Act, 1939, show that it was
intended to bring within the ambit of section 2 proceedings to which the term
‘action’ would not normally be appropriate.
It remains to consider the meaning of
’cause of action’ if ‘action’ is to be considered as including proceedings for
the recovery of rates. If the word ‘action’ is to embrace proceedings which are
not actions in the ordinary sense, ’cause of action’ should, in my view, be
read as ’cause of proceeding.’ The cause of the proceedings, in my opinion,
accrues when a ratepayer fails to pay on demand a rate duly made and published
in respect of which he has been assessed and the period of six years in which
the proceedings must be taken would run from the failure to pay on demand.
The judgments in China are
important in two respects. First, they demonstrate the width of meaning to be
given to the word ‘action’ in the Limitation Acts. Second, they show that the
words ’cause of action’ must be similarly, and consequentially, widely
construed. Of particular relevance in the present connection is the statement
of Sellers J, at p187, that ‘whilst in the case of rates it cannot be said
there is a cause of action … there does arise a cause of proceeding in a court
of law’, and therefore a cause of action within the meaning of the Limitation
Acts. It is to be contrasted with the statement of Avory J, in Turner,
that ‘a right to compensation … is a very different thing from a cause of
action’. The meaning of ’cause of action’ depends on the context, and in
particular on the meaning given to ‘action’.
The width and effect of section 2(1)(d)
of the 1939 Act were further emphasised by the judgment of Lord Goddard CJ in West
Riding County Council v Huddersfield Corporation [1957] 1 QB 540.
Orders had been made under the Local Government Act 1929 transferring parts of
the area of the West Riding County Council to the Borough of Huddersfield. The
Local Government Act 1933 provided for there to be financial adjustment
resulting from such a transfer, which in default of agreement was to be
referred to arbitration. The county council presented their claim to
Huddersfield more than six years after the transfer. Lord Goddard held that the
arbitration was to recover a sum of money by virtue of the provisions of the
1933 Act, and was therefore statute-barred.
The decision of the House of Lords in Central
Electricity Generating Board v Halifax Corporation [1963] AC 785
arose from the transfer of the assets of electricity undertakings to electricity
boards under the Electricity Act 1947. By the Electricity Act 1947, the assets
and liabilities of electricity undertakings were transferred to electricity
boards which were set up to carry on the nationalised industry. A number of
local authorities, including the respondents, were electricity undertakers, and
special provision was made for the separation and transfer to the boards of
those parts of their assets and liabilities which pertained to their
electricity undertakings. The combined effect of sections 14(1) and 15(1) of
the 1947 Act was that:
property held or used by the local
authority wholly or mainly in their capacity as authorised undertakers, and
rights, liabilities and obligations acquired or incurred by the local authority
in the said capacity ‘should’ on the vesting date vest by virtue of this Act
and without further assurance in such electricity board or boards as may be
specified in the following provisions of this section or determined thereunder.
In general the assets and liabilities
vested in the appropriate area board, but under proviso (iii) to section 14(2)
all investments and cash vested in the central authority, British Electricity
Authority, of which the appellants were the successors. Before the ‘vesting
date’, which was April 1 1948, the respondent local authority had accumulated a
fund of £34,500 out of the revenues of their electricity undertaking. On March
31 1948, they transferred that fund from their electricity account to their
general rate account. It would seem that they relied on some provision in a
private Act. It did not appear when this first came to the knowledge of the
electricity authority, but nearly three years elapsed before a claim was made
that this fund had vested in the authority by virtue of the Act. The claim was
denied by the respondents, but no further action was taken until January 3
1957. On that date the dispute was referred to the minister under section 15
(3), of which the relevant parts were:
Any question arising under this section
as to whether any property is; or was held or used by any such local authority
wholly or mainly in their capacity as authorised undertakers … or whether any
rights, liabilities or obligations were acquired or incurred by any such local
authority in the said capacity … shall, in default of agreement, be determined
by the Minister of Health …
By that time more than six years had
elapsed since the vesting date. The respondents contended that the appellants’
claim was barred by section 2 (l)(d) of the Limitation Act 1939. The
minister held that the question whether the claim was statute-barred was not
for him and he decided on September 18 1958, that this sum was held by the
respondents wholly or mainly in their capacity as electricity undertakers. The
respondents refused to pay this sum to the appellants 26
and on March 6 1959, the action was begun by the appellants, claiming that the
sum of £34,500 due to them.
The House of Lords held that the claim
was statute-barred, notwithstanding that, if the question whether the money in
question had been held by the respondents in their capacity as electricity
undertakers had been denied by them, that question could only have been
determined by the minister. The requirement of the minister’s decision was
procedural rather than substantive. Lord Reid said, at p801:
No new right or liability came into
existence at its date (ie the date of the Minister’s decision) … the effect of
the Minister’s decision was merely to prove that this sum had belonged to the
appellants ever since the vesting date. It created no new right of property or
chose in action: it merely enabled a pre-existing right to be enforced …
If the appellants had begun an action
within six years of the vesting date, and had applied to the Minister for his
decision when the respondents traversed their allegation that the sum sued for
had been held or used by the respondents in their capacity of electricity
undertakers, proceedings in the action could, if necessary, have been stayed to
await the Minister’s decision. But they did not do that and, in my judgment,
this action is barred by section 2(1)(d) of the Limitation Act.
The CEB case shows that a cause of
action may accrue although one of the issues which may be, or is, raised as to
the cause of action cannot be decided by the court before which the action must
be brought.
Last, I must refer to the decision of the
Court of Appeal in Moore v Gadd, The Times, February 17 1997, in
which it was held that proceedings under section 214 of the Insolvency Act 1986
for a declaration that a director knew or ought to have concluded that there
was no reasonable prospect that a company would avoid going into insolvent
liquidation and that he should make a contribution to the assets of the company
were proceedings to ‘recover any sum recoverable by virtue of any enactment’
within section 9 of the Limitation Act, 1980.
These authorities establish the following
propositions:
(1) The expression ‘action’ in section 9
is extremely wide, encompassing all proceedings in a court of law: China
v Harrow Urban District Council.
(2) The expression ’cause of action’ in
section 9 is correspondingly wide: China v Harrow Urban District
Council.
(3) What may not have been a cause of
action under the Statute of Limitations, 1623, may be a cause of action for the
purposes of the Limitation Act 1980: China v Harrow Urban District
Council.
(4) The policy of the Limitation Acts, to
prevent the litigation of stale claims, is equally applicable to claims against
public authorities for sums payable by them pursuant to statute: the CEB
case and the West Riding County Council case.
(5) A cause of action may accrue for the
purposes of section 9 although a constituent element of the cause of action, if
disputed, may have to be determined by someone other than a court of law: the CEB
case.
(6) An action may be for a sum
recoverable by virtue of an enactment even though the liability in question is
not and cannot be quantified when the action is commenced: Moore v Gadd.
Accrual of the cause of action
In the light of these authorities, I turn
to the issue in this case, namely when the defendant’s cause of action accrued
or will accrue.
It was common ground that the question
when the cause of action arose depends on the true construction of the
enactment which created the right to compensation, that is the 1965 Act. In
this connection, see Swansea City Council v Glass (Executor) [1992]
2 All ER 680*, per Taylor LJ at p685h:
*Editor’s note: Also reported at [1992] 1
EGLR 303
Where the cause of action arises from
statute, the question as to what is merely procedural and what is an inherent
element in the cause of action is one of construction.
As is well known, the 1965 Act, like
other enactments in this sphere, does not in terms confer a right to
compensation. The right to compensation was effectively created by judicial
decision. The 1965 Act assumes that there is a right to compensation, and
section 11, with which I am primarily concerned, assumes that compensation may
be awarded in respect of the land of which possession is taken. There is
nothing in section 11 to suggest that the right to compensation is inchoate or
incomplete, and the express provision that such compensation is to carry
interest from the time of entry until the compensation is paid strongly
suggests that the right to compensation accrues at the time of entry.
It is true, of course, that compensation
is not quantified until agreed or awarded. However, many causes of action
accrue before the plaintiff is able to quantify his claim, and before a
specific figure is agreed or determined for it. The authorities to which I have
referred above make it clear that a ‘sum recoverable by virtue of any
enactment’ need not be liquidated or quantified.
Furthermore, the legislation does not
suggest that the agreement of the parties as to the amount of compensation, or
that the award of the Lands Tribunal, constitutes or completes the right of
action. To the contrary, the wording of section 6 of the 1965 Act that ‘the
question of disputed compensation shall be referred to the Lands Tribunal’
suggests a procedural provision, whereby what is alleged to be an existing
right to compensation is referred for decision, rather than a substantive
provision, completing an inchoate cause of action. The wording of section 10 of
the 1965 Act, that in the case of a claim for compensation for injurious
affection, ‘any dispute arising in relation to the compensation shall be
referred to and determined by the Lands Tribunal’ is even clearer, following
the wording of a typical and conventional arbitration agreement, which applies
to an accrued cause of action or cause of arbitration. The is no wording
suggestive of a Scott v Avery (1856) 5 HLC 811 approach. It has
not been suggested that a different rule as to the accrual of a cause of action
should apply under section 10 to that under section 11.
I am fortified in my view that the cause
of action accrues on entry by the wording of section 10 of the Compulsory
Purchase (Vesting Declarations) Act 1981. It in effect treats the cause of
action for compensation under that section as accruing when the land in
question vests in the acquiring authority. It is inconsistent with the
limitation period in relation to such compensation starting to run only when
the compensation is agreed or awarded. It expressly refers to section 11 of the
1965 Act, which suggests that parliament assumed that there was no material
difference between the right to compensation under section 11 of the 1965 Act
and under section 10 of the 1981 Act.
The only indication to the contrary is
the provision of section 3(6)(a) of the Lands Tribunal Act 1949, to
which I have referred above. It is however too equivocal to lead me to conclude
that limitation of actions for the recovery of compensation for compulsory
purchase is not subject to section 9(1) of the Limitation Act 1980.
I therefore conclude, and hold, that the
defendant’s cause of action accrued on April 26 1982, on the plaintiffs’ entry
on the land, pursuant to section 11 of the 1965 Act.
It follows that, unless by reason of its
conduct the plaintiffs are not entitled to rely on section 9 of the Limitation
Act, no action to recover the defendant’s compensation may now be brought.
Is a reference to the Lands Tribunal ‘an
action to recover’ compensation?
It is on the facts of the present case
unnecessary for me to decide whether it is sufficient for a claimant of
compulsory purchase to refer the question of his compensation to the Lands
Tribunal within six years of his claim arising in order to prevent his claim
becoming statute-barred, or whether, as Mr Harper submitted, he must issue a writ
in the High Court. In the present case, the defendant took neither step. It
follows that any view that I express as to whether a reference to the Lands
Tribunal is an action to recover compensation for the purposes of section 9 of
the Limitation Act 1980 will be obiter. I raised this question with
counsel after the conclusion of oral argument, but, because its resolution is
unnecessary for the determination of the present case, I did not think it
appropriate to involve the parties in the additional costs of a further hearing
for it to be argued orally.
I do, however, question whether it is
necessary for High Court proceedings to be issued. In the first place, I
consider that the Lands Tribunal is a court of law within the meaning of
section of the 27
Limitation Act. What is a court of law, at least for the purposes of the law of
contempt of court, was most recently authoritatively considered in Attorney-General
v BBC [1981] AC 303. In the House of Lords, Viscount Dilhorne at p338
and Lord Edmund-Davies at p350 considered the Lands Tribunal to be a court of
law. Lord Scarman, at pp359–360, formulated the test to be applied as follows:
I would identify a court in (or ‘of’)
law, ie a court of judicature, as a body established by law to exercise, either
generally or subject to defined limits, the judicial power of the state. In
this context judicial power is to be contrasted with legislative and executive
(ie administrative) power. If the body under review is established for a purely
legislative or administrative purpose, it is part of the legislative or
administrative system of the state, even though it has to perform duties which
are judicial in character. Though the ubiquitous presence of the state makes
itself felt in all sorts of situations never envisaged when our law was in its
formative stage, the judicial power of the state exercised through judges
appointed by the state remains an independent, and recognisably separate,
function of government. Unless a body exercising judicial functions can be
demonstrated to be part of this judicial system, it is not, in my judgment, a
court in law.
In my view, the Lands Tribunal is a court
of law within this test. It has a specialised and defined jurisdiction, but
this does not prevent its being a court of law. Its functions, procedural
rules, powers and its composition qualify it as a court of law. Furthermore,
the context here is the Limitation Act 1980 rather than contempt of court, and
as has been seen it contains a wide definition of a court of law. The only
indication to the contrary is that the Lands Tribunal is a ‘tribunal’
designated under the Tribunals and Inquiries Act 1992, in Schedule 1, as a
tribunal under the supervision of the Council on Tribunals; from which it would
seem to follow that it is not one of the ‘ordinary courts of law’: see section
l(l)(b). Given the width of the definition of a court of law in the
Limitation Act 1980, I do not think that it follows that the Lands Tribunal
cannot be a court of law for the purposes of that Act, even if it is not an
‘ordinary court of law’ (which it clearly is not) for other purposes.
Is a reference to the Lands Tribunal ‘an
action to recover’ compensation within the meaning of section 9(1) of the
Limitation Act 1980, or only a procedural step required in order to quantify a
sum to be recovered by an action before another court? Both Mr Harper and Mr
King stated, and I accept, that the Lands Tribunal only quantifies a claim for
compensation. This may be explicable on the basis that no order for the payment
of compensation is in practice necessary because the party liable is always a
public authority. However, whether a reference to the Lands Tribunal is an
action for the recovery of the compensation in question depends on the
procedure and powers of the tribunal, as set out in the relevant statutes and
in its procedural rules.
The wording of the 1965 Act and of the
Land Compensation Act 1961 that the ‘question of disputed compensation’ be
referred to the Lands Tribunal seems to me sufficient to enable the Lands
Tribunal to make an order for payment of disputed compensation. The wording of
section 10 of the 1965 Act, similar to that found in a typical arbitration
clause, would also justify such an order: arbitrators regularly make
enforceable awards, ordering the payment of a sum of money, in the exercise of
the contractual jurisdiction created by such words. It was not suggested that
these provisions deprived the High Court of jurisdiction to decide the issue
raised by the originating summons.
Under r 38 of the Lands Tribunal Rules
1975, which were in force at the times material to this case, section 26 of the
Arbitration Act 1950 was made applicable to all proceedings in the Lands
Tribunal as it applied to an arbitration. It follows that an award of
compensation could have been enforced, by leave of the High Court, in the same
manner as a judgment to the same effect, and, where leave was given, judgment
might be entered in terms of the award. This suggests that the Lands Tribunal
had power, under those rules, to award (that is to say, make an order for) the
payment of compensation by an acquiring authority to a claimant: there would
otherwise be no point in this provision applying to ‘all proceedings’. R 38
also made applicable to all proceedings in the Lands Tribunal sections 14
(interim awards) and 20 (interest on awards) of the Arbitration Act 1950.
Section 20 of the Arbitration Act 1950 was as follows:
A sum directed to be paid by an award
shall, unless the award otherwise directs, carry interest as from the date of
the award …
Thus, the 1975 rules envisaged that the
Lands Tribunal could direct that compensation be paid. The Lands Tribunal also
had power, under section 4 of the Land Compensation Act 1961 and under r 56, to
direct that the costs of a party be paid by the other party to the proceedings.
Under the Lands Tribunal Rules 1996
(which did not apply when, as I have held, the cause of action of the defendant
accrued and when it became statute-barred) the Lands Tribunal has express power
to award interest in the same way as an arbitrator, and section 20 of the
Arbitration Act 1950 was again applied to ‘all proceedings as they apply to an
arbitration (r 32(e)). It would be strange if, having power to award
interest on compensation (that is to say, to make an order that it be paid by
the acquiring authority), it does not have power to award the principal sum,
that is the compensation, itself. It also has power to make an order as to
costs, to direct that the costs of a party be paid by the another party: r 52.
R 50(3) empowers the tribunal to ‘issue an order incorporating its decision’.
For reasons which are obscure, the 1996 Rules did not contain the equivalent of
r 38 of the 1975 Rules, enabling an award of the Lands Tribunal to be enforced
in the same way as an arbitration award.
These provisions would lead me to
conclude that a reference to the Lands Tribunal was, and is, ‘an action to
recover’ compensation for the purposes of the Limitation Act 1980. I add that
there is nothing in the Lands Tribunal Rules that would lead me to doubt my
conclusion as to the accrual of the defendant’s cause of action. To the
contrary, the reference in r 10(5) of the 1996 Rules to ‘A notice of reference
in relation to the compensation payable on the compulsory acquisition of land’
is consistent with my conclusion.
Lastly, it seems to me that section 10(3)
of the Compulsory Purchase (Vesting Declarations) Act 1981, indicates that
parliament assumed that the reference of a question of disputed compensation to
the Lands Tribunal was the equivalent of the commencement of a High Court
action for the purposes of the Limitation Act 1980. If this is the position,
the law is more just and practical and consistent than it would be if the
position were as suggested by Mr Harper.
Assuming that an action for a declaration
of the sum payable by a defendant is not an ‘action to recover’ that sum for
the purposes of the Limitation Act 1980, if necessary I should have held, for
the above reasons, that a reference to the Lands Tribunal is ‘an action to
recover’ compensation for compulsory purchase for the purposes of section 9 of
the Limitation Act 1980.
I end this judgment with a plea that the
law on this question be clarified as soon as possible. If my decision is not
appealed, the position should be clarified by legislation. It is obviously
highly undesirable that there should be uncertainty as to the law and procedure
on an important question affecting rights and obligations between public
authorities and the private citizen.
Declaration accordingly.